Proposal to give Calif. hospitals more time for earthquake retrofits stirs controversy

Codes and Standards

Proposal to give Calif. hospitals more time for earthquake retrofits stirs controversy

State hospital association says 2030 deadline should be extended.


By Peter Fabris, Contributing Editor | July 21, 2021

A proposal in the California Assembly to extend a deadline for hospitals to make seismic retrofits has drawn sharp criticism from labor groups.

The controversy pertains to two requirements passed in the wake of the 1994 Northridge earthquake that destroyed many buildings in Southern California. Almost all of the state’s hospitals have already met the first requirement to meet standards that ensure buildings don’t collapse during a major quake. The second mandate is more costly for hospitals and more controversial.

It calls for hospitals to be able to remain operable and serve patients after a major quake by 2030. Nearly two-thirds of hospitals have yet to meet that goal. The California Hospital Association is asking for a seven-year extension as well as more limited scope. The association wants the rule to only apply to emergency facilities.

The legislature and Gov. Gavin Newsom are still working out details of the state’s $263 billion budget, two weeks after the new fiscal year began. The hospital provision is a major sticking point.

Related Stories

| Nov 16, 2012

Green building councils in 62 countries expect 60% of their work to be green by 2015

More than half of the respondents to a survey of members of the Green Building Council in 62 countries expect green projects to comprise 60% of their work by 2015.

| Nov 16, 2012

Voters approve fewer construction ballot measures in 2012 than in 2008

Voters passed fewer ballot measures related to construction projects this year than they did in 2008, according to an analysis by the Associated General Contractors of America.

| Nov 9, 2012

New ANSI/BIFMA standard adds point for lower formaldehyde emissions

The ANSI/BIFMA e3-2012 Furniture Sustainability Standard now includes an additional point for furniture products that meet a new, lower formaldehyde emissions limit.

| Nov 9, 2012

Higher bar on LEED may not be harder to reach

The U.S. Green Building Council expects to substantially revise LEED next year, requiring builders beginning in 2015 to take new and more-detailed steps to get buildings certified.

| Nov 9, 2012

CSI’s sustainability practice group offers webinar on EPA's WaterSense Program

The Construction Specification Institute’s sustainability practice group is offering a webinar Nov. 20 on EPA’s WaterSense Program, featuring Lynn Gilleland, drinking water specialist with EPA’s New England office.

| Nov 9, 2012

Mayor in Calif. wants to expedite permits for $1B worth of projects

The mayor of San Jose, Calif., plans to issue new construction permits worth an estimated $1 billion in the next six months to spur job creation and create revenue for the city.

| Nov 9, 2012

Jury awards N.Y. roofer $2 million for injuries after construction site fall

A roofing worker from Cortland County, N.Y., has been awarded $2 million in damages due to the injuries he sustained from a 60-foot fall at a dormitory construction site.

| Oct 31, 2012

Investigators look into crane severely damaged by Sandy in Manhattan

Investigators are examining a construction crane collapse atop a $1.5 billion luxury high-rise in midtown Manhattan due to high winds during Hurricane Sandy.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021