When Mortenson was charged with the 831,000-sf, 360-bed Exempla Saint Joseph Heritage Project in Denver, we found that a traditional, on-site linear building approach would have resulted in a schedule that did not meet the customer's needs.
To address the challenge, we leveraged prefabrication across all applicable components in the facility.
Below is an executive summary (the full report will be released soon) of the results from value-based cost-benefit analyses performed during this project on the most significant performance drivers for prefab (schedule, cost, and safety).
We are pleased to share these results with owners who are considering the merits and challenges of prefab, and we invite you to sign-up to be alerted when the full research report is available.
Related Stories
| Sep 28, 2011
Look who's coming to BD+C's Under-40 Leadership Summit
AEC industry "under-40 superstars" from top design and construction firms have signed up for BD+C's "Under-40 Leadership Summit."
| Sep 28, 2011
GBCI announces LEED fellow class of 2011
LEED Fellows represent green building industry's most accomplished professionals.
| Sep 28, 2011
Bradley sponsors design studio on intelligent buildings for UWM SARUP
The studio is taught by Gregory D. Thomson, assistant professor and co-director of the Institute for Ecological Design at UWM.
| Sep 23, 2011
Fire and hurricane rated glazed wall assemblies installed at multi-family residence in Florida
Fire and hurricane assemblies meet design and code requirements.
| Sep 23, 2011
ABI turns positive after four monthly declines
On the heels of a period of weakness in design activity, the Architecture Billings Index (ABI) took a sudden upturn in August.
| Sep 23, 2011
Under 40 Leadership Summit
Building Design+Construction’s Under 40 Leadership Summit takes place October 26-28, 2011 Hotel at the Monteleone in New Orleans. Discounted hotel rate deadline: October 2, 2011.