Prefab payback: Mortenson quantifies cost and schedule savings from prefabrication techniques

Prefab payback: Mortenson quantifies cost and schedule savings from prefabrication techniques

Value-based cost-benefit analysis of prefab approaches on the firm's 360-bed Exempla Saint Joseph Heritage Project shows significant savings for the Building Team. 


By Mortenson Construction | May 14, 2014
The contractor implemented advanced prefabrication measures on the 360-bed Exemp
The contractor implemented advanced prefabrication measures on the 360-bed Exempla Saint Joseph Heritage Project in Denver, incl

When Mortenson was charged with the 831,000-sf, 360-bed Exempla Saint Joseph Heritage Project in Denver, we found that a traditional, on-site linear building approach would have resulted in a schedule that did not meet the customer's needs. 

To address the challenge, we leveraged prefabrication across all applicable components in the facility.

Below is an executive summary (the full report will be released soon) of the results from value-based cost-benefit analyses performed during this project on the most significant performance drivers for prefab (schedule, cost, and safety).

We are pleased to share these results with owners who are considering the merits and challenges of prefab, and we invite you to sign-up to be alerted when the full research report is available.

 

Related Stories

| Dec 4, 2012

MKK’s Denver Human Services Eastside Building wins ACEC Excellence Award

MKK provided mechanical, plumbing and fire protection consulting services on this LEED-NC Gold project.

| Dec 4, 2012

Thornton Tomasetti opens new office in São Paulo, Brazil

The move to São Paulo is strategic and timely, as the country continues preparations for the 2014 World Cup and 2016 Olympic Games in Rio de Janeiro.

| Dec 4, 2012

Greenhorne & O’Mara signs letter of intent to join Stantec

Acquisitions of C3TS and Architecture 2000 also completed.

| Dec 4, 2012

Sto Corp. announces new distributor in the Carolinas

Company will now have coverage in several parts of North Carolina.

| Dec 4, 2012

Wirtz Beverage Illinois’ corporate headquarters completed

WBI Center, a new state-of-the-art facility, is designed by Ware Malcomb.

| Dec 4, 2012

Wagner joins Ghafari as Manager of Structural Engineering

Wagner comes to Ghafari from Walter P Moore, where he served as a principal, chaired the construction administration task force and led the design of numerous projects ranging in size from $10 million to $70 million.

| Dec 4, 2012

City of Gainesville to break ground on $33 million bus fleet maintenance and ops facility

The 140,000-sf facility will include dispatch, administrative and maintenance facilities.

| Nov 28, 2012

Project team to showcase design for first mixed-use retail center of its kind in Mexico City

Project reaching construction milestone, offering national model for urban development in Mexico.

| Nov 28, 2012

Cummins announces ratings classification for data center power systems

The Data Center Continuous ratings span the range of Cummins Power Generation’s high horsepower diesel generator sets, from 1 MW up to 2.5 MW, and will apply to both 50 Hz and 60 Hz configurations.

| Nov 28, 2012

Francis Cauffman appoints Stainbrook Director of Higher Education

Stainbrook has 16 years of experience as a strategic planner and urban designer working on complex projects on- and off-campus.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021