flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Prefab helps Valparaiso student residence project meet an ambitious deadline

Prefab helps Valparaiso student residence project meet an ambitious deadline

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University.


By Peter Fabris, Contributing Editor | November 7, 2014
Precast units from Coreslab Structures (left) being put in place at Valparaiso (
Precast units from Coreslab Structures (left) being put in place at Valparaiso (Ind.) Universitys new student residence. A bath

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University. The Lutheran-based institution completed a $27 million residence hall this past summer in which the structural elements were all precast. The modular bathroom pods were manufactured in and shipped from New Jersey.

“The primary motivation for prefab was an accelerated schedule,” says Andy Frank, Construction Executive with Mortenson Construction. Much of the structural and exterior work on the 85,000-sf building was completed before the start of winter, which was critical in an area prone to blinding snowfalls fed by nearby Lake Michigan. 

Manufacturing precast flooring planks and exterior panels that mimic limestone and brick masonry in a climate-controlled plant saved two to three months on the construction schedule, says Frank. The modular bathroom units, made by AmeriPOD, Dayton, N.J., shaved another month off the construction timetable of the suite-style residence hall. The time savings enabled the building to be ready for the fall 2014 semester.

FGM Architects and Mortenson collaborated on the design-build project using 3D BIM modeling to deliver a Collegiate Gothic structure that blends in with the prevailing campus architectural style. One of the critical factors in the construction process was leaving wall openings large enough for the bathroom pods to be transported from a staging area at one end of each floor through the building to their final position. Workers rolled the bathroom units through each floor to a preformed depression, where they were lowered by jacks into place.

Frank attributes the success of the prefab approach in part to the type of project. “When you have a large number of users involved in programming the building”—such as an academic building shared by multiple departments—“you’re going to need a longer design process,” he says. Housing projects tend be more suitable for prefab because they usually have a limited number of stakeholders—in the Valparaiso project, primarily residential life officials and some students.

 

Related Stories

| Dec 2, 2011

What are you waiting for? BD+C's 2012 40 Under 40 nominations are due Friday, Jan. 20

Nominate a colleague, peer, or even yourself. Applications available here.

| Dec 2, 2011

Legrand joins White House initiative to spur energy efficiency in commercial buildings

Company agrees to aggressive energy savings and reporting.

| Dec 2, 2011

Goody Clancy awarded Ohio State residential project

The project, which is focused on developing a vibrant on-campus community of learning for OSU undergraduates.

| Dec 1, 2011

Nauset Construction breaks ground on Massachusetts health care center

The $20 million project is scheduled to be completed by December 2012. 

| Dec 1, 2011

Ground broken on first LEED Platinum designed school house built by volunteers

Phoenix public school receives the generous gift of a state-of-the-art building for student and community use.

| Dec 1, 2011

VLK Architects’ office receives LEED certification

The West 7th development, which houses the firm’s office, was designed to be LEED for Core & Shell, which gave VLK the head start on finishing out the area for LEED Silver Certification CI.

| Nov 29, 2011

First EPD awarded to exterior roof and wall products manufacturer

EPD is a standardized, internationally recognized tool for providing information on a product’s environmental impact. 

| Nov 29, 2011

Suffolk Construction breaks ground on Boston residential tower

Millennium Place III is a $220 million, 256-unit development that will occupy a full city block in Boston’s Downtown Crossing.

| Nov 29, 2011

Report finds credit crunch accounts for 20% of nation’s stalled projects

Persistent financing crunch continues to plague design and construction sector.

| Nov 29, 2011

SB Architects completes Mission Hills Volcanic Mineral Springs and Spa in China

Mission Hills Volcanic Mineral Springs and Spa is home to the largest natural springs reserve in the region, and measures 950,000 sf.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021