Prefab helps Valparaiso student residence project meet an ambitious deadline

Prefab helps Valparaiso student residence project meet an ambitious deadline

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University.


By Peter Fabris, Contributing Editor | November 7, 2014
Precast units from Coreslab Structures (left) being put in place at Valparaiso (
Precast units from Coreslab Structures (left) being put in place at Valparaiso (Ind.) Universitys new student residence. A bath

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University. The Lutheran-based institution completed a $27 million residence hall this past summer in which the structural elements were all precast. The modular bathroom pods were manufactured in and shipped from New Jersey.

“The primary motivation for prefab was an accelerated schedule,” says Andy Frank, Construction Executive with Mortenson Construction. Much of the structural and exterior work on the 85,000-sf building was completed before the start of winter, which was critical in an area prone to blinding snowfalls fed by nearby Lake Michigan. 

Manufacturing precast flooring planks and exterior panels that mimic limestone and brick masonry in a climate-controlled plant saved two to three months on the construction schedule, says Frank. The modular bathroom units, made by AmeriPOD, Dayton, N.J., shaved another month off the construction timetable of the suite-style residence hall. The time savings enabled the building to be ready for the fall 2014 semester.

FGM Architects and Mortenson collaborated on the design-build project using 3D BIM modeling to deliver a Collegiate Gothic structure that blends in with the prevailing campus architectural style. One of the critical factors in the construction process was leaving wall openings large enough for the bathroom pods to be transported from a staging area at one end of each floor through the building to their final position. Workers rolled the bathroom units through each floor to a preformed depression, where they were lowered by jacks into place.

Frank attributes the success of the prefab approach in part to the type of project. “When you have a large number of users involved in programming the building”—such as an academic building shared by multiple departments—“you’re going to need a longer design process,” he says. Housing projects tend be more suitable for prefab because they usually have a limited number of stakeholders—in the Valparaiso project, primarily residential life officials and some students.

 

Related Stories

| Jan 31, 2012

Suffolk Construction to manage Lawrence & Memorial Hospital Cancer Center project in Waterford, Conn.

Leading construction management firm overseeing one of first healthcare projects in the country to utilize innovative IPD process.

| Jan 31, 2012

Perkins Eastman’s Miller appointed Chairman of the AIA International Committee

International expertise leveraged as global industry resource.

| Jan 31, 2012

KBE selected for school project in Waterbury, Conn.

Located adjacent to the existing elementary school, the $28 million, 82,000 s/f Pre-K to eighth Grade school is expected to host its first students in the fall of 2013.

| Jan 31, 2012

Construction Law Firm Allensworth & Porter, LLP adds May to the firm

Prior to joining Allensworth & Porter, May served as the staff attorney for the Texas Civil Justice League, and was responsible for drafting, analyzing, and tracking civil justice and business-related legislation during the 82nd Legislative Session. 

| Jan 31, 2012

Skanska USA Civil promotes Bradley to southeast general superintendent

In Bradley’s new position, he will manage field operations for all Skanska Civil projects in the southeast.

| Jan 30, 2012

Siemens and Air-Ex Team deliver building controls training to Mt. San Antonio College students

Siemens contributes training modules and technology to support hands-on courses.

| Jan 30, 2012

Hollister Construction Services to renovate 30 Montgomery Street in Jersey City, N.J.

Owner Onyx Equities hires firm to oversee comprehensive upgrades of office building.

| Jan 27, 2012

Caterpillar reports record sales and profit for 4Q and full-year 2011

Momentum carries into 2012 with sales and revenues outlook raised to $68 to $72 billion.

| Jan 27, 2012

Smith Seckman Reid opens two new offices

Smith Seckman Reid, Inc. (SSR), an engineering design and facility consulting firm, has opened two new offices, one in Chicago, the other in Washington, D.C.

| Jan 27, 2012

BRB Architects designs new campus center for Molloy College

Intended to be the centerpiece of the College’s transformation from a commuter college to a 24-hour learning community, the “Public Square” will support student life with spaces such as a café, lounges, study rooms, student club space, a bookstore and an art gallery.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021