Prefab helps Valparaiso student residence project meet an ambitious deadline

Prefab helps Valparaiso student residence project meet an ambitious deadline

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University.


By Peter Fabris, Contributing Editor | November 7, 2014
Precast units from Coreslab Structures (left) being put in place at Valparaiso (
Precast units from Coreslab Structures (left) being put in place at Valparaiso (Ind.) Universitys new student residence. A bath

Few colleges or universities have embraced prefabrication more wholeheartedly than Valparaiso (Ind.) University. The Lutheran-based institution completed a $27 million residence hall this past summer in which the structural elements were all precast. The modular bathroom pods were manufactured in and shipped from New Jersey.

“The primary motivation for prefab was an accelerated schedule,” says Andy Frank, Construction Executive with Mortenson Construction. Much of the structural and exterior work on the 85,000-sf building was completed before the start of winter, which was critical in an area prone to blinding snowfalls fed by nearby Lake Michigan. 

Manufacturing precast flooring planks and exterior panels that mimic limestone and brick masonry in a climate-controlled plant saved two to three months on the construction schedule, says Frank. The modular bathroom units, made by AmeriPOD, Dayton, N.J., shaved another month off the construction timetable of the suite-style residence hall. The time savings enabled the building to be ready for the fall 2014 semester.

FGM Architects and Mortenson collaborated on the design-build project using 3D BIM modeling to deliver a Collegiate Gothic structure that blends in with the prevailing campus architectural style. One of the critical factors in the construction process was leaving wall openings large enough for the bathroom pods to be transported from a staging area at one end of each floor through the building to their final position. Workers rolled the bathroom units through each floor to a preformed depression, where they were lowered by jacks into place.

Frank attributes the success of the prefab approach in part to the type of project. “When you have a large number of users involved in programming the building”—such as an academic building shared by multiple departments—“you’re going to need a longer design process,” he says. Housing projects tend be more suitable for prefab because they usually have a limited number of stakeholders—in the Valparaiso project, primarily residential life officials and some students.

 

Related Stories

| May 1, 2014

First look: Cal State San Marcos's posh student union complex

The new 89,000-sf University Student Union at CSUSM features a massive, open-air amphitheater, student activity center with a game lounge, rooftop garden and patio, and ballroom space.

| May 1, 2014

Super BIM: 7 award-winning BIM/VDC-driven projects

Thom Mayne's Perot Museum of Nature and Science and Anaheim's new intermodal center are among the 2014 AIA TAP BIM Award winners. 

| May 1, 2014

Tight on space for multifamily? Check out this modular kitchen tower

The Clei Ecooking kitchen, recently rolled out at Milan's Salone de Mobile furniture fair, squeezes multiple appliances into a tiny footprint.

| May 1, 2014

Chinese spec 'world's fastest' elevators for supertall project

Hitachi Elevator Co. will build and install 95 elevators—including two that the manufacturer labels as the "world's fastest"—for the Kohn Pedersen Fox-designed Guangzhou CTF Finance Center. 

| Apr 30, 2014

Visiting Beijing's massive Chaoyang Park Plaza will be like 'moving through a urban forest'

Construction work has begun on the 120,000-sm mixed-use development, which was envisioned by MAD architects as a modern, urban forest.

| Apr 29, 2014

Best of Canada: 12 projects nab nation's top architectural prize [slideshow]

The conversion of a Mies van der Rohe-designed gas station and North Vancouver City Hall are among the recently completed projects to win the 2014 Governor General's Medal in Architecture. 

| Apr 29, 2014

USGBC launches real-time green building data dashboard

The online data visualization resource highlights green building data for each state and Washington, D.C.

| Apr 29, 2014

Big U in the Big Apple: New design to protect New York City's coastline

Bjarke Ingels' proposed design for the Rebuild by Design competition adapts a key design principle in ship building to improve urban flood protection.

| Apr 28, 2014

Welcome to the Hive: OVA designs wild shipping container hotel for competition

Hong Kong-based OVA envisions a shipping-container hotel, where rooms could be removed at will and designed by advertisers.

Smart Buildings | Apr 28, 2014

Cities Alive: Arup report examines latest trends in urban green spaces

From vertical farming to glowing trees (yes, glowing trees), Arup engineers imagine the future of green infrastructure in cities across the world.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021