From power plant to office: Ambler Boiler House conversion

From power plant to office: Ambler Boiler House conversion

The shell of a 19th-century industrial plant is converted into three levels of modern office space. 


By Julie Higginbotham, Senior Editor | October 9, 2013
Located adjacent to a regional rail stop and near good roads, Ambler Boiler Hous
Located adjacent to a regional rail stop and near good roads, Ambler Boiler House spent years as an abandoned, dilapidated industrial building. It now offers 48,000 sf of office space in a LEED Platinum facility. Photo: Don Pearse

Like many 19th-century industrial facilities, the Ambler Boiler House long ago outlived its initial use. Built in 1897 to generate power for an asbestos plant, the structure was abandoned when the owner folded after the Depression. In the early 2000s, Summit Realty Advisors bought the site, appreciating its proximity to a rail stop—Philadelphia is 40 minutes away by train—as well as good roads and utility services.

The 2008 crash delayed plans, but three years later, construction of an office complex began. Summit used creative financing, including state and county funds, to realize this speculative project in tough economic times.

Asbestos was remediated with the help of the Pennsylvania Department of Environmental Protection and state grants and loans. The endeavor required 760 man-hours of labor and the removal of 530 cubic yards of contaminated construction debris and waste. All that remained was a brick shell and steel roof trusses.

AMBLER BOILER HOUSE
Ambler, Pa.

 
Building Team 
Submitting firm: Heckendorn Shiles Architects 
Owner/developer: Summit Realty Advisors 
Owner’s representative: The AT Group 
Structural engineer: Elton & Thompson 
MEP engineer: PHY Engineers 
General contractor: Domus
 
General Information 
Size: 48,000 sf 
Construction cost: $16 million (core and shell) 
Construction time: 2011 to August 2013 
Delivery method: Design-bid-build

The former two-story plan entailed excessive floor-to-floor heights for offices, so the Building Team, led by Heckendorn Shiles Architects, inserted structural steel and concrete slabs to create three levels. Entryways and windows, many of which had been walled up, were reopened and infilled with high-efficiency store-front glazing. An iconic 140-foot smokestack was retained, and the original monitor roof profile, now equipped with translucent composite clerestories, enhances daylighting. Loft-style office spaces are characterized by references to the past, including exposed brick and reclaimed wood. However, the infrastructure is thoroughly modern. In particular, a 54-well geothermal system makes the building economical to operate, contributing to a LEED Platinum designation.

Since it opened in August 2012, the development has attracted a mix of tenants, including Summit Realty, Clutch (a mobile app designer), and AEC firm Core States Group. DiD, a boutique healthcare marketing agency, recently completed a two-story fit-out, with an open communicating stair and a “village green” common space. Ambler Boiler House—first an economic engine, then an eyesore—is most emphatically back in business.

Related Stories

Healthcare Facilities | Mar 16, 2015

Healthcare planning in a post-ACA world: 3 strategies for success

Healthcare providers are seeking direction on how to plan for a value-based world while still very much operating in a volume-based market. CBRE Healthcare's Curtis Skolnick offers helpful strategies. 

Resort Design | Mar 16, 2015

Giancarlo Zema Design Group unveils plans for semi-submerged resort in Qatar

The resort will have four semi-submerged hotels that look similar to super-yachts, each including 75 luxury suites with private terraces.

Mixed-Use | Mar 13, 2015

Dubai announces mega waterfront development Aladdin City

Planned on 4,000 acres in the Dubai Creek area, the towers will be covered in gold lattice and connected via air-conditioned bridges.

Contractors | Mar 13, 2015

Construction materials prices rise for first time in six months

The largest monthly gain in petroleum prices in over three years caused construction materials prices to expand 0.4% in February, ending a six-month streak when prices failed to rise, according to the Bureau of Labor Statistics.

High-rise Construction | Mar 12, 2015

Developers confirm Renzo Piano’s contribution in Sydney harbor overhaul

If the entire development is approved, One Sydney Harbour will be Piano’s second project in Australia.

High-rise Construction | Mar 12, 2015

Foster and Partners designs 'The One' in Toronto

Developer Sam Mizrahi worked with Foster and Partners and Core Architects to design Toronto's tallest skyscraper aside from the CN Tower, The One, which will house a luxury shopping mall and condos.

Contractors | Mar 12, 2015

Construction demand exploding in 2015, but costs complicate recovery

Raw materials and labor costs temper expectations for soaring profits.

Codes and Standards | Mar 12, 2015

Energy Trust of Oregon offers financial incentives for net-zero buildings

The organization is offering technical assistance along with financial benefits.

BIM and Information Technology | Mar 11, 2015

Google plans to use robots, cranes to manipulate modular offices at its new HQ

Its visions of “crabots” accentuate the search-engine giant’s recent fascination with robotics and automation.

Sports and Recreational Facilities | Mar 11, 2015

Foster + Partners wins bid for 2022 World Cup centerpiece stadium in Qatar

Norman Foster described the design as “an exciting step forward in stadium design—it will be the first to break the mold of the free-standing suburban concept, and instead anticipates the grid of this future city.” 

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021