From power plant to office: Ambler Boiler House conversion

From power plant to office: Ambler Boiler House conversion

The shell of a 19th-century industrial plant is converted into three levels of modern office space. 


By Julie Higginbotham, Senior Editor | October 9, 2013
Located adjacent to a regional rail stop and near good roads, Ambler Boiler Hous
Located adjacent to a regional rail stop and near good roads, Ambler Boiler House spent years as an abandoned, dilapidated industrial building. It now offers 48,000 sf of office space in a LEED Platinum facility. Photo: Don Pearse

Like many 19th-century industrial facilities, the Ambler Boiler House long ago outlived its initial use. Built in 1897 to generate power for an asbestos plant, the structure was abandoned when the owner folded after the Depression. In the early 2000s, Summit Realty Advisors bought the site, appreciating its proximity to a rail stop—Philadelphia is 40 minutes away by train—as well as good roads and utility services.

The 2008 crash delayed plans, but three years later, construction of an office complex began. Summit used creative financing, including state and county funds, to realize this speculative project in tough economic times.

Asbestos was remediated with the help of the Pennsylvania Department of Environmental Protection and state grants and loans. The endeavor required 760 man-hours of labor and the removal of 530 cubic yards of contaminated construction debris and waste. All that remained was a brick shell and steel roof trusses.

AMBLER BOILER HOUSE
Ambler, Pa.

 
Building Team 
Submitting firm: Heckendorn Shiles Architects 
Owner/developer: Summit Realty Advisors 
Owner’s representative: The AT Group 
Structural engineer: Elton & Thompson 
MEP engineer: PHY Engineers 
General contractor: Domus
 
General Information 
Size: 48,000 sf 
Construction cost: $16 million (core and shell) 
Construction time: 2011 to August 2013 
Delivery method: Design-bid-build

The former two-story plan entailed excessive floor-to-floor heights for offices, so the Building Team, led by Heckendorn Shiles Architects, inserted structural steel and concrete slabs to create three levels. Entryways and windows, many of which had been walled up, were reopened and infilled with high-efficiency store-front glazing. An iconic 140-foot smokestack was retained, and the original monitor roof profile, now equipped with translucent composite clerestories, enhances daylighting. Loft-style office spaces are characterized by references to the past, including exposed brick and reclaimed wood. However, the infrastructure is thoroughly modern. In particular, a 54-well geothermal system makes the building economical to operate, contributing to a LEED Platinum designation.

Since it opened in August 2012, the development has attracted a mix of tenants, including Summit Realty, Clutch (a mobile app designer), and AEC firm Core States Group. DiD, a boutique healthcare marketing agency, recently completed a two-story fit-out, with an open communicating stair and a “village green” common space. Ambler Boiler House—first an economic engine, then an eyesore—is most emphatically back in business.

Related Stories

Healthcare Facilities | Dec 15, 2021

MEP design considerations for rural hospitals

Rural hospitals present unique opportunities and challenges for healthcare facility operators. Oftentimes, the infrastructure and building systems have not been updated for years and require significant improvements in order to meet today’s modern medical demands. Additionally, as these smaller, more remote hospitals are acquired by larger regional and national healthcare systems, the first step by new ownership is often to update and rehabilitate the building. But how can this be done thoughtfully, economically, and efficiently in ways that allow the engineering and facility staff to adapt to the changes? And how can the updates accurately reflect the specific needs of rural communities and the afflictions with which these areas most commonly face?

Architects | Dec 13, 2021

Dan Hart, FAIA, inaugurated AIA 2022 President

Dan Hart will be the AIA's 98th President.

Architects | Dec 13, 2021

MASS Design Group receives 2022 AIA Architecture Firm Award

The annual AIA Architecture Firm Award is the highest honor the AIA bestows on an architecture practice.

Architects | Dec 13, 2021

2022 AIA Gold Medal awarded to Angela Brooks and Lawrence Scarpa

The Gold Medal honors an individual or pair whose significant body of work has had a lasting influence on the theory and practice of architecture.

K-12 Schools | Dec 10, 2021

Trends in K-12 school design, with Dan Boggio and Melissa Turnbaugh of PBK

Dan Boggio and Melissa Turnbaugh of PBK, the largest K-12 design firm in the U.S.,  discuss the favorable market conditions and the latest trends in K-12 school design with BD+C's Rob Cassidy.    

Architects | Dec 9, 2021

Hoffmann Architects wins Connecticut American Institute of Architects Justice, Equity, Diversity & Inclusion Award

The AIA Connecticut J.E.D.I. Challenge, launched in November 2020, offers member firms the opportunity to commit to actions in each of the Challenge areas.

Giants 400 | Dec 5, 2021

2021 Justice Facility Sector Giants: Top architecture, engineering, and construction firms in the U.S. justice facility/public safety sector

Turner Construction, DLR Group, AECOM, and Stantec top BD+C's rankings of the nation's largest architecture, engineering, and construction firms for justice facility/public safety buildings work, including correctional facilities, fire stations, jails, police stations, and prisons, as reported in the 2021 Giants 400 Report.

Giants 400 | Dec 3, 2021

2021 Hotel Sector Giants: Top architecture, engineering, and construction firms in the U.S. hospitality sector

Gensler, Jacobs, Suffolk Construction, and WATG top BD+C's rankings of the nation's largest hotel sector architecture, engineering, and construction firms, as reported in the 2021 Giants 400 Report.

Architects | Nov 29, 2021

LRK Names Tony Pellicciotti ‘Managing Principal’ of firm

Pellicciotti is one of LRK’s fourteen principals representing its markets in Memphis, Dallas, Philadelphia, Orlando/Celebration, New Orleans, Baton Rouge, Little Rock, and Princeton.

Architects | Nov 23, 2021

HMC names new Director of Design

James Krueger will oversee design and lead strategies to improve the impact of HMC’s work.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021