flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Power of IPD: Is integrated project delivery truly a transformative delivery model?

Power of IPD: Is integrated project delivery truly a transformative delivery model?

Now that many of the first-generation IPD projects have been completed, CBRE Healthcare's Tim McCurley and Stephen Powell ponder the lessons learned and pros and cons of the industry's newest delivery model. 


By Tim McCurley & Stephen Powell, CBRE Healthcare | June 23, 2014
Photo Credit: Mark Ahsmann, Wikimedia Commons.
Photo Credit: Mark Ahsmann, Wikimedia Commons.

In 2007, the seemingly new term Integrated Project Delivery (IPD) was making its way through the inner circles of contractors, architects and owners. IPD was developed as a method to enhance lagging efficiencies in the construction industry. During this time, it was no secret that major capital projects were a high risk endeavor, potentially wrought with problems, cost overruns, finger pointing and backstabbing. Furthermore, relationships began quickly deteriorating, problems ensued and the building owners were left holding the bag.

IPD was the method that was going to transform the construction industry into a model of efficiency and teamwork. Now, after approximately seven years, many of the “beta test” projects have been completed using the IPD Model. What have we learned? And is it truly a transformative delivery model?

Is it relational?

IPD is billed as being a relational delivery method due to the Integrated Form of Agreement (IFOA) or tri-party contract which provides financial incentive to mitigate risk. This is a true statement from a contracting stance. Many IPD contracts are developed to hold the project team members accountable when dealing with project risks.

This is helpful to the lower tiered subcontractors and consultants who, in a traditional process, would usually bear the most risk in project issues. In an IPD process, teams are incentivized by dealing with these issues quickly in order to get them completed in the most efficient and cost-effective manner. If this doesn’t happen, it will increase costs which will in turn increase risks to their own incentives and profits. 

Regardless of the delivery model, it is still impossible to contract trust. What held true in a traditional project still holds true in IPD. Teams must be able to trust one another. The IPD team could possibly be the biggest factor in determining the success of a project. CBRE Healthcare has facilitated engagements where contractors, architects and owners believe they are ready for IPD only to find themselves slipping right back into traditional project delivery methods. Just saying you are using IPD does not make it true. The attitude and culture must be sincere to ensure success.

Is it collaborative?

For most project teams, collaboration is one of the biggest changes and challenges from a traditional method. Architects and planners no longer act alone in the early design process. Contractors find themselves participating in conversations from the design intent of a patient room to a clock's location on a given wall. Initially, this interaction can be awkward and tricky. Establishing a process early in the initiation phase will ensure team members are acclimated to their new roles and are confident in their participation. Architects and contractors come to rely on the new partnership that fosters accountability within the parameters that have been established.

Is it Lean?

IPD was initially born out of Lean Methodologies. The main element of Lean that applies to IPD is the elimination of waste and duplication. One objective in eliminating waste is to avoid multiple entities creating different iterations of the same drawing. Building Information Modeling (BIM) is a useful tool in achieving this goal.

Imagine for a moment the traditional design to final product process. First, a designer creates a set of drawings and specifications for a design element. Then, it’s sent to a contractor(s) and they establish a price on the design. Next, the contractor must send a set of drawings and information back to the designer (known as a submittal) to be checked for accuracy and to ensure the contractor understands the design. Rarely does the submittal process end there. For a variety of reasons, there are usually changes and redesign. This means more drawing iterations, detail changes and mistakes.

The use of BIM in construction is revolutionizing the industry and combined with IPD it drastically improves the process as the designer and contractor are in one room working on the same building element. This allows for timely modifications due to design changes/enhancements or correcting design clashes/conflicts all while never changing “hands” or being printed.

Thanks to this process, when the final design is complete, the confidence level is extremely high, leading to another revolution in the construction industry: pre-manufacturing. Many other types of Lean Methodologies are seeing enormous success within construction in general. Combining Lean Methodologies with IPD makes for an even better process.

What Have We Learned?

Having been involved in numerous IPD projects, we have found that there are many factors that can impact success. Some of the most important, whether structured through an IFOA or merely operating in a collaborative environment (IPD “lite”), are team selection, team member experience, managing team member involvement and project size.

In order to have success on any project, specifically IPD, properly implementing the launch phase is critical. Owners not aligned in their overall strategies risk potential delays and setbacks. Probably, the most important step at this phase is team selection. A well-thought-out Request for Integrated Team (RFIT) will go a long way to ensuring success.

 

 

One of the key elements of the RFIT process is allowing teams to self-select/assemble. Though this concept may seem foreign, it provides owners confidence in knowing that their selected team has a history of working together, is aligned along common goals, and has a culture conducive to collaboration. We have seen it time and again: forced marriages rarely produce desired outcomes. Therefore, it is important for the owners to abandon past practices and external influences to enable the best team to rise to the top.

It is also a good idea to have a series of planned interactions with the top candidates prior to awarding the project. This will allow the owner to determine if each team can truly deliver on their claims and work well together. For example, the top candidates can evaluate the current program elements/budget and present their findings as a part of the selection process. Don’t set up anything too specific. Challenge the teams to identify solutions and not merely react to a set of guidelines.

A legitimate concern that most have upon engaging in IPD is whether the team truly has the required knowledge base to deliver the project. It seems these days that everyone claims to have IPD experience. But just saying so doesn’t make it true.

While architects and prime contractors may be well-versed in IPD methodology, subcontractors and consultants may not have the necessary experience and could potentially be a burden to the team. Be sure to truly investigate team claims and talk to references. Specifically ask about the collaborative nature of the team and their interactions with the referring staff. The contractors with the most experience will have developed a team of subs with whom they have proven success.

Contractors have found themselves in a much expanded role due to IPD. Their involvement has greatly increased as they are now engaged at the onset of the project. While this absolutely has value to the end result, ensuring a balance in their involvement is paramount to successfully transitioning from design to construction. The contractor is a large contributor in the success of maintaining IPD through the construction phase. If their commitment fades, it will inevitably lead projects back down a traditional delivery path.

And finally, not only does IPD work on large capital projects, but it can benefit small projects as well. During the early IPD days, it was noted that the process would only work on large construction projects. This was mainly due to the insurance structure that was required. Additionally, it was thought the early investment in resources from the contractor would not be cost-effective on a small project. However, we are seeing IPD implemented on smaller projects, and it’s a real testament to the fact that early investment in planning can pay off with any project. Contractors, and more importantly subcontractors, are finding value in the fact that they no longer have to budget for potential risk.

Conclusion

Recently, CBRE Healthcare polled participants of an ongoing project to determine how many team members had actually been involved in an IPD project. Interestingly enough, three team members were not even familiar with the traditional approach as they had never worked on anything but IPD projects. The construction industry is experiencing a paradigm shift. Owners are now realizing the benefits of Lean philosophies and IPD is the approach that delivers results. As the initial IPD projects come to completion, significant success stories are being communicated.

Capital project delivery methods may still have a ways to go in achieving efficiency, but, as the industry continues to evolve, we believe IPD is a step in the right direction. Everything is changing in project delivery. Are you onboard?

About the Authors
Tim McCurley is a Principal Consultant and Stephen Powell is a Senior Consultant at CBRE Healthcare.

Related Stories

Sponsored | Reconstruction & Renovation | Jan 25, 2022

Concrete buildings: Effective solutions for restorations and major repairs

Architectural concrete as we know it today was invented in the 19th century. It reached new heights in the U.S. after World War II when mid-century modernism was in vogue, following in the footsteps of a European aesthetic that expressed structure and permanent surfaces through this exposed material. Concrete was treated as a monolithic miracle, waterproof and structurally and visually versatile.

Urban Planning | Jan 25, 2022

Retooling innovation districts for medium-sized cities

This type of development isn’t just about innovation or lab space; and it’s not just universities or research institutions that are driving this change.

Sponsored | Resiliency | Jan 24, 2022

Norshield Products Fortify Critical NYC Infrastructure

New York City has two very large buildings dedicated to answering the 911 calls of its five boroughs. With more than 11 million emergency calls annually, it makes perfect sense. The second of these buildings, the Public Safety Answering Center II (PSAC II) is located on a nine-acre parcel of land in the Bronx. It’s an imposing 450,000 square-foot structure—a 240-foot-wide by 240-foot-tall cube. The gleaming aluminum cube risesthe equivalent of 24 stories from behind a grassy berm, projecting the unlikely impression that it might actually be floating. Like most visually striking structures, the building has drawn as much scorn as it has admiration. 

Coronavirus | Jan 20, 2022

Advances and challenges in improving indoor air quality in commercial buildings

Michael Dreidger, CEO of IAQ tech startup Airsset speaks with BD+C's John Caulfield about how building owners and property managers can improve their buildings' air quality.

Architects | Jan 17, 2022

OSPORTS adds Robert Hayes to lead operational and business development efforts

Hayes will guide the OSPORTS organization in its mission to offer a unique perspective to designing world-class facilities.

Architects | Jan 13, 2022

Hollywood is now the Stream Factory

Insatiable demand for original content, and its availability on a growing number of streaming platforms, have created shortages — and opportunities — for new sound stages.

Architects | Jan 13, 2022

Robert Eisenstat and Paul Mankins receive 2022 AIA Award for Excellence in Public Architecture

The award recognizes architects, public officials, or other individuals who design distinguished public facilities and advocate for design excellence.

3D Printing | Jan 12, 2022

Using 3D-printed molds to create unitized window forms

COOKFOX designer Pam Campbell and Gate Precast's Mo Wright discuss the use of 3D-printed molds from Oak Ridge National Lab to create unitized window panels for One South First, a residential-commercial high-rise in Brooklyn, N.Y.

Engineers | Jan 12, 2022

Private equity: An increasingly attractive alternative for AEC firm sellers

Private equity firms active in the AEC sector work quietly in the background to partner with management, hold for longer periods, and build a win-win for investors and the firm. At a minimum, AEC firms contemplating ownership transition should consider private equity as a viable option. Here is why.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021