U.S. contractors lost between $30 billion and $40 billion in 2022 due to poor labor productivity, according to a new report from FMI Corp. The survey focused on self-performing contractors, those typically engaged as a trade partner to a general contractor.
The productivity problem seems to be getting worse, the report says. Almost half (45%) of respondents to a survey conducted during the summer saw declining labor productivity, with only 23% noting improvement.
“Labor is the largest, riskiest, yet most controllable variable cost,” the report says. “Managed well, labor productivity can significantly improve bottom-line margins. Managed poorly, labor overruns, or exceeding labor budgets, can wipe out contractor profitability.”
![Poor productivity cost U.S contractors as much as $40 billion last year](/sites/default/files/inline-images/Poor%20productivity%20cost%20U.S%20contractors%20as%20much%20as%20%2440%20billion%20last%20year.png)
Respondents say 11% to 15% of field labor costs are wasted or unproductive, but better management practices could reduce labor spending by 6% to 10%, or $15 billion to $25 billion. That level of improvement would result in a 50% to 100% boost to profitability.
Respondents also cited low-quality design and construction documents, outdated and unrealistic schedules, lack of coordination with general contractors, and change order
inefficiencies as key concerns.
Related Stories
| Apr 16, 2012
$80 million in export financing for solar project in India
The project, “Rajasthan Sun Technique Energy Private Limited,” is a subsidiary of Reliance Power and is being co-financed by the Asian Development Bank and FMO, the Dutch development bank.
| Apr 13, 2012
Arcadis merges with Davis Langon & Seah
Merger will help company expand business in Asia.
| Apr 13, 2012
Goettsch Partners designs new music building for Northwestern
The showcase facility is the recital hall, an intimate, two-level space with undulating walls of wood that provide optimal acoustics and lead to the stage, as well as a 50-foot-high wall of cable-supported, double-skin glass
| Apr 13, 2012
Best Commercial Modular Buildings Recognized
Judges scored building entries on a number of criteria including architectural excellence, technical innovation, cost effectiveness, energy efficiency, and calendar days to complete, while marketing pieces were judged on strategy, implementation, and quantifiable results. Read More
| Apr 12, 2012
Solar PV carport, electrical charging stations unveiled in California
Project contractor Oltman Construction noted that the carport provides shaded area for 940 car stalls and generates 2 MW DC of electric power.
| Apr 11, 2012
Shawmut appoints Tripp as business development director
Tripp joined Shawmut in 1998 and previously held the positions of assistant superintendent, superintendent, and national construction manager.
| Apr 11, 2012
Corgan & SOM awarded contract to design SSA National Support Center
The new SSA campus is expected to meet all Federal energy and water conservation goals while achieving LEED Gold Certification from the United States Green Building Council.
| Apr 11, 2012
C.W. Driver completes Rec Center on CSUN campus
The state-of-the-art fitness center supports university’s goal to encourage student recruitment and retention.
| Apr 10, 2012
JE Dunn completes two medical office buildings at St. Anthony’s Lakewood, Colo. campus
Designed by Davis Partnership Architects, P.C., Medical Plaza 1 and 2 are four-story structures totaling 96,804-sf and 101,581-sf respectively.