Plans to make over New York’s aging LaGuardia Airport are revealed

Airports

Plans to make over New York’s aging LaGuardia Airport are revealed

The complete redesign, devised by a panel of experts, would unify terminals, relieve ground traffic congestion, and install state-of-the-art amenities. 


By John Caulfield, Senior Editor | July 28, 2015
Plans to make over New York’s aging LaGuardia Airport are revealed

Construction on the first half of the new unified terminal is expected to be a $4 billion project. It will be managed by LaGuardia Gateway Partners, a new public private partnership chosen by the Port Authority of New York and New Jersey to build the project. Renderings: Port Authority of New York and New Jersey

The Board of Directors for Port Authority of New York and New Jersey is expected to give its final OK early next year to start the first half of construction on the rebuilding of New York’s LaGuardia Airport.

On Monday, New York Gov. Andrew Cuomo, with Vice President Joe Biden at his side, unveiled the airport’s comprehensive redesign, devised by a panel of architects, engineers, planners, and lawmakers that was chaired by Dan Tishman, vice chairman of AECOM Technology and chairman and CEO of Tishman Realty and Construction.

The panel’s report is an amalgam of the top design submissions presented by New York-based Dattner Architects, PRESENT Architecture, and SHoP Architects. It was not clear, though, whether any of these firms will end up being the designer on this project.

The panel’s vision calls for transforming the 76-year-old airport into a unified, single terminal with transportation access.

The plan would alleviate vehicular congestion that continues to plague this airport, which served nearly 27 million passengers in 2014.

The first half of this project, which is projected to cost  between $3.6 billion and $4 billion, is expected to take 18 months to complete and be open to passengers in 2019.

 

 

The second half of the new unified terminal would be executed by Delta Air Lines, whose plans to redevelop its terminals are expected to follow the same timeline as the first half of the construction.

LaGuardia, which once fancied itself as “the air gateway to America,” has deteriorated into one of the country’s most dilapidated and overburdened major airports. Its redesign would include the following:
• Demolish Terminal B—the 50-year-old Central Terminal—and thoroughly redevelop Terminals C and D to build a unified airport terminal to form a complete, efficient, and appealing experience for passengers;
• Build the new unified terminal 600 feet closer to the Grand Central Parkway coupled with an island-gate system that will create nearly two miles additional aircraft taxiways for better aircraft circulation and reduce gate delays that are frustrating for passengers and expensive for airlines;
• Appealing and significant terminal architecture with high ceilings, expansive natural lighting, and openness, designed so passengers intuitively understand the airport’s layout; automated tram to provide passengers with easier movement between the airport’s terminals;
• Business and conference center capabilities to meet the needs of the business traveler and local businesses;
• A sustainable and resilient airport that minimizes energy consumption, reduces harmful emissions, and protects critical infrastructure to keep the airport operational during a flood event;
• A design that accommodates a potential hotel, as well as future growth at the airport; and
• A Marine Air Terminal that is better integrated with the main airport via an automated tram or some other form of reliable and convenient mode of transportation.

The airport would also be designed to accommodate a future AirTrain that would bring passengers and visitors to a subway station in Queens. Ferry service to the Marine Air Terminal and, if feasible, to the east end of the airport, could be available. And improved road configuration would reduce congestion on the surrounding roadway network, including the Grand Central Parkway.

To assure accountability and progress of this project, the city is retaining a Master Planning firm (which it did not identify) to advise the Port Authority and the Governor, to translate the panel’s recommendations into an implementable master plan, and to coordinate airport development for the long-term. The Port Authority will establish a board committee to oversee airport development and implementation of the master plan.

The project is being financed and executed through a public-private partnership with LaGuardia Gateway Partners, a consortium that includes the giant contractor Skanska. It is projected to create 8,000 direct jobs and 10,000 indirect jobs.

 

Tags

Related Stories

| Jul 18, 2013

Top Federal Government Sector Construction Firms [2013 Giants 300 Report]

Clark Group, PCL, Hensel Phelps top Building Design+Construction's 2013 ranking of the largest federal government sector contractor and construction management firms in the U.S.

| Jul 18, 2013

Top Federal Government Sector Engineering Firms [2013 Giants 300 Report]

Fluor, URS, AECOM top Building Design+Construction's 2013 ranking of the largest federal government sector engineering and engineering/architecture firms in the U.S.

| Jul 18, 2013

Top Federal Government Sector Architecture Firms [2013 Giants 300 Report]

HOK, SmithGroupJJR, PageSoutherlandPage top Building Design+Construction's 2013 ranking of the largest federal government sector architecture and architecture/engineering firms in the U.S.

| Jul 18, 2013

Top Government Sector Construction Firms [2013 Giants 300 Report]

Clark Group, Turner, PCL head Building Design+Construction's 2013 ranking of the largest government sector contractors and construction management firms in the U.S.

| Jul 18, 2013

Top Government Sector Engineering Firms [2013 Giants 300 Report]

Fluor, URS, AECOM top Building Design+Construction's 2013 ranking of the largest government sector engineering and engineering/architecture firms in the U.S.

| Jul 18, 2013

Top Government Sector Architecture Firms [2013 Giants 300 Report]

Stantec, HOK, HDR top Building Design+Construction's 2013 ranking of the largest government sector architecture and architecture/engineering firms in the U.S.

| Jul 18, 2013

GSA regains stature under Tangherlini, who looks to trim its holdings, cut energy costs [2013 Giants 300 Report]

Over the past 15 months, Acting GSA Administrator Dan Tangherlini has done a creditable job of restoring the agency’s standing with Congress and the public.

| Jul 2, 2013

LEED v4 gets green light, will launch this fall

The U.S. Green Building Council membership has voted to adopt LEED v4, the next update to the world’s premier green building rating system.

| Jul 1, 2013

Report: Global construction market to reach $15 trillion by 2025

A new report released today forecasts the volume of construction output will grow by more than 70% to $15 trillion worldwide by 2025.

| Jun 28, 2013

Building owners cite BIM/VDC as 'most exciting trend' in facilities management, says Mortenson report

A recent survey of more than 60 building owners and facility management professionals by Mortenson Construction shows that BIM/VDC is top of mind among owner professionals. 

boombox1
boombox2
native1

More In Category

Airports

SOM unveils ‘branching’ structural design for new Satellite Concourse 1 at O’Hare Airport

The Chicago Department of Aviation has revealed the design for Satellite Concourse 1 at O’Hare International Airport, one of the nation’s business airports. Designed by Skidmore, Owings & Merrill (SOM), with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA), and Arup, the concourse will be the first new building in the Terminal Area Program, the largest concourse area expansion and revitalization in the airport’s almost seven-decade history. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021