Over budget Homeland Security headquarters project may be canceled

Over budget Homeland Security headquarters project may be canceled

Congressional support lacking for additional funds


By Peter Fabris, Contributing Editor | June 5, 2014
Under the original plan, the complex was scheduled to be finished as early as th
Under the original plan, the complex was scheduled to be finished as early as this year for less than $3 billion. But only a Coa

A massive new headquarters for the Department of Homeland Security is more than $1.5 billion over budget, 11 years behind schedule, and may never be completed.

When it was first proposed, the development was said to be critical for national security and the revitalization of Southeast Washington. The project on the grounds of the former St. Elizabeth’s Hospital would centralize the department’s operations. More than 50 historic buildings would be renovated and new ones erected.

Under the original plan, the complex was scheduled to be finished as early as this year for less than $3 billion. But only a Coast Guard building has been completed, with the rest of the grounds remaining undeveloped. The budget has inflated to $4.5 billion, with completion pushed back to 2026.

Neither Congressional Republicans nor Democrats have given the project much support, and the Obama Administration hasn’t made the project a priority, the Washington Post reported.

A revised administration plan with anticipated completion in 2026 was given to Congress last year, requiring about $280 million a year. It got only $190 million in 2014.

(http://www.washingtonpost.com/politics/planned-homeland-security-headquarters-long-delayed-and-over-budget-now-in-doubt/2014/05/20/d0df2580-dc42-11e3-8009-71de85b9c527_story.html)

Related Stories

Codes and Standards | Mar 5, 2019

Persistent flooding having economic impact on coastal cities

Atlantic City, Annapolis among communities affected.

Codes and Standards | Mar 1, 2019

$1 billion Boston hospital project to include extensive disaster resiliency features

Mass. General expansion will be designed for four days of shelter in place.

Codes and Standards | Mar 1, 2019

U.S. cities have become more dangerous for bicyclists and pedestrians

Reduced speed limits, traffic calming, better education seen as keys to improvement.

Codes and Standards | Feb 28, 2019

High-income renters now the fastest-growing housing market segment

Growth is fastest in mid-sized cities with strong economies.

Codes and Standards | Feb 27, 2019

Katerra launches software platform for ‘entire lifecycle of the building process’

Firm is accepting industry applicants to test the product.

Codes and Standards | Feb 26, 2019

AAMA updates two specifications for test methods related to seismic drift

For evaluating window wall, curtain wall and storefront systems.

Codes and Standards | Feb 21, 2019

Researchers develop software that can calculate potential solar energy yield at any location

Accounts for dynamic shading from trees, buildings and other structures.

Codes and Standards | Feb 20, 2019

Hospitals not making much progress in reducing their carbon footprint

Energy benchmarking survey shows flat emissions pattern over past 20 years.

Codes and Standards | Feb 15, 2019

Super Bowl stadium helps alleviate Atlanta’s flood problems

Capacity to store more than 2 million gallons of storm water on site.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021