Over budget Homeland Security headquarters project may be canceled

Over budget Homeland Security headquarters project may be canceled

Congressional support lacking for additional funds


By Peter Fabris, Contributing Editor | June 5, 2014
Under the original plan, the complex was scheduled to be finished as early as th
Under the original plan, the complex was scheduled to be finished as early as this year for less than $3 billion. But only a Coa

A massive new headquarters for the Department of Homeland Security is more than $1.5 billion over budget, 11 years behind schedule, and may never be completed.

When it was first proposed, the development was said to be critical for national security and the revitalization of Southeast Washington. The project on the grounds of the former St. Elizabeth’s Hospital would centralize the department’s operations. More than 50 historic buildings would be renovated and new ones erected.

Under the original plan, the complex was scheduled to be finished as early as this year for less than $3 billion. But only a Coast Guard building has been completed, with the rest of the grounds remaining undeveloped. The budget has inflated to $4.5 billion, with completion pushed back to 2026.

Neither Congressional Republicans nor Democrats have given the project much support, and the Obama Administration hasn’t made the project a priority, the Washington Post reported.

A revised administration plan with anticipated completion in 2026 was given to Congress last year, requiring about $280 million a year. It got only $190 million in 2014.

(http://www.washingtonpost.com/politics/planned-homeland-security-headquarters-long-delayed-and-over-budget-now-in-doubt/2014/05/20/d0df2580-dc42-11e3-8009-71de85b9c527_story.html)

Related Stories

Codes and Standards | Sep 17, 2020

Spate of energy code appeals could hamper efficiency progress

Construction and fossil fuel interests oppose portions of latest model energy code.

Codes and Standards | Sep 16, 2020

Heat pumps are the future for hot water

Sustainability policies will drive trend.

Codes and Standards | Sep 15, 2020

Taller timber buildings approved in National Fire Protection Association code

Ensures compatibility with the International Building Code.

Codes and Standards | Sep 14, 2020

Relocation of neighborhoods, the next step in U.S. flood strategy, is underway

Repeated rebuilding after successive floods now seen as bad policy.

Codes and Standards | Sep 10, 2020

Fannie Mae programs provide incentives for multifamily solar

Affordable housing projects can find PV installations to be cost-effective.

Codes and Standards | Sep 9, 2020

Corporate pledges accelerate net-zero building movement

World Green Building Council drives goal of net-zero carbon emissions by 2050.

Codes and Standards | Sep 8, 2020

Study will examine elevator airflow amid COVID-19 pandemic

Researchers to investigate risk of airborne transmission.

Codes and Standards | Sep 4, 2020

Updated selection, application guide for plastic glazed skylights, sloped glazing released

Part of suite of skylight documents by Fenestration and Glazing Industry Alliance.

Codes and Standards | Sep 3, 2020

Turner Construction takes strong stand against racism

Shuts down work sites for anti-bias training.

Codes and Standards | Sep 2, 2020

California releases guide for state water policy

Water Resilience Portfolio is roadmap for meeting water needs as climate changes.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021