A massive new headquarters for the Department of Homeland Security is more than $1.5 billion over budget, 11 years behind schedule, and may never be completed.
When it was first proposed, the development was said to be critical for national security and the revitalization of Southeast Washington. The project on the grounds of the former St. Elizabeth’s Hospital would centralize the department’s operations. More than 50 historic buildings would be renovated and new ones erected.
Under the original plan, the complex was scheduled to be finished as early as this year for less than $3 billion. But only a Coast Guard building has been completed, with the rest of the grounds remaining undeveloped. The budget has inflated to $4.5 billion, with completion pushed back to 2026.
Neither Congressional Republicans nor Democrats have given the project much support, and the Obama Administration hasn’t made the project a priority, the Washington Post reported.
A revised administration plan with anticipated completion in 2026 was given to Congress last year, requiring about $280 million a year. It got only $190 million in 2014.
Related Stories
Codes and Standards | Nov 9, 2016
NRMCA updates environmental impacts of concrete
The EPD now includes 88 companies, 72 mixes.
Codes and Standards | Nov 9, 2016
Louisiana flood projections require urgent action, officials say
The 'no net loss’ prediction now seems unrealistic.
Codes and Standards | Nov 8, 2016
American Concrete Institute offers new guide for repair of concrete buildings
The guide provides assistance on assessment and rehab.
Codes and Standards | Nov 7, 2016
The AISC prequalified seismic moment connection standard is now available
You can download the 2016 version for free.
Codes and Standards | Nov 4, 2016
Obama Administration makes a push for denser, more affordable cities
The administration calls for zoning code changes and other measures to create more housing.
Codes and Standards | Nov 3, 2016
OSHA proposes safety standards changes to reduce employer costs
The changes include clarification on excavation standard and reporting job-related hearing loss.
Codes and Standards | Nov 2, 2016
New resources available to reduce plug loads using advanced power strips
A tenant education program can boost efficiency in office buildings.
Codes and Standards | Oct 26, 2016
Design industry lagging in meeting AIA 2030 Commitment goals, says AIA
Only 4% of projects have met the 70% energy savings target.
Codes and Standards | Oct 25, 2016
Concerns over megaquake in Oregon provoke debate over school building standards
According to advocates, communities should consider increased resiliency.
Codes and Standards | Oct 24, 2016
Building energy codes projected to save $126 billion in energy costs from 2010-2040
Commercial and residential structures are both included in the total.