Open plenum vs. dropped ceiling: The debate over life cycle cost

Open plenum vs. dropped ceiling: The debate over life cycle cost

Calculating the tradeoffs between cost and performance can be tricky.


By C.C. Sullivan and Barbara Horwitz-Bennett, Contributing Editors | September 22, 2014

While suspended, lay-in ceilings have long been the norm in commercial design, the open-plenum ceiling has become trendy and economical, particularly in office and retail environments. However, calculating the tradeoffs between cost and performance can be tricky.

Very little data exists comparing suspended ceilings with open ceilings on the basis of cost and performance. The most recent study came from the Ceilings & Interior Systems Construction Association (www.cisca.org) five years ago. In the study, office and retail spaces were modeled in Chicago, Charlotte, Oklahoma City, Orlando, and Phoenix to reflect the differences in energy costs, climate, and installation costs. Initial construction costs were determined using RSMeans data; annual operating costs for HVAC, lighting, and maintenance were calculated according to Building Owners and Managers Association data.

The study found initial construction costs for suspended ceilings to be 15-22% higher in offices, and 4-11% higher in retail spaces. However, total energy savings for lay-in ceilings vs. open plenums were 9-10.3% in offices and 12.7-17% for retail. A 10.5% energy reduction qualifies buildings for a LEED EA credit, and a 14% reduction is good for two points.

 

 

The study attributed the energy performance advantage of suspended ceilings to the use of a return air plenum with low static pressures and fan horsepower vs. ducted air returns with higher static pressures and fan horsepower in open-plenum systems. In addition, return air plenums more efficiently remove heat from lighting systems and reduce the AC load. Suspended ceilings also offer about 20% higher light reflectance, thereby reducing lighting costs.

For more information, see: http://www.cisca.org/files/public/LCS_brochure_rev_9-08_lo-res.pdf.

Related Stories

| Jun 11, 2012

SimplexGrinnell highlights integrated suite of web-based technologies at NFPA Expo

eservices platform uses the power of the Internet to deliver more value to customers.

| Jun 11, 2012

Reed Construction announces new hire and promotion

Reed Construction hired Augie Insalaco as a project manager and promoted Matt Mahoney from project intern to project engineer.

| Jun 11, 2012

Hill International selected as CM for Porto Arabia Towers in Qatar

The complex is a mixed-use development featuring both residential and commercial properties.

| Jun 8, 2012

Living Building Challenge wins the 2012 Buckminster Fuller Challenge

The Living Building Challenge was chosen from a pool of 122 of entries from around the world.

| Jun 8, 2012

Nauset Construction completing sustainable dorm for Brooks School

Student input on green elements provides learning experience.

| Jun 8, 2012

Skyline Construction names Millitello president

Millitello is a 31-year veteran who has overseen the construction of campus-size projects.

| Jun 8, 2012

Allsteel names Kris Yates to head architectural products group

Yates is responsible for the start up, launch and ongoing sales and marketing of Allsteel’s new Beyond movable walls.

| Jun 8, 2012

Chestnut Hill College dedicates Jack and Rosemary Murphy Gulati complex

Casaccio Yu Architects designed the 11,300-sf fitness and social complex.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021