Many things—from a cup of coffee to tickets to a ballgame to a month’s rent—are expensive in New York City and San Francisco.
Add construction costs to the list. A report from the CBRE's Valuation & Advisory Services found that new office space core and shell construction costs are highest in the two coastal cities.
In New York, new office construction costs between $500 and $550 per sf, as of Q3 2015, the highest amount of the cities studied. San Francisco was second, with costs between $350 and $400 per sf.
Boston ($280 to $320 per sf), Seattle ($250-$300), Chicago ($240-$290), and Houston ($220-$270) finished the list.
“These numbers are for prices associated with the direct hard construction costs, and the ranges do not include acquisition costs or indirect soft costs,” said Robert Barone, of CBRE’s Valuation & Advisory Services, in a statement. “Indirect soft costs, which include costs for things such as architect/engineering fees, legal, administration, marketing, financing, FF&E and tenant improvements, can represent an additional 30% to 40% of the direct hard costs ranges.”
In addition, New York ($70.54 per sf, per annum, as of Q3) and San Francisco ($67.33) had the highest asking rents for offices, too.
Related Stories
| Aug 29, 2013
McCownGordon Construction plans Kansas office
In response to business growth and client demand, McCownGordon Construction of Kansas City announced today it is opening an office in the State of Kansas located in Manhattan, Kan.
| Aug 27, 2013
Industrial Sector Report [2013 Giants 300 Report]
Building Design+Construction's rankings of the nation's largest industrial sector design and construction firms, as reported in the 2013 Giants 300 Report.
| Aug 26, 2013
What you missed last week: Architecture billings up again; record year for hotel renovations; nation's most expensive real estate markets
BD+C's roundup of the top construction market news for the week of August 18 includes the latest architecture billings index from AIA and a BOMA study on the nation's most and least expensive commercial real estate markets.
| Aug 26, 2013
Chicago Bears kick off season at renovated Halas Hall
An upgraded locker room, expanded weight room, and updated dining room with an outdoor patio greeted the Chicago Bears when they arrived at Halas Hall for practice this month. The improvements are part of a major expansion and renovation of the Bears’ headquarters in Lake Forest, Ill., completed by Mortenson Construction in less than seven months.
| Aug 22, 2013
Energy-efficient glazing technology [AIA Course]
This course discuses the latest technological advances in glazing, which make possible ever more efficient enclosures with ever greater glazed area.
| Aug 22, 2013
Warehouse remake: Conversion project turns derelict freight terminal into modern office space [slideshow]
The goal of the Freight development is to attract businesses to an abandoned industrial zone north of downtown Denver.
| Aug 21, 2013
First look: Petersen Automotive Museum's dramatic facelift
One of the world's largest automotive museums unveils plans for a stunning, sculptured metal exterior and cutting-edge interior upgrades.
| Aug 20, 2013
40 Under 40 retrospective: ‘U40s’ take on continuing ed, snake’s blood
Every month we’ll be touching base with past 40 Under 40 honorees to see what’s been happening in their professional and personal lives since winning the award. This month: An accomplished author of test-prep books and an architect who headed to China when the American economy turned sour.
| Aug 20, 2013
Top Data Center Construction Firms [2013 Giants 300 Report]
DPR, Balfour Beatty, Holder head Building Design+Construction's 2013 ranking of the largest data center contractors and construction management firms in the U.S.
| Aug 20, 2013
First look: $550 million Billie Jean King National Tennis Center renovation
The United States Tennis Association has announced its plans for a sweeping transformation of the USTABillie Jean King National Tennis Center that will include the construction of two new stadiums, as well as a retractable roof over Arthur Ashe Stadium. The transformation will be implemented in three phases to begin at the conclusion of the 2013 US Open, with the goal of overall completion by the 2018 US Open.