flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence

Data Centers

North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence

Pre-leasing rates exceed 70% in primary North American data center markets


By CBRE | September 21, 2023
North American data center construction rises 25% to record high in first half of 2023, driven by growth of artificial intelligence  - Image by Pete Linforth from Pixabay
Image by Pete Linforth from Pixabay

Demand for data center space overshadowed economic uncertainty and concerns around power availability in the first half of the year. Construction of North American data centers is at an all-time high in part due to the continued growth of artificial intelligence, according to CBRE. 

CBRE’s latest North American Data Center Trends Report found there is 2,287.6 megawatts (MW) of data center supply currently under construction in primary markets, reaching a new all-time high with more than 70% already preleased. At the same time last year, there was 1,830.3 MW under construction. Companies are leasing space up to 36 months in advance of construction completion in anticipation of future demand and to secure data center space at current pricing. 

“Data center construction is at an all-time high, driven by strong demand from all users, including AI, hyperscale and enterprise,” said Pat Lynch, executive managing director for CBRE’s Data Centers Solution. “New and existing uses of artificial intelligence cases grew tremendously in the first half of the year, and we expect demand to remain strong with AI driving leasing opportunities in the second half of the year.” 

Absorption in the eight primary U.S. data center markets* remained resilient in H1 2023, totaling 468.8 MW despite challenges within the supply chain. While supply increased 19.2% year-over-year, vacancy remains near a record low of 3.3%. Strong demand paired with a lack of available power and extended timelines have kept asking rental rates climbing. Average primary market asking rents rose to $147.80 per kW/month from $127.50 (a 15.9% year-over-year increase). 

Top Data Center Construction Markets 

Northern Virginia remained the most active data center market in the first half of 2023 with 918 MW under construction. The market set a record low vacancy rate of 0.94% while power improvement projects are underway. Separately, Chicago recorded a 125% spike in under-construction activity - the largest increase among all U.S. data center markets. 

“Most major markets are grappling with power constraints, and developers are facing challenges within their supply chain, but it’s not slowing down the demand for data center space,” said Gordon Dolven, director of Americas Data Center Research at CBRE. “Data center operators are prioritizing power availability, rather than selecting markets based on traditional factors such as location, connectivity, water and land pricing.”

Top 10 most active data center construction markets
MarketH1 2023 Total InventoryH1 2023 Under Construction
Northern Virginia2,254.1 MW918 MW
Hillsboro248.4 MW267.3 MW
Silicon Valley410.7 MW125 MW
Chicago367.5 MW205 MW
Dallas-Fort Worth499.4 MW273.3 MW
Phoenix360 MW163.5 MW
Toronto291.3 MW99.6 MW
New York Tri-State177.5 MW99.9 MW
Atlanta271 MW235.6 MW
Montreal135.5 MW106.5 MW
 

Other market highlights include Dallas-Fort Worth, which saw the greatest year-over-year increase in absorption of 327%, jumping to 110.6 MW from 25.89 MW. Hillsboro also experienced the largest inventory growth of all primary markets, increasing to 248.4 MW from 139.4 MW (78% year-over-year growth). 

To view the full report, click here.

Related Stories

Data Centers | Feb 18, 2021

Arcari Cimini Architettura designs Data Center Floating Island

The concept looks to create an entire floating city centered around a data center.

Data Centers | Jan 21, 2021

The Weekly show, Jan 21, 2021: Data centers in a pandemic world, and LGBT certification for AEC firms

This week on The Weekly show, BD+C editors speak with AEC industry leaders about LGBT certification for architecture, engineering, and construction firms, and the current state of data centers in a pandemic world.

Giants 400 | Dec 16, 2020

Download a PDF of all 2020 Giants 400 Rankings

This 70-page PDF features AEC firm rankings across 51 building sectors, disciplines, and specialty services.

Data Centers | Dec 9, 2020

COVID-19 pandemic elevates data centers to key priority market for investors

But supply-chain and labor problems could slow deliveries, according to Turner & Townsend’s 2020 report that looks at 40 markets.

Giants 400 | Dec 3, 2020

2020 Data Center Giants: Top architecture, engineering, and construction firms in the U.S. data center facilities sector

Corgan, Jacobs, and Whiting-Turner Contracting Company top BD+C's rankings of the nation's largest data center facilities sector architecture, engineering, and construction firms, as reported in the 2020 Giants 400 Report.

Data Centers | Oct 26, 2020

Speed to market is biggest obstacle for burgeoning data center construction sector

Hyperscale and edge computing are driving growth in data center and mission critical facilities construction.

Data Centers | Sep 17, 2020

Data center provider Aligned links new financing to sustainability performance

One goal: 100% renewable energy consumption by 2024.

Data Centers | Jun 30, 2020

Facebook to build $800 million data center in DeKalb, Ill.

Mortenson Construction is the project’s general contractor.

Data Centers | May 8, 2020

Data centers as a service: The next big opportunity for design teams

As data centers compete to process more data with lower latency, the AEC industry is ideally positioned to develop design standards that ensure long-term flexibility. 

Giants 400 | Aug 28, 2019

Top 45 Data Center Construction Firms for 2019

Whiting-Turner, Turner, Holder, DPR, and Fortis top the rankings of the nation's largest data center sector contractors and construction management firms, as reported in Building Design+Construction's 2019 Giants 300 Report.

boombox1
boombox2
native1

More In Category

Data Centers

What’s next for data center design in 2024

Nuclear power, direct-to-chip liquid cooling, and data centers as learning destinations are among the emerging design trends in the data center sector, according to Scott Hays, Sector Leader, Sustainable Design, with HED. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021