No significant settling reported in preliminary finding


By Peter Fabris, Contributing Editor | September 15, 2023
NIST investigation of Champlain Towers South collapse indicates no sinkhole Photo courtesy NIST
Photo courtesy NIST

Investigators from the National Institute of Standards and Technology (NIST) say they have found no evidence of underground voids on the site of the Champlain Towers South collapse, according to a new NIST report.

The team of investigators have studied the site’s subsurface conditions to determine if sinkholes or excessive settling of the pile foundations might have caused the collapse. They have found no such evidence to support that potential cause.

Preliminary evaluation of data indicates about one quarter of an inch or less of settling in the pile foundations supporting the pool deck structure and basement. This would have had minimal impact on the pool deck structure, NIST says.

“Understanding exactly what caused this collapse is taking meticulous investigation and the collection of copious amounts of evidence and information,” said Joannie Chin, director of NIST’s Engineering Laboratory. “Our team members are dedicated to unraveling the complexities of this tragic event, and their rigorous research and analysis will not only help us understand the likely technical cause of the collapse but will improve the safety of our communities.”

The team’s preliminary evaluation of physical and historical evidence found that the pool deck construction deviated from design requirements. Specifically, the number of slab reinforcing bars centered over vertical columns was inadequate, and the reinforcing bars in the top of the slab in the vicinity of the columns were spaced farther apart than the design required, according to investigators. These deviations weakened the slab-column connections, they said.

NIST expects technical work on the investigation to be substantially completed in late June 2024 and aims to release a report with findings and recommendations in late June 2025.

Related Stories

| Nov 6, 2013

PECI tests New Buildings Institute’s plug load energy use metrics at HQ

Earlier this year, PECI used the NBI metrics to assess plug load energy use at PECI headquarters in downtown Portland, Ore. The study, which informed an energy-saving campaign, resulted in an 18 percent kWh reduction of PECI’s plug load.

| Nov 5, 2013

Net-zero movement gaining traction in U.S. schools market

As more net-zero energy schools come online, school officials are asking: Is NZE a more logical approach for school districts than holistic green buildings? 

| Nov 5, 2013

New IECC provision tightens historic building exemption

The International Energy Conservation Code has been revised to eliminate what has been seen as a blanket exemption for historic buildings.

| Nov 5, 2013

Living Building Challenge clarifies net-zero definitions and standards

The Living Building Challenge has released the Net Zero Energy Building Certification to provide clearer definitions regarding what net zero really means and how it is to be achieved.

| Nov 5, 2013

Oakland University’s Human Health Building first LEED Platinum university building in Michigan [slideshow]

Built on the former site of a parking lot and an untended natural wetland, the 160,260-sf, five-story, terra cotta-clad building features some of the industry’s most innovative, energy-efficient building systems and advanced sustainable design features.

| Nov 4, 2013

Architecture and engineering industry outlook remains positive on all major indicators

While still below pre-recession levels, all of the key indicators in the latest Quarterly Market Forecast (QMF) report from PSMJ Resources remain in positive territory.  

| Nov 1, 2013

CBRE Group enhances healthcare platform with acquisition of KLMK Group

CBRE Group, Inc. (NYSE:CBG) today announced that it has acquired KLMK Group, a leading provider of facility consulting, project advisory and facility activation solutions to the healthcare industry. 

| Oct 31, 2013

74 years later, Frank Lloyd Wright structure built at Florida Southern College

The Lakeland, Fla., college adds to its collection of FLW buildings with the completion of the Usonian house, designed by the famed architect in 1939, but never built—until now. 

| Oct 31, 2013

CBRE's bold experiment: 200-person office with no assigned desks [slideshow]

In an effort to reduce rent costs, real estate brokerage firm CBRE created its first completely "untethered" office in Los Angeles, where assigned desks and offices are replaced with flexible workspaces. 

| Oct 30, 2013

15 stellar historic preservation, adaptive reuse, and renovation projects

The winners of the 2013 Reconstruction Awards showcase the best work of distinguished Building Teams, encompassing historic preservation, adaptive reuse, and renovations and additions.

boombox1
boombox2
native1

More In Category




Engineers

Navigating battery energy storage augmentation

By implementing an augmentation plan upfront, owners can minimize potential delays and unforeseen costs when augmentation needs to occur, according to Burns & McDonnell energy storage technology manager Joshua Crawford.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021