flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Newark Liberty International Airport breaks ground on $2.4 billion redevelopment project

Airports

Newark Liberty International Airport breaks ground on $2.4 billion redevelopment project

The project includes a new 1 million-sf terminal building with 33 domestic aircraft gates.


By David Malone, Associate Editor | June 26, 2017

Rendering courtesy PGAL

The modernization project at the Newark Liberty International Airport is officially underway. The Port Authority of New York and New Jersey has recently broken ground on the $2.4 billion project.

The largest aspect of the project is the redevelopment of the original Terminal A building, which opened in 1973 and is being replaced with a new 1 million-sf terminal building. PGAL is the lead architect responsible for advanced planning and concept development for the structure.

Included in the new terminal are 33 domestic aircraft gates, expanded departures and arrivals curbside frontage, a parking garage complex, and infrastructure improvements. The terminal is designed to initially accommodate up to 13.6 million passengers each year, but is incorporating the flexibility necessary to expand to serve larger aircraft and increased passenger demand in the future.

 

Rendering courtesy PGAL.

 

An expandable security screening checkpoint will provide increased passenger queue space and dedicated lanes for premium passengers, crew, and physically challenged travelers. A new baggage claim area will include six claim units with immediate access to airline services offices and passenger amenities for two defined arrivals areas from the departures concourses. Hold room seating areas will comprise a broad range of retail and food and beverage options and airline lounges are immediately accessible after the security checkpoint.

Additionally, a new departures and arrivals roadway system will support Terminal A. The new 3,000-car parking garage complex will feature a pedestrian bridge and hub connection that links passengers from the garage and Air Train to the terminal.

 

Rendering courtesy PGAL.

 

The new Terminal A is expected to be fully operational in 2022.

Related Stories

| Jun 14, 2012

Viscardi joins LEO A DALY as VP, corporate director of aviation programs

Viscardi will be responsible for providing the vision and strategy for growing the firm’s aviation practice, identifying and establishing new clients, as well as maintaining existing client relationships.

| Jun 1, 2012

New BD+C University Course on Insulated Metal Panels available

By completing this course, you earn 1.0 HSW/SD AIA Learning Units.

| May 30, 2012

Construction milestone reached for $1B expansion of San Diego International Airport

Components of the $9-million structural concrete construction phase included a 700-foot-long, below-grade baggage-handling tunnel; metal decks covered in poured-in-place concrete; slab-on-grade for the new terminal; and 10 exterior architectural columns––each 56-feet tall and erected at a 14-degree angle.

| May 29, 2012

Reconstruction Awards Entry Information

Download a PDF of the Entry Information at the bottom of this page.

| May 24, 2012

2012 Reconstruction Awards Entry Form

Download a PDF of the Entry Form at the bottom of this page.

| Mar 29, 2012

U.K.’s Manchester Airport tower constructed in nine days

Time-lapse video shows construction workers on the jobsite for 222 continuous hours.

| Mar 27, 2012

Skanska hires aviation construction expert Bob Postma

Postma will manage Skanska’s nationwide in-house team of airport construction experts who lead the industry in building and renovating airport facilities and their essential features.

| Jan 4, 2012

New LEED Silver complex provides space for education and research

The academic-style facility supports education/training and research functions, and contains classrooms, auditoriums, laboratories, administrative offices and library facilities, as well as spaces for operating highly sophisticated training equipment.

| Nov 10, 2011

Skanska Moss to expand and renovate Greenville-Spartanburg International Airport

The multi-phase terminal improvement program consists of an overall expansion to the airport’s footprint and major renovations to the existing airport terminal.

boombox1
boombox2
native1

More In Category


Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.


Airports

SOM unveils ‘branching’ structural design for new Satellite Concourse 1 at O’Hare Airport

The Chicago Department of Aviation has revealed the design for Satellite Concourse 1 at O’Hare International Airport, one of the nation’s business airports. Designed by Skidmore, Owings & Merrill (SOM), with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA), and Arup, the concourse will be the first new building in the Terminal Area Program, the largest concourse area expansion and revitalization in the airport’s almost seven-decade history. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021