New York City construction site inspections, enforcement found ‘inadequate’

New York City construction site inspections, enforcement found ‘inadequate’

New York State Comptroller finds DOB practices faulty.


By Peter Fabris, Contributing Editor | September 19, 2022
New York City construction
Courtesy Pexels.

A new report by the New York State Comptroller found that New York City construction site inspections and regulation enforcement need improvement.

The state watchdog found that nearly 90% of active New York City construction sites it visited had safety problems. It also said the city’s Department of Buildings doesn’t effectively prioritize which sites get inspected.

Officials from the Comptroller’s office visited 18 active construction sites last summer and reported that 16 of those sites had a total of 77 safety issues. The problems included not having a site safety manager, missing or incomplete site safety logs and daily inspection records, and no documentation of workers completing required site safety training or attending mandatory safety meetings.

In 60% of cases where hazardous conditions were present for more than 30 days, DOB did not issue a citation for failing to correct the problem, the report says. The DOB agreed with most recommendations made to improve practices as cited in the report, which included more timely action to fix hazardous conditions at job sites.

The city department’s chief also noted that conditions “may change on a daily, or even hourly basis; therefore, the types of conditions that the auditors noted may not be present at the time of DOB’s inspection.”

Related Stories

| Oct 6, 2011

GREENBUILD 2011: Growing green building market supports 661,000 green jobs in the U.S.

Green jobs are already an important part of the construction labor workforce, and signs are that they will become industry standard.

| Oct 6, 2011

GREENBUILD 2011: NEXT Living EcoSuite showcased

  Tridel teams up with Cisco and Control4 to unveil the future of green condo living in Canada.

| Oct 5, 2011

GREENBUILD 2011: Johnson Controls announces Panoptix, a new approach to building efficiency

Panoptix combines latest technology, new business model and industry-leading expertise to make building efficiency easier and more accessible to a broader market.

| Oct 5, 2011

GREENBUILD 2011: Software an architectural game changer

Interactive modeling software transforms the design­build process. 

| Oct 5, 2011

GREENBUILD 2011: Tile manufacturer attains third-party certification for waste recycling processes

Crossville has joined with TOTO to recycle that company’s pre-consumer fired sanitary ware.

| Oct 5, 2011

GREENBUILD 2011: Roof hatch designed for energy efficiency

The cover features a specially designed EPDM finger-type gasket that ensures a positive seal with the curb to reduce air permeability and ensure energy performance. 

| Oct 4, 2011

GREENBUILD 2011

Click here for the latest news and products from Greenbuild 2011, Oct. 4-7, in Toronto.

| Oct 4, 2011

GREENBUILD 2011: Methods, impacts, and opportunities in the concrete building life cycle

Researchers at the Massachusetts Institute of Technology’s (MIT) Concrete Sustainability Hub conducted a life-cycle assessment (LCA) study to evaluate and improve the environmental impact and study how the “dual use” aspect of concrete.

| Oct 4, 2011

GREENBUILD 2011: Johnsonite features sustainable products

Products include rubber flooring tiles, treads, wall bases, and more. 

boombox1
boombox2
native1

More In Category


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021