New York City code update changes definition of a major building

Codes and Standards

New York City code update changes definition of a major building

Impacts how construction projects are permitted with major implications for contractors


By Peter Fabris, Contributing Editor | July 15, 2024
Image by Melissa Mahon from Pixabay

Image by Melissa Mahon from Pixabay

Changes affecting how construction projects in New York City are permitted will have significant impacts for contractors.

On Dec. 11, the definition of a major building in the city’s code will change from 10 stories to seven, or 75 feet. The change will affect thousands more projects.

It will require a site safety coordinator and an approved site safety plan for any major new build, full demolition, or interior demolition with mechanical equipment that is seven stories or higher. Contractors working on these major projects should hire professionals to assist them with navigating through the entire application, permit, certificate of occupancy, approval, and sign-off processes, advises a former New York Department of Buildings assistant commissioner. Contractors who have previously built only low-rise buildings should also hire a safety consultant to provide full-time safety professionals and obtain approvals for site safety plans and tenant protection plans, he says.

The code change includes a provision for construction superintendents to only be designated on three permits at one time. In January 2026, this number will be reduced to one permit. As a result, contractors should send their staff to obtain superintendent licenses and Supervisory SST training cards.

Related Stories

Codes and Standards | Mar 2, 2015

Nevada moves to suspend prevailing wage rules on school projects

The Nevada Senate approved a bill that would suspend prevailing wage rules on school projects.

Codes and Standards | Mar 2, 2015

Proposed energy standard for data centers, telecom buildings open for public comment

The intent of ASHRAE Standard 90.4P is to create a performance-based approach that would be more flexible and accommodating of innovative change.

Codes and Standards | Feb 22, 2015

Louisiana officials critical of stricter building standards in flood-prone areas

Buildings would have to be built either two or three feet above the base flood elevation for a 100-year flood or above the base elevation for a 500-year flood. 

Codes and Standards | Feb 18, 2015

Buildings with rocking steel-braced frames are advantageous in earthquakes

Research at Case Western Reserve University has found that buildings that rock during an earthquake and return to plumb would withstand seismic shaking better than structural designs commonly used today in vulnerable zones of California and elsewhere.

Codes and Standards | Feb 18, 2015

USGBC concerned about developers using LEED registration in marketing

LEED administrators are concerned about a small group of developers or project owners who tout their projects as “LEED pre-certified” and then fail to follow through with certification.

Codes and Standards | Feb 12, 2015

ASHRAE, USGBC, IES consider biomass requirements in green building standard

The proposal would add biomass to approved renewables.

Codes and Standards | Feb 12, 2015

New Appraisal Institute form aids in analysis of green commercial building features

The Institute’s Commercial Green and Energy Efficient Addendum offers a communication tool that lenders can use as part of the scope of work. 

Codes and Standards | Feb 8, 2015

ASHRAE, IAQA approve consolidation

Under the consolidation, IAQA will become a part of the ASHRAE organization while maintaining its own brand and Board of Directors.

Codes and Standards | Feb 6, 2015

Obama executive order requires federal construction projects to consider flood damage caused by climate change

To meet the new standard, builders must build two feet above the currently projected elevation for 100-year floods for most projects.

HVAC | Feb 6, 2015

ASHRAE, REHVA publish guide to chilled beam systems

The guide provides tools and advice for designing, commissioning, and operating chilled-beam systems.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021