flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

New SJI Rule on Steel Joists

New SJI Rule on Steel Joists

A new rule from the Steel Joist Institute clarifies when local reinforcement of joists is required for chord loads away from panel points. SJI members offer guidance about how and when to specify loads.


By By Susan Bady, Contributing Editor | January 3, 2012
New SJI Rule on Steel Joists
According to a new rule issued by the Steel Joist Institute, the proper way to hang loads from joist chords is concentrically (n
This article first appeared in the January 2012 issue of BD+C.

For years, the steel joist industry standard has been that loads either need to be applied at panel points, or a member brace (strut) must be added in the field. In response to inquiries from structural engineers and other members of the Building Team, the Steel Joist Institute recently issued a new rule for loads not exceeding 100 pounds within any given panel.Ā 

The full text of the SJI rule reads as follows: ā€œFor nominal concentrated loads between panel points, which have been accounted for in the specified uniform design loads, a strut to transfer the load to a panel point on the opposite chord shall not be required, provided the sum of the concentrated loads within a chord panel does not exceed 100 pounds and the attachments are concentric to the chord.ā€

Bruce Brothersen, engineering manager for Vulcraft-Utah, Brigham, Utah, says, ā€œThe rule is an attempt to better define what is acceptable and put some quantitative numbers to it.ā€

Tim Holtermann, corporate engineering manager for Canam Steel in Washington, Mo., says that even with the new rule, manufacturers remain concerned that ā€œpeople may be hanging things in excess of 100 pounds away from panel points and not field-adding struts, as theyā€™re required to do.ā€

Holtermann says one option for structural engineers is to ask the manufacturer to provide a specially designed joist that can take point loads over 100 pounds without the added members. ā€œItā€™s not uncommon to have a design requirement for, say, 250 pounds or 400 pounds,ā€ he says. ā€œWe can readily do that as long as the magnitude of the loads and this design requirement are specified on the contract drawings.ā€

DONā€™T WAIT FOR THE FINAL PUNCH LIST
Often the problem with the joist loads isnā€™t discovered until the project is completed and the final walkthrough is taking place, says Joe Pote, director of research and development for New Millennium Building Systems, Hope, Ark.

ā€œThe inspector notices ductwork or sprinkler lines or mechanicals hanging from the joists between panel points that arenā€™t called out on the contract drawings,ā€ says Pote. ā€œThen he comes back to us and asks if itā€™s okay.ā€ Many times the loads are small (20-50 pounds), so additional reinforcementĀ isnā€™t necessary. ā€œBut we never had a good rule that stated the maximum load,ā€ he says. ā€œI think it helps clear up some of the discrepancy between SJI requirements and actual field practice.ā€

The manner in which the loads are hung is a key element of the 100-pound rule, says Holtermann. ā€œThe rule presumes that the load will be placed concentrically,ā€ he says.

As SJI managing director Ken Charles notes, some trade installers make the mistake of attaching beam clamps to only one bottom chord angle of the joist instead of both. On top of that, he says, ā€œthe load isnā€™t placed concentrically even to that one chord angle, so youā€™re inducing some torsion and bending of the horizontal leg of the angle.ā€

His advice: ā€œBy far the better way to do it is to make sure the attachment is always concentric and always attached to both chord angles.ā€ (See diagram.)

Steel Joist Doā€™s and Donā€™ts

  • Recognize how and when to specify total uniform load or factored load and/or net uplift load, and when loads need to be broken out by load category and combinations.
  • Know the limits of a concentrated load applied between panel points before an additional web is needed on the joist. The Steel Joist Instituteā€™s new ā€œ100-pound ruleā€ clarifies these limits.
  • Install bridging early and follow the proper procedures to avoid safety problems, such as a partial building collapse.
  • Designate a field representative to inspect the joists during construction and ensure that components are being installed correctly.Ideally, a representative of the team should walk the job site before completion and look for situations where loads arenā€™t handled correctly.

ā€œA lot of times thereā€™s a disconnect between the design intent and the construction site personnel,ā€ says Charles. ā€œSome sites have representatives in the field to do inspections, but often thatā€™s not the case. Those are the projects that are most likely to have problems down the road when the final punch list is done.ā€

GET YOUR SPECS STRAIGHT
Joists are designed to handle different types of loads, such as dead load, live load, and wind, snow, and seismic loads. A given joist might experience more than one type of load, so the joist manufacturer needs to know which loads apply and properly combine them according to parameters set by the International Building Code. Most jurisdictions use the 2006 version of the IBC or the 2009 version, which is similar with regard to steel joists.

Brothersen notes that the building code loading combinations are based on the probability of which loads will act simultaneously. ā€œFor instance, the probability of a seismic event occurring when the maximum snow load is on the joist is relatively small, so the building code reduces the loads in those cases,ā€ he says. ā€œThis is more realistic and doesnā€™t require manufacturers to design for the maximum load in every category at the same time.ā€

Pote says manufacturers prefer, when itā€™s feasible, that loads be provided to them as either a total uniform load or a factored load. In other words, if all components of the joist can be designed for a single downward-acting load case and a single upward-acting load case, the easiest thing for engineers to do is provide the total uniform load and/or net uplift load (dead load minus wind load).

ā€œItā€™s just easier to communicate,ā€ says Charles. ā€œHowever, if we have to consider multiple load combinations, we need the breakdownā€”dead load, live load, snow load, and so forth.ā€

Holtermann adds that if the structure might be affected by downward-acting winds, the total uniform load should assume the worst-case scenario.

DONā€™T FORGET THE BRIDGING
Once the joists arrive on site, itā€™s important that bridging be installed early and correctly, says Brothersen. ā€œIf the joists are put up but the bridging isnā€™t installed, it can become a safety issue.ā€ For example, lack of bridging can result in a partial building collapse when the crew begins stacking bundles of deck material on the joists.

Charles agrees. ā€œThe best-laid plans of the engineer and manufacturer can go out the window when the product arrives at the job site and the erector doesnā€™t follow proper safety regulations and the manufacturerā€™s advice.ā€ BD+C
--
Editorā€™s note: To order SJIā€™s ā€œ43rd Edition Catalog of Standard Specifications and Load and Weight Tables for Steel Joists and Joist Girders,ā€ go to: http://steeljoist.org/free-download-form.

Related Stories

| Jan 19, 2011

Architecture Billings Index jumped more than 2 points in December

On the heels of its highest mark since 2007, the Architecture Billings Index jumped more than two points in December. The American Institute of Architects reported the December ABI score was 54.2, up from a reading of 52.0 the previous month.Ā 

| Jan 19, 2011

Large-Scale Concrete Reconstruction Solid Thinking

Driven by both current economic conditions and sustainable building trends, Building Teams are looking more and more to retrofits and reconstruction as the most viable alternative to new construction. In that context, large-scale concrete restoration projects are playing an important role within this growing specialty.

| Jan 10, 2011

Architect Jean Nouvel designs an island near Paris

Abandoned by carmaker Renault almost 20 years ago, Seguin Island in Boulogne-Billancourt, France, is being renewed by architect Jean Nouvel. Plans for the 300,000-square-meter project includes a mix of culture, commerce, urban parks, and gardens, which officials hope will attract both Parisians and tourists.

| Jan 10, 2011

Michael J. Alter, president of The Alter Group: ā€˜Thereā€™s a significant pent-up demand for projectsā€™

Michael J. Alter, president of The Alter Group, a national corporate real estate development firm headquartered in Skokie, Ill., on the growth of urban centers, project financing, and what clients are saying about sustainability.

| Jan 7, 2011

BIM on Target

By using BIM for the design of its new San Clemente, Calif., store, big-box retailer Target has been able to model the entire structural steel package, including joists, in 3D, chopping the timeline for shop drawings from as much as 10 weeks down to an ā€˜unheard ofā€™ three-and-a-half weeks.

| Jan 7, 2011

How Building Teams Choose Roofing Systems

A roofing survey emailed to a representative sample of BD+Cā€™s subscriber list revealed such key findings as: Respondents named metal (56%) and EPDM (50%) as the roofing systems they (or their firms) employed most in projects. Also, new construction and retrofits were fairly evenly split among respondentsā€™ roofing-related projects over the last couple of years.

| Jan 7, 2011

Total construction to rise 5.1% in 2011

Total U.S. construction spending will increase 5.1% in 2011. The gain from the end of 2010 to the end of 2011 will be 10%. The biggest annual gain in 2011 will be 10% for new residential construction, far above the 2-3% gains in all other construction sectors.

| Jan 7, 2011

Mixed-Use on Steroids

Mixed-use development has been one of the few bright spots in real estate in the last few years. Successful mixed-use projects are almost always located in dense urban or suburban areas, usually close to public transportation. Itā€™s a sign of the times that the residential component tends to be rental rather than for-sale.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Ā