The contractor Consigli Construction has released its latest breakdown of predictions about materials and labor pricing for 21 categories, based on the firm’s survey of more than 200 subcontractors working in the Northeast.
From that polling, Consigli considers HVAC and electrical trades to be at the greatest risk for price increases, based on their projected percentage of a project’s total cost. The firm elaborates that there is potential for price hikes in copper tubing and small-bore pipe, as well as lighting fixtures, copper and PVC, and distribution equipment.
Consigli breaks down pricing risks by 21 categories. Image: Consigli
The good news is that 56% of the subs polled said they were experiencing no major increases in lead times as a result of the coronavirus pandemic. That being said, “subcontractors are continuing to place focus on ordering materials as soon as possible to prevent schedule delays,” says Peter Capone, Consigli’s Director of Purchasing.
The firm singles out glass and aluminum, lumber, distribution and transportation issues, electrical lighting/PVC, and custom fabricated materials as “risks to watch for” in the future. Concerning lumber, which has been in short supply across North America, the report states that suppliers “should catch up” with demand by this winter and next Spring, when homebuilding shifts into a higher gear.
WORKER AVAILABILITY SHOULDN’T HAMPER PROJECTS
More than half of the subs polled weren't having lead time problems. Image: Consigli Construction
Consigli notes that, lately, it has experienced “better than normal” bid coverage and aggressive pricing in nearly every trade. Despite their healthy backlogs, subs are still looking to book work for next year and beyond. And most of the subs polled—93%—are confident they will be able to hire more workers to meet work demand.
“There is potential when the COVID-19 vaccine is developed, the construction market may start trending back toward pre-COVID-19 levels of activity,” which could add product and labor costs. “Therefore, now is the time to move forward with upcoming projects,” writes Capone.
Related Stories
| Jul 31, 2012
Thornton Tomasetti announces four promotions in Chicago office
Promotions in Thornton Tomasetti office key on industy veterans.
| Jul 25, 2012
Contract awarded for Gaillard Municipal Auditorium renovations in Charleston, S.C.
Seeking LEED Silver certification, the project will begin in August and is slated for completion in December 2014.
| Jul 25, 2012
Hill International selected as project manager for two Abu Dhabi hospitals
The two hospitals have a combined estimated project value of approximately AED 784 million ($213 million).
| Jul 25, 2012
KBE Building renovates UConn dining hall
Construction for McMahon Dining Hall will be completed in September 2012.
| Jul 24, 2012
Dragon Valley Retail at epicenter of Yongsan International Business District
Masterplanned by architect Daniel Libeskind, the Yongsan IBD encompasses ten city blocks and includes a collection of high-rise residences and commercial buildings.
| Jul 23, 2012
Giants 300 Firm Index 2012
An alphabetical index of the Giants 300 AEC firms and their ranking in specific categories.
| Jul 23, 2012
Haynes Whaley announces leadership transition
Pronier has worked in the construction industry for the past 30 years.
| Jul 23, 2012
Missner Group completes construction of Chicago auto dealership
The Missner Group also incorporated numerous sustainable improvements to the property including the implementation of a vegetative roof, and the utilization of permeable pavers for the parking lot.
| Jul 20, 2012
2012 Giants 300 Special Report
Ranking the leading firms in Architecture, Engineering, and Construction.
| Jul 20, 2012
Data Centers Report: Demand ‘exploding’
BD+C's Giants 300 Top 25 AEC Firms in the Data Center sector.