The contractor Consigli Construction has released its latest breakdown of predictions about materials and labor pricing for 21 categories, based on the firm’s survey of more than 200 subcontractors working in the Northeast.
From that polling, Consigli considers HVAC and electrical trades to be at the greatest risk for price increases, based on their projected percentage of a project’s total cost. The firm elaborates that there is potential for price hikes in copper tubing and small-bore pipe, as well as lighting fixtures, copper and PVC, and distribution equipment.
Consigli breaks down pricing risks by 21 categories. Image: Consigli
The good news is that 56% of the subs polled said they were experiencing no major increases in lead times as a result of the coronavirus pandemic. That being said, “subcontractors are continuing to place focus on ordering materials as soon as possible to prevent schedule delays,” says Peter Capone, Consigli’s Director of Purchasing.
The firm singles out glass and aluminum, lumber, distribution and transportation issues, electrical lighting/PVC, and custom fabricated materials as “risks to watch for” in the future. Concerning lumber, which has been in short supply across North America, the report states that suppliers “should catch up” with demand by this winter and next Spring, when homebuilding shifts into a higher gear.
WORKER AVAILABILITY SHOULDN’T HAMPER PROJECTS
More than half of the subs polled weren't having lead time problems. Image: Consigli Construction
Consigli notes that, lately, it has experienced “better than normal” bid coverage and aggressive pricing in nearly every trade. Despite their healthy backlogs, subs are still looking to book work for next year and beyond. And most of the subs polled—93%—are confident they will be able to hire more workers to meet work demand.
“There is potential when the COVID-19 vaccine is developed, the construction market may start trending back toward pre-COVID-19 levels of activity,” which could add product and labor costs. “Therefore, now is the time to move forward with upcoming projects,” writes Capone.
Related Stories
| Jan 10, 2013
Guide predicts strongest, weakest AEC markets for 2013
2013 Guide to U.S. AEC markets touts apartments, natural gas, senior housing and transmission and distribution.
| Jan 8, 2013
PC Construction names McCarthy President/CEO
McCarthy, who joined PC Construction in 1998 and currently serves as executive vice president, will become a member of the employee-owned company’s board of directors and a trustee of the employee stock ownership plan.
| Jan 3, 2013
Answered prayers
A bold renovation enables a small church to expand its mission on a grand scale.
| Jan 2, 2013
M&A activity at U.S. AEC firms up slightly
Total mergers and acquisitions in the AEC industry hit 171 in 2012, up slight from the 169 deals in 2011.
| Jan 2, 2013
Construction jobs made gains in 2012, even with a slow Q4, says Gilbane report
The construction sector in the nine states with 50% of construction employment was up 169,000 jobs from February to September 2012, following a lost of 137,000 jobs from September 2011 to January 2012.
| Dec 21, 2012
ABI gains for fourth straight month
Positive business conditions for all building sectors.
| Dec 13, 2012
LPCiminelli opens New York City office
Steve Giordano named executive in charge of new office.