The contractor Consigli Construction has released its latest breakdown of predictions about materials and labor pricing for 21 categories, based on the firm’s survey of more than 200 subcontractors working in the Northeast.
From that polling, Consigli considers HVAC and electrical trades to be at the greatest risk for price increases, based on their projected percentage of a project’s total cost. The firm elaborates that there is potential for price hikes in copper tubing and small-bore pipe, as well as lighting fixtures, copper and PVC, and distribution equipment.
Consigli breaks down pricing risks by 21 categories. Image: Consigli
The good news is that 56% of the subs polled said they were experiencing no major increases in lead times as a result of the coronavirus pandemic. That being said, “subcontractors are continuing to place focus on ordering materials as soon as possible to prevent schedule delays,” says Peter Capone, Consigli’s Director of Purchasing.
The firm singles out glass and aluminum, lumber, distribution and transportation issues, electrical lighting/PVC, and custom fabricated materials as “risks to watch for” in the future. Concerning lumber, which has been in short supply across North America, the report states that suppliers “should catch up” with demand by this winter and next Spring, when homebuilding shifts into a higher gear.
WORKER AVAILABILITY SHOULDN’T HAMPER PROJECTS
More than half of the subs polled weren't having lead time problems. Image: Consigli Construction
Consigli notes that, lately, it has experienced “better than normal” bid coverage and aggressive pricing in nearly every trade. Despite their healthy backlogs, subs are still looking to book work for next year and beyond. And most of the subs polled—93%—are confident they will be able to hire more workers to meet work demand.
“There is potential when the COVID-19 vaccine is developed, the construction market may start trending back toward pre-COVID-19 levels of activity,” which could add product and labor costs. “Therefore, now is the time to move forward with upcoming projects,” writes Capone.
Related Stories
Contractors | May 1, 2015
Construction workers among top U.S. drug users: study
Construction workers are topped only by miners when it comes to heavy drinking, according to a new study by the Substance Abuse and Mental Health Services Administration.
Multifamily Housing | May 1, 2015
Trade groups extend campaign to promote apartment living
The groups claim that there are more than 37 million Americans—12% of the population—living in just under 20 million apartment units nationwide. Apartments and their residents contribute $1.3 trillion annually to the economy.
Contractors | May 1, 2015
Nonresidential fixed investments fall in latest Construction Economic Update
This is the first time that nonresidential fixed investment declined since the first quarter of 2011, ABC reported. Nonresidential fixed investment had been rising by more than 4% on an annualized basis during five of the previous six quarters.
Contractors | Apr 29, 2015
Construction costs are expected to remain soft through fall of 2015
Labor and materials haven’t appreciated this year through April, according to market analyst IHS.
Contractors | Apr 23, 2015
Leopardo releases 2015 Construction Economics Outlook
Low oil prices have reduced the cost of construction, but not enough to offset the rise in labor costs, according to Leopardo's new outlook report.
High-rise Construction | Apr 23, 2015
Size matters in NYC, where several projects vie for the city’s tallest building honor
The latest renderings of 217 West 57th Street show a tower that would rise higher than the World Trade Center’s pinnacle, when elevations are included.
Multifamily Housing | Apr 22, 2015
Condo developers covet churches for conversions
Former churches, many of which are sitting on prime urban real estate, are being converted into libraries, restaurants, and with greater frequency condominiums.
Green | Apr 22, 2015
AIA Committee on the Environment recognizes Top 10 Green Projects
Seattle's Bullitt Center and the University Center at The New School are among AIA's top 10 green buildings for 2015.
BIM and Information Technology | Apr 21, 2015
Software tools shouldn't dictate the AEC process
With over 200 solutions on the market, construction software is one of the most complex and fragmented markets, writes Gensler's Mark Thole.
Contractors | Apr 20, 2015
Too many construction projects don’t meet owners’ expectations: KPMG report
Causes for delays, overruns, and underperformance include project management talent shortages, distrust between owners and contractors, and the lack of fully integrated project management systems.