Net-zero energy pioneers on the el-hi frontier

Net-zero energy pioneers on the el-hi frontier

Getting to net-zero is not easy, but the promise of eliminating energy bills and using state-of-the-art technology as a learning lab can make a compelling case to reach for net-zero.


By By Peter Fabris, Contributing Editor | September 7, 2012
The Colonel Smith Middle School in Fort Huachuca, Ariz., is about to open for th
The Colonel Smith Middle School in Fort Huachuca, Ariz., is about to open for the 2012-2013 school year. The 330-student facilit
This article first appeared in the September 2012 issue of BD+C.

Net-zero may seem beyond the budgets of most K-12 school districts, but a couple of trailblazers have found the means to construct schools designed to produce as much power as they use.

The new $20 million, 88,693-sf Colonel Smith Middle School in Ft. Huachuca, Ariz., takes daylighting to the highest level. Every regularly occupied space has a window, skylight, or clerestory glazing for layered daylighting. To hold down the cooling load, the building obtains most of its sunlight from the north sky through clerestory windows. On the south exterior wall, exterior overhangs prevent direct solar exposure in the summer, while allowing passive solar heating in winter. Locker rooms and other support spaces have shaded high-wall translucent fiberglass panels to provide privacy. Lighting energy use is expected to be 80% less than that of a standard school building.

Energy is recovered from locker room exhaust to pre-heat or pre-cool supply air delivered to locker rooms. Solar panels heat domestic water for locker rooms and the kitchen. PVs were obtained through a power purchase agreement. “We didn’t have net-zero in mind when we were starting out,” notes Dr. Ronda Frueauff, Superintendent of the Ft. Huachuca Accommodation School District. That changed as the design committee evaluated the affordability of each green element. Only geothermal was ruled out as cost-prohibitive.

Geothermal is, however, a key component of the Lady Bird Johnson Middle School in Irving, Texas, with 530 geothermal wells and 105 water-source heat pumps. The school is powered by 2,988 rooftop solar panels and 12 wind turbines. Opened in August 2011, the $29 million, 152,000-sf school cost about 12% more to build than one of traditional construction. School officials expect to recoup their investment in 10-12 years.

“We didn’t have net-zero in mind when we were starting out.”
--Dr. Ronda Frueauff, Superintendent of the Ft. Huachuca Accommodation School District.

Both schools incorporate green features into lesson plans. The Texas school features museum-type displays along the main hallway highlighting geothermal, solar, and wind technology, along with water efficiency. Students can get a close-up view of the PVs from a roof observation deck.

Getting to net-zero is not easy, but the promise of eliminating energy bills and using state-of-the-art technology as a learning lab can make a compelling case to reach for net-zero. +

Related Stories

Energy | Jul 13, 2022

Electrification of buildings, new and old, furthers environmental responsibility and equity

 It’s almost a cliché in our industry, but nonetheless: The greenest building is the one that is already built. 

Building Team | Jul 13, 2022

Austin’s newest entertainment and hospitality complex has been made from repurposed shipping containers

A new entertainment and hospitality complex in Austin, The Pitch, has been made out of repurposed shipping containers. 

Codes and Standards | Jul 12, 2022

USGBC sets out principles for LEED’s future

The U.S. Green Building Council recently published a report containing principles outlining how LEED will evolve.

Building Team | Jul 12, 2022

10 resource reduction measures for more efficient and sustainable biopharma facilities

Resource reduction measures are solutions that can lead to lifecycle energy and cost savings for a favorable return on investment while simultaneously improving resiliency and promoting health and wellness in your facility.

Office Buildings | Jul 12, 2022

Miami office tower nears completion, topping off at 55 stories

In Miami, construction of OKO Group and Cain International’s 830 Brickell office tower is nearing completion.

University Buildings | Jul 11, 2022

Student life design impacts campus wellness

As interior designers, we have the opportunity and responsibility to help students achieve deeper levels of engagement in their learning, social involvement, and personal growth on college campuses.

Museums | Jul 11, 2022

Denmark opens a museum that tells the stories of refugees worldwide

Located on the site of Denmark’s largest World War II refugee camp, the new Refugee Museum of Denmark, FLUGT, tells the stories of refugees from the camp as well as refugees worldwide. 

Codes and Standards | Jul 8, 2022

Inefficient supply chains, outdated project delivery systems hamper construction investment

Constructing and justifying the cost of physical assets such as a manufacturing plant is much more difficult than it was decades ago, according to a report by Steffen Fuchs, senior partner with McKinsey & Company.

Airports | Jul 8, 2022

Phoenix Sky Harbor Airport’s new terminal prioritizes passenger experience and sustainability

McCarthy Building Companies recently completed construction of the final concourse in Terminal 4 at Phoenix Sky Harbor International Airport.

Architects | Jul 7, 2022

Page acquires AE giant EYP to form 1,300-person international design firm

The combined firm will “be able to invest in research and thought leadership to co-create with our clients,” stated Page CEO Thomas McCarthy.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021