Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

3D imaging key to project timetable and cost containment.


By By BD+C Staff | April 19, 2012
When finished, the four-story, 80,000-sf office building will connect to the exi
When finished, the four-story, 80,000-sf office building will connect to the existing 193,000-sf facility and is anticipated to

Nauset Construction has begun foundation work on Phase Two of the National Guard Bureau’s new Joint Force Headquarters at Hanscom Air Force Base, Lincoln, Mass.

When finished, the four-story, 80,000-sf office building will connect to the existing 193,000-sf facility and is anticipated to be completed by May of 2013.

The construction of the building and connections to the existing facility have been well coordinated by Nauset’s BIM Management Team, which used 3D modeling to detect structural clashes. 

The new facility will have its own air handling units and heating and cooling systems, but the water, fire protection, and electrical systems will be central to the two phases.  

Designed to resist the effects of earthquake motions, the facility will house classrooms with raised computer access flooring, heated storage and vehicle ready work bays. The foundation will consist of reinforced concrete footings and floor slab with steel framed masonry walls, aluminum windows, and a metal paneled roof system with integrated gutters. The HVAC system will include three 2,000 MBH gas fired boilers, two 140 ton electric air-cooled chillers and air handlers with multiple zones.

Additional building features will include auxiliary power, fire detection and suppression, security access and surveillance and intrusion detection systems. Extensive hardscaping (roadways, ground level parking, an amphitheater with tiered seating, pedestrian walkways) and landscaping is also part of the project’s scope of work. The LEED Silver rating will be achieved by utilizing energy efficient MEP systems and controls, as well as bio-swales to reduce storm water runoff. Project challenges include close coordination with all subcontractors due to the highly sensitive, occupied and restricted site location. BD+C

Related Stories

| Jun 12, 2013

More than 90% of New York City schools have code violations

More than 90% of New York City schools have at least one outstanding building code violation. Loose wires, stuck doors and inadequate ventilation are just some of the problems.

| Jun 12, 2013

5 building projects that put the 'team' in teamwork

The winners of the 2013 Building Team Awards show that great buildings cannot be built without the successful collaboration of the Building Team. 

| Jun 12, 2013

Sacred synergy achieves goals for religious education [2013 Building Team Award winner]

A renovation/addition project at Columbia Theological Seminary unites a historic residence hall with a modern classroom facility.

| Jun 12, 2013

‘Talking’ Braille maps help the visual impaired

Talking pen technology, combined with tactile maps, allows blind people to more easily make their way around BART stations in the Bay Area.

| Jun 11, 2013

Music/dance building supports sweet harmony [2013 Building Team Award winner]

A LEED Gold project enhances a busy Chicago neighborhood, meeting ambitious criteria for acoustical design and adaptability.

| Jun 11, 2013

Vertical urban campus fills a tall order [2013 Building Team Award winner]

Roosevelt University builds a 32-story tower to satisfy students’ needs for housing, instruction, and recreation.

| Jun 11, 2013

Building a better box: High-bay lab aims for net-zero [2013 Building Team Award winner]

Building Team cooperation and expertise help Georgia Tech create a LEED Platinum building for energy science.

| Jun 11, 2013

Finnish elevator technology could facilitate supertall building design

KONE Corporation has announced a new elevator technology that could make it possible for supertall buildings to reach new heights by eliminating several problems of existing elevator technology. The firm's new UltraRope hoisting system uses a rope with a carbon-fiber core and high-friction coating, rather than conventional steel rope.

| Jun 10, 2013

Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

When the Lake Washington School District outside Seattle needed a new high school built on an ambitious permitting and construction schedule of seven months, modular construction proved to be an ideal solution.

| Jun 7, 2013

Must see: Building façade made of massive concrete drain pipes

Looking to create a unique atmosphere using natural materials for the Prahran Hotel pub near Melbourne, local architect Techné Architects cleverly incorporated a series of concrete sewer pipes into the building's main façade.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021