Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

3D imaging key to project timetable and cost containment.


By By BD+C Staff | April 19, 2012
When finished, the four-story, 80,000-sf office building will connect to the exi
When finished, the four-story, 80,000-sf office building will connect to the existing 193,000-sf facility and is anticipated to

Nauset Construction has begun foundation work on Phase Two of the National Guard Bureau’s new Joint Force Headquarters at Hanscom Air Force Base, Lincoln, Mass.

When finished, the four-story, 80,000-sf office building will connect to the existing 193,000-sf facility and is anticipated to be completed by May of 2013.

The construction of the building and connections to the existing facility have been well coordinated by Nauset’s BIM Management Team, which used 3D modeling to detect structural clashes. 

The new facility will have its own air handling units and heating and cooling systems, but the water, fire protection, and electrical systems will be central to the two phases.  

Designed to resist the effects of earthquake motions, the facility will house classrooms with raised computer access flooring, heated storage and vehicle ready work bays. The foundation will consist of reinforced concrete footings and floor slab with steel framed masonry walls, aluminum windows, and a metal paneled roof system with integrated gutters. The HVAC system will include three 2,000 MBH gas fired boilers, two 140 ton electric air-cooled chillers and air handlers with multiple zones.

Additional building features will include auxiliary power, fire detection and suppression, security access and surveillance and intrusion detection systems. Extensive hardscaping (roadways, ground level parking, an amphitheater with tiered seating, pedestrian walkways) and landscaping is also part of the project’s scope of work. The LEED Silver rating will be achieved by utilizing energy efficient MEP systems and controls, as well as bio-swales to reduce storm water runoff. Project challenges include close coordination with all subcontractors due to the highly sensitive, occupied and restricted site location. BD+C

Related Stories

Multifamily Housing | Aug 24, 2017

Storage units, lounges most popular indoor and outdoor amenities in multifamily developments

Tenants and condo owners crave extra space for their stuff. Most developers are happy to oblige.

Green | Aug 24, 2017

Business case for WELL still developing after first generation office fitouts completed

The costs ranged from 50 cents to $4 per sf, according to a ULI report. 

Healthcare Facilities | Aug 24, 2017

7 design elements for creating timeless pediatric health environments

A recently published report by Shepley Bulfinch presents pediatric healthcare environments as “incubators for hospital design innovation.”

BD+C University Course | Aug 23, 2017

AIA course: New steel systems add strength and beauty

Advances in R&D are fostering new forms of structural and aesthetic steel.

Market Data | Aug 23, 2017

Architecture Billings Index growth moderates

“The July figures show the continuation of healthy trends in the construction sector of our economy,” said AIA Chief Economist, Kermit Baker.

Architects | Aug 21, 2017

AIA: Architectural salaries exceed gains in the broader economy

AIA’s latest compensation report finds average compensation for staff positions up 2.8% from early 2015.

Sports and Recreational Facilities | Aug 18, 2017

Video: Designing the ideal rugby stadium

HOK invited four world-class rugby players into its London studio to discuss what they would like to see in the rugby stadiums of the future.

Architects | Aug 16, 2017

Staffelbach joins DLR Group

The firm will be merging operations immediately with full integration and the name change to DLR Group| Staffelbach effective October 2.

Multifamily Housing | Aug 9, 2017

Related Companies unveils plans for One Hudson Yards luxury rental residences

The 33-story tower will be positioned on the High Line with views of the Hudson River and downtown Manhattan.

boombox1
boombox2
native1

More In Category

Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021