flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.


September 19, 2012
During the construction of Mountaineer Hall, 129 modules were set and sealed in
During the construction of Mountaineer Hall, 129 modules were set and sealed in 12 days.

As the student population rose at Appalachian State University in Boone, N.C., so did the demand for housing. Because residence officials at the school needed to have a new dormitory in place for the upcoming academic year—and use a method in line with the school’s focus on sustainability—modular construction was the logical choice for one of two dorms on campus.

“After visiting other campuses, we decided a modular style project was the correct approach,” said Tom Kane, director of University Housing.

By using modular, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction. The traditional dorm, a 333-bed suite style hall, opened in August 2012. The modular facility, a 460-bed complex, was finished in just nine months and was ready for students by August 2011.

Even though the project was completed quickly, construction was not without challenges.

“Coordinating the transport of the units to the site without interrupting traffic on campus was a concern from the very beginning because of the sharp turn and incline entering the site,” said project manager Dustin Hunter of Hunter Saak Modular. “Safety was our number one concern from the very beginning.”

Once finished, Mountaineer Hall became a beautiful home for students. The 97,000-sf, brick-exterior facility features two-person hotel style rooms with individual bathrooms for increased student privacy. Common areas on each floor lend a feeling of community between the residents.

Not only is the dorm attractive and comfortable, it is LEED Gold certified. The facility received a total of 68 points based on its energy-saving and sustainability features. (Sixty-five points are needed to receive Gold certification). LEED-certified homes complete a technically rigorous process that often includes a home energy (HERS) rating and onsite inspections to verify that the home is built to be energy and water efficient, environmentally sound and a healthier place to live.

The building’s energy and water conserving features include energy-efficient, tinted windows and a 40-panel solar thermal system to provide hot water.? Site stewardship involved erosion control measures taken during construction, landscaping and storm water controls.

Mold-resistant drywall was used throughout the entire building, improving future indoor air quality. The same type of drywall was placed throughout the building to reduce the amount of drywall waste.

Pre-built floor assembly was utilized at the factory to lessen production time. Identical boxes with an average size of 12- x 64- x 10-ft allowed for shortened production and installation time. The dormitory was 80 percent complete when it arrived on site, lessening the time spent on trim work and finishing on site.

All utility chases were designed to be accessed from the building exterior, eliminating unnecessary down time when crane setting the units. The modules were set and sealed in 12 days.

With its outstanding design features, Mountaineer Hall received Honorable Mention in the Permanent Commercial Housing: Over 10,000 Square Feet category in the Modular Building Institute’s 2012 Awards of Distinction. The modular contractor on the project was Hunter Saak Modular with affiliates Clayton Building Solutions and R&S Tavares.

For more information about the project, visit Hunter Saak Modular.

The Modular Building Institute (MBI) is the international non-profit trade association serving the modular construction industry. Members are suppliers, manufacturers and contractors engaged in all aspects of modular projects from complex multi-story solutions to temporary accommodations.

As the Voice of Commercial Modular Construction, it is MBI's mission to expand the use of offsite construction through innovative construction practices, outreach and education to the construction community and customers, and recognition of high quality modular designs and facilities. To learn more about modular construction, go to www.modular.org. +

Related Stories

| May 1, 2012

White paper discusses benefits of diaphragm and piston flushometer valves

The white paper highlights considerations that impact which type of technology is most appropriate for various restroom environments.

| May 1, 2012

Time-lapse video: World Trade Center, New York

One World Trade Center, being built at the site of the fallen twin towers, surpassed the Empire State Building on Monday as the tallest building in New York.

| May 1, 2012

Bruce E. Brooks Associates announces new commissioning subsidiary

Brooks + Wright Commissioning to be led by Will Wright.

| May 1, 2012

Young rejoins Altoon Partners

Takes on role of director of strategic development.

| May 1, 2012

Gilbane to build $100 million cranberries manufacturing facility

Gilbane to provide design build services for a new Lean manufacturing facility for Ocean Spray Cranberries Inc., beverage products.

| May 1, 2012

Construction is underway on MLK ambulatory care center in L.A.

Featuring a variety of sustainable features, the new facility is designed to achieve LEED Gold Certification.

| Apr 30, 2012

Virginia Commonwealth unveils design for Arts Institution

Institute for Contemporary Art will serve as a catalyst for exhibitions, programs, research and collaboration.

| Apr 30, 2012

Summit Design + Build completes build-out for Office Concepts

The project is seeking LEED ID Silver certification from the U.S. Green Building Council.

| Apr 30, 2012

HSA Commercial selected as consultant for Orland Park’s Main Street Triangle project

HSA will be responsible for designing an overall mixed-use merchandise plan, attracting a unique retail tenant mix and completing leases with prospective tenants.

| Apr 30, 2012

Gilbane to manage retrofit of the Fraunhofer CSE R&B structure

Building is a first-of-its-kind research and demonstration building for sustainable technologies in Boston's Innovation District.

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021