Modular fire station allows for possible future reconfigurations

Modular Building

Modular fire station allows for possible future reconfigurations

Rancho Mission Viejo’s Fire Station 67 deployed offsite fabrication and rapid onsite assembly, resulting in a construction timeline of six months.


By Novid Parsi, Contributing Editor | February 6, 2024
Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67, Rancho Mission Viejo, Calif. Photo © Nic Lehoux, courtesy Wittman Estes

In Southern California’s Rancho Mission Viejo (RMV), Fire Station 67 has been designed and constructed as a prefab, modular build—enabling faster completion and future reconfiguration.

Designed by Seattle-based Wittman Estes, the 4,667-sf station was prefabricated offsite as 10 modules that were then assembled onsite. The offsite fabrication and rapid assembly led to a streamlined design, documentation, and permitting process. This approach allowed for parallel site development work in California and factory construction in Nevada, resulting in a construction timeline of six months. 

Fire Station 67: Modular System

The modular system also allows for relocation and reconfiguration. The sturdy, durable steel modules can be easily transported and rearranged for possible future uses, such as an environmental learning center for RMV.

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Fire Station 67. Photo © Nic Lehoux, courtesy Wittman Estes

Fire Station 67 includes a vehicle bay for two fire trucks, six sleeping rooms, a day room, kitchen/dining room, dispatch/workspace, and a captain’s office. The 12-foot modules were assembled around a shaded, semi-protected central courtyard.

Construction Strategy

The building configuration enables the firefighters to serve the public quickly while also feeling calm and privacy. The north-facing public entry, captain’s office, and dispatch room face the neighborhood. The more active areas, including break room, kitchen, and fitness rooms, face east toward the firetrucks. And the sleeping rooms and bathrooms are located in a quiet zone in the west. The firetruck bay is painted bright red, while the interior spaces have a neutral, tranquil palette.

Modular construction plan of fire department

In response to climate change and the rising risk of wildfires, the prefab structure is clad in fireproof, corrugated steel siding. To improve indoor air quality, Wittman Estes designed an open-air apparatus bay to bring in fresh outside air and eliminate the need for large exhaust machines.

On the Building Team:
Clients: Orange County Fire Authority and Rancho Mission Viejo
Architect: Wittman Estes
Interior designer: Birsel+Seck
Structural engineer: DCI Engineers
Landscape architect: Land Concern
Civil engineer: Fuscoe Engineering
GC: Xtreme Cubes 

Modular fire station, Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes
Rancho Mission Viejo’s Fire Station 67
Photo © Nic Lehoux, courtesy Wittman Estes

Related Stories

Government Buildings | Oct 5, 2018

Six-story courthouse under construction in Nashville

Fentress Architects, Michael Graves Architecture & Design, and Hensel Phelps Construction Company are collaborating on designing and building the facility.

| May 24, 2018

Accelerate Live! talk: Security and the built environment: Insights from an embassy designer

In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), embassy designer Tom Jacobs explores ways that provide the needed protection while keeping intact the representational and inspirational qualities of a design.

Government Buildings | Apr 26, 2018

DLR Group’s design for the new Lansing Correctional Facility focuses on energy-efficiency

JE Dunn will manage the design and construction of the Kansas-based facility.

Reconstruction & Renovation | Feb 7, 2018

Renovations begin on an underground facility that is investigating the nature of dark matter

This LEO A DALY-designed project makes way to produce the world’s most sensitive detector to this point.

Government Buildings | Dec 11, 2017

Is this the world’s most humane prison?

The C.F. Møller-designed prison’s architecture supports the inmates’ and staff’s mental and physical well-being.

Architects | Oct 11, 2017

Architects to policymakers: Buildings are infrastructure, too

Left out of this ongoing national debate over infrastructure are the nation’s other public buildings: the libraries, community centers, courthouses, community college buildings, affordable housing developments, and justice facilities.

Giants 400 | Sep 28, 2017

Top 85 government construction firms

Turner Construction Co., PCL Construction Enterprises, and Clark Group top BD+C’s ranking of the nation’s largest government sector contractors and construction management firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Sep 28, 2017

Top 55 government engineering firms

WSP, AECOM, and Arup top BD+C’s ranking of the nation’s largest government sector engineering and EA firms, as reported in the 2017 Giants 300 Report.

Giants 400 | Sep 27, 2017

Top 95 government architecture firms

Stantec, HOK, and Gensler top BD+C’s ranking of the nation’s largest government sector architecture and AE firms, as reported in the 2017 Giants 300 Report.

boombox1
boombox2
native1

More In Category




Laboratories

The Department of Energy breaks ground on the Princeton Plasma Innovation Center

In Princeton, N.J., the U.S. Department of Energy’s Princeton Plasma Physics Laboratory (PPPL) has broken ground on the Princeton Plasma Innovation Center (PPIC), a state-of-the-art office and laboratory building. Designed and constructed by SmithGroup, the $109.7 million facility will provide space for research supporting PPPL’s expanded mission into microelectronics, quantum sensors and devices, and sustainability sciences. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021