MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

MILITARY GIANTS: Cross-laminated timber construction gets a salute from the Army

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels the Army expects to cut a 20-year timetable for repairs and replacement of its lodging down to eight years.


By David Malone, Associate Editor | August 15, 2016

A construction crew installs one of 1,200 prefabricated cross-laminated timber (CLT) wall panels that make up the 92-room Candlewood Suites at Redstone Arsenal, Huntsville, Ala. Leadlease was the GC, developer, and owner on the project. It is the nation’s first all-CLT hotel project. Photo courtesy of Lendlease.

The United States Army has enough on its plate without having to worry about operating as a hotel manager, too.  

TOP 30 MILITARY ARCHITECTURE FIRMS
Rank, Firm, 2015 Revenue
1. HDR $24,971,124
2. Clark Nexsen $13,005,940
3. Guernsey $10,279,317
4. EwingCole $8,541,000
5. RS&H $8,100,000
6. Integrus Architecture $8,054,265
7. Leo A Daly $6,179,243
8. VOA Associates $4,600,000
9. Morris Architects $4,227,000
10. Emersion Design $4,095,748

SEE FULL LIST 

 

TOP 40 MILITARY CONSTRUCTION FIRMS
Rank, Firm, 2015 Revenue
1. Fluor Corp. $823,562,993
2. Walsh Group, The $382,116,917
3. Hensel Phelps $340,673,000
4. Gilbane Building Co. $303,821,000
5. Lendlease $269,240,000
6. Whiting-Turner Contracting Co., The $180,266,105
7. Balfour Beatty US $167,548,244
8. Turner Construction Co. $137,117,144
9. McCarthy Holdings $121,411,531
10. Haskell $81,252,088

SEE FULL LIST

 

TOP 40 MILITARY ENGINEERING FIRMS
Rank, Firm, 2015 Revenue
1. Jacobs $67,384,666
2. AECOM $50,000,000
3. Burns & McDonnell $41,464,789
4. Benham Design $15,481,228
5. Sherlock, Smith & Adams $14,439,000
6. Thornton Tomasetti $10,840,435
7. Jensen Hughes $8,068,991
8. Dewberry $5,353,171
9. RMF Engineering $5,028,000
10. Woolpert $4,083,332

SEE FULL LIST

On the heels of a U.S. Government Accountability Office report that showed that more than 80% of Army lodging needed repairs or replacement—at an estimated price tag of $1.8 billion over 20 years—the Army kicked its Privatization of Army Lodging (PAL) program into high gear.

By privatizing the construction, renovation, operation, maintenance, and ownership of its hotels (it is the only military branch to do so), the Army expects to cut that 20-year timetable down to eight years. 

Lendlease is a key partner in the PAL program, serving as the exclusive developer and owner of the hotels (the Army owns the land). InterContinental Hotels Group (IHG) is the PAL hotel operator under the Holiday Inn Express brand (for renovated Army hotels) and Candlewood Suites name (for newly constructed hotels).

The relationship between the Department of Defense, the Army, Lendlease, and IHG has produced lodging that has far exceeded anything created before PAL went into effect. For instance, the 310-room extended-stay hotel built on Joint Base San Antonio, completed in 2014, is the largest Candlewood Suites in the world.

The recently completed 92-room Candlewood Suites at Redstone Arsenal in Huntsville, Ala., is the first cross-laminated timber structure on a U.S. military installation and the first all-CLT hotel under any ownership type in the country.

Lendlease’s use of CLT, which is made of several layers of pressed lumber board stacked in alternating directions, is not a surprise. The company has committed $1 billion over the next five years to its Sydney, Australia-based startup, Design Make, which is dedicated to manufacturing prefabricated building components such as CLT.

Despite some early obstacles, such as meeting the highly restrictive military Anti-Terrorism and Force Protection requirements, the Building Team found that CLT construction was a great solution for the Redstone Arsenal project. Testing showed that the material performed well against the ATFP requirements due to its ability to carry load in varying directions.

“Labor scarcity, labor cost issues, schedule concerns, and foundation issues are all challenges that make CLT an attractive proposition,” says Lendlease’s Murray Woolcock, Executive General Manager, Strategic Business Units.

The Candlewood Suites on Redstone Arsenal totals 62,688 sf and can house 492 occupants. The structure used 1,200 CLT wall panels and 200,000 CLT fasteners. It is the first PAL structure to use prefabricated bathroom pods, which further helped to accelerate the construction schedule and reduce on-site waste.

By using prefabricated CLT, the Candlewood Suites was erected in just 10 working weeks by an 11-person crew, a 37% speed increase compared to conventional framing materials and methods for a similar-sized structure, according to Lendlease. 

The Redstone Arsenal hotel represents a small portion of the PAL program, which encompasses 12,492 guestrooms across 41 Army installations. Because CLT lends itself to structures with a repetitive room types, such as hotels, there is a good chance the Redstone Arsenal project will not be the only building on an Army base to utilize the material.

“Lendlease is currently evaluating numerous sites in our PAL portfolio to implement the use of CLT,” says Woolcock. “We are confident that CLT will gain traction in many areas, and Lendlease is well positioned to grow our platform off the back of the successful delivery of Redstone Arsenal.”

House approves $81B military Construction bill

With a vote of 277 to 147, the House on May 19 passed the Military Construction and Veterans Affairs bill, which, if enacted, would provide $81.6 billion in discretionary funding for the sectors in 2017. The total is $1.8 billion more than the 2016 budget, but $1.2 billion short of what President Obama requested.

Contained within the bill is funding to house, train, and equip military personnel, provide housing and services to military families, and maintain infrastructure. 

Nearly 10% of the total ($7.9 billion) would be used for large- and small-scale military construction projects at military bases in the U.S. and abroad. The allocation marks a $305 million decrease from fiscal year 2016, but is $250 million more than the President’s request. 

Other allocations of note: 

• $172 million for Overseas Contingency Operations and European Reassurance Initiative projects involving overseas bases

• $1.3 billion for the construction, operation, and maintenance of military family housing; while meeting the President’s budget request, it is $84 million off the budgeted amount in FY2015

• $304 million for the construction and alteration of military medical facilities

• $673 million for construction projects at National Guard and Reserve facilities across 21 states

• $900 million for VA construction projects

• $246 million for safety improvements and infrastructure work at DOD Education Activities facilities.

More on the bill at: http://bit.ly/28L8vwb.

 

RETURN TO THE GIANTS 300 LANDING PAGE

Related Stories

Office Buildings | Jan 19, 2024

How to strengthen office design as employees return to work

Adam James, AIA, Senior Architect, Design Collaborative, shares office design tips for the increasingly dynamic workplace.

Modular Building | Jan 19, 2024

Building with shipping containers not as eco-friendly as it seems

With millions of shipping containers lying empty at ports around the world, it may seem like repurposing them to construct buildings would be a clear environmental winner. The reality of building with shipping containers is complicated, though, and in many cases isn’t a net-positive for the environment, critics charge, according to a report by NPR's Chloe Veltman.

Adaptive Reuse | Jan 18, 2024

Coca-Cola packaging warehouse transformed into mixed-use complex

The 250,000-sf structure is located along a now defunct railroad line that forms the footprint for the city’s multi-phase Beltline pedestrian/bike path that will eventually loop around the city.

Sponsored | BD+C University Course | Jan 17, 2024

Waterproofing deep foundations for new construction

This continuing education course, by Walter P Moore's Amos Chan, P.E., BECxP, CxA+BE, covers design considerations for below-grade waterproofing for new construction, the types of below-grade systems available, and specific concerns associated with waterproofing deep foundations.

Sponsored | Performing Arts Centers | Jan 17, 2024

Performance-based facilities for performing arts boost the bottom line

A look at design trends for “budget-wise” performing arts facilities reveals ways in which well-planned and well-built facilities help performers and audiences get the most out of the arts. This continuing education course is worth 1.0 AIA learning unit.

Giants 400 | Jan 15, 2024

Top 130 Hospital Facility Architecture Firms for 2023

HKS, HDR, Stantec, CannonDesign, and Page Southerland Page top BD+C's ranking of the nation's largest hospital facility architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.

Airports | Jan 15, 2024

How to keep airports functional during construction

Gensler's aviation experts share new ideas about how to make the airport construction process better moving forward.

Adaptive Reuse | Jan 12, 2024

Office-to-residential conversions put pressure on curbside management and parking

With many office and commercial buildings being converted to residential use, two important issues—curbside management and parking—are sometimes not given their due attention. Cities need to assess how vehicle storage, bike and bus lanes, and drop-off zones in front of buildings may need to change because of office-to-residential conversions.

MFPRO+ News | Jan 12, 2024

As demand rises for EV chargers at multifamily housing properties, options and incentives multiply

As electric vehicle sales continue to increase, more renters are looking for apartments that offer charging options.

Student Housing | Jan 12, 2024

UC Berkeley uses shipping containers to block protestors of student housing project

The University of California at Berkeley took the drastic step of erecting a wall of shipping containers to keep protestors out of a site of a planned student housing complex. The $312 million project would provide badly needed housing at the site of People’s Park. 

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021