More than 130,000 sf of Metl-Span CF36R insulated panels were utilized to re-roof the 8-building Haughton Middle School complex in Haughton, LA. The 2 ½ ft. panels were finished in Cool Bright Red and replaced a standing seam metal roof that was not performing properly.
“The old roof had been a problem for years,” said Lauren Marchive, project architect with Newman Marchive Carlisle, Inc., Shreveport, “and the Bossier Parish School Board wanted it gone.”
The design team researched three options:
- Removing the roof and installing decking with a new roof over it
- Using a single ply membrane system with insulation over the existing roof
- Removing the roof and installing an insulated metal panel system.
After consideration, the School Board determined the insulated metal panel system was the best solution. “Metl-Span was included in our bidding process and was the successful low bidder,” according to Marchive. “We had used Metl-Span roof and wall panels before on a Louisiana Department of Transportation building and the success of that project is what convinced us that this was a good option.”
Other factors that contributed to the selection of the Metl-Span system were thermal insulation qualities and the speed and ease of installation. “School remained in session during the renovation and it was important to minimize the disruption as much as possible,” Marchive said.
Installation of the Metl-Span panels was done by Louisiana Roofing Contractors, LLC, Bossier City, LA. “The biggest challenge was working around the school schedule,” according to Paul Tipton, owner. “We literally tore off the old and installed the new on a daily basis and made the roof watertight overnight, of course.”
The architectural design of the new roof was basically unchanged from the original. “There was quite a variety of different slopes to contend with and lots of details on the dormers,” according to Tipton. “But the system worked really well and achieved the design and performance everyone was looking for.” BD+C
Related Stories
| May 27, 2014
What are your services worth?
The price, cost, and value of design services are explored in a recent Design Intelligence article authored by Scott Simpson, a senior fellow of the Design Futures Council. Value, he explains, represents the difference between “price” and “cost.” SPONSORED CONTENT
| May 27, 2014
Contractors survey reveals improving construction market
The construction industry is on the road to recovery, according to a new survey by Metal Construction News. Most metrics improved from the previous year’s survey, including a 19.4% increase in the average annual gross contracting sales volume. SPONSORED CONTENT
| May 27, 2014
How to develop a dynamic referral system
Compelling your clients to provide you with quality referrals is one of the best ways to build a successful business. Here are ways to ‘train’ your clients to make quality referrals. SPONSORED CONTENT
Sponsored | | May 27, 2014
Grim Hall opens the door to fire safety with fire-rated ceramic glass
For the renovation of Lincoln University’s Grim Hall life sciences building into a state-of-the-art computer facility, Tevebaugh Associates worked to provide students and faculty with improved life safety protection. Updating the 1925-era facility's fire-rated doors was an important component of the project.
| May 26, 2014
New Jersey data centers will manage loads with pods
The two data center facilities totaling almost 430,000 sf for owner Digital Realty Trust will use the company's TK-Flex planning module, allowing for 24 pods.
| May 23, 2014
Big design, small package: AIA Chicago names 2014 Small Project Awards winners
Winning projects include an events center for Mies van der Rohe's landmark Farnsworth House and a new boathouse along the Chicago river.
| May 23, 2014
Top interior design trends: Gensler, HOK, FXFOWLE, Mancini Duffy weigh in
Tech-friendly furniture, “live walls,” sit-stand desks, and circadian lighting are among the emerging trends identified by leading interior designers.
| May 22, 2014
How to measure what matters
Measuring what matters is essential for professional services firms, says author and consultant Tim Williams, particularly as firms continue to experiment with the concept of outcome-based compensation agreements.
| May 22, 2014
BIM-driven prototype turns data centers into a kit of parts
Data center design specialist SPARCH creates a modular scheme for solutions provider Digital Realty.
| May 22, 2014
7 ways it pays to use BIM for data centers
Here’s where AEC firms and owners are getting the most bang for the buck when using BIM/VDC to coordinate data center projects.