Materials shortages, cost spikes throwing Design-Bid-Build process out of whack

Contractors

Materials shortages, cost spikes throwing Design-Bid-Build process out of whack

Delays are commonplace; prices rising faster than expected.


By Peter Fabris, Contributing Editor | October 5, 2022
Material Shortages
Courtesy Pexels.

The traditional Design-Bid-Build delivery process is under considerable stress this year as materials shortages and cost spikes are upending usual practices, according to a new report from JLL.

Delays are “pretty much universal,” a JLL executive says. “Volatility around materials is hitting developer’s wallets at a higher rate than initially anticipated earlier this year,” according to the report.

Customarily, materials purchasing was the last step in the process, but building teams have had to adjust to the new environment by purchasing much sooner. Project managers are involved early in the design phase, and once they have a general idea of specs, they place orders for materials.

Having a cohesive team of designers, architects, contractors, and market researchers is more critical than ever for project success—even on smaller projects. Such an assemblage working in concert can account for fluctuating materials costs and establish realistic timelines to execute the project while minimizing costs and maximizing efficiency.

Related Stories

| Aug 11, 2010

Inspiring Offices: Office Design That Drives Creativity

Office design has always been linked to productivity—how many workers can be reasonably squeezed into a given space—but why isn’t it more frequently linked to creativity? “In general, I don’t think enough people link the design of space to business outcome,” says Janice Linster, partner with the Minneapolis design firm Studio Hive.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.


Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Â