Massive student housing project in Texas will be ready this Fall

University Buildings

Massive student housing project in Texas will be ready this Fall

Developers hope the early opening of some units sets the tone for the community and future rentals.


By John Caulfield, Senior Editor | January 9, 2017

Park West, a 3,400-plus bed student housing complex at Texas A&M, is the university system's fifth public-private parternship in the county. Image: Weitz Company, courtesy of Servitas

Park West is the biggest student housing project under development in the country. Located within 47 acres on the campus of Texas A&M University in College Station, the project will encompass 15 buildings, 2.2 million sf and 3,406 beds. Nearly 1,000 construction workers have been this jobsite daily, and another 100-plus offsite designers, managers and engineers have worked on this project, whose developer, Servitas, with its design-builder and joint-venture partner Weitz Company, have pumped $300 million into the local and state economy.

Last August, Weitz delivered the first 144 beds at Park West, a year ahead of the project’s August 2017 completion date. “On a project of this size, having beds open early can be a tremendous asset,” Michael Short, Servitas’ COO, explains to BD+C. “It starts to set the culture for what it will feel like to live at Park West, and builds awareness and interest among the student body. 

“When Weitz came to us,” he continues, “and said that by moving a few things around, we could have these beds ready earlier than planned, of course we were excited.”

The one- to- four-bedroom studio, apartment, and garden-style units are renting for between $600 to $1,000 per month.

But Short acknowledges that opening part of a student housing project that early is risky because “if we pre-leased these beds and then construction slipped by even a day, it could ruin the reputation of the entire project.”

When a student housing project can’t open when the school year begins, it loses the opportunity to lease those apartments for at least another seminar, or more.

Aside from Weitz, the Building Team includes the Boca Raton, Fla., and Houston offices of PGAL (design partner); Power Design Inc., Kilgore Mechanical, Coleman & Associates Landscape Design, Moss Construction, and Godfrey Construction. Subcontractors include Larry Young Paving and RSL Contractors Ltd.

Park West is the university system’s fifth student housing public-private partnership in Brazos County, joining White Creek Apartments, U Centre at Northgate, Easterwood Airport and Century Square.

Its $368 million development and construction cost—which Short believes is the largest single new-build student housing P3 to this point—was financed upfront with tax-exempt bonds. The project is expected to generate $600 million for the university system of the life of its 30-year ground lease to its owner, the nonprofit National Campus and Community Development-College Station, which paid $18.5 million upfront, and will give back $20 million in revenue per year to the system.

Servitas’ initial management contract is for five years. But Short hopes his company will prove itself to the university so that the service contract would be extended at least the life of the ground lease, and possibly beyond.

 

 

Part of the amenities-rich Park West opened a year early, with the goal of drumming up interest in this project among students and the community. Image: Weitz Company, courtesy of Servitas

 

 

Related Stories

Multifamily Housing | May 8, 2019

Multifamily visionary: AvalonBay’s relentless attention to detail

The nation's fourth-largest owner of apartments holds more than 85,000 apartments in 291 communities. 

| Apr 28, 2019

New York Is NOT Most Expensive City for Apartment Sales Transactions

Data from Marcus & Millichap 2019 U.S. Multifamily Investment Forecast on Average Price/Dwelling Unit in apartment transactions.

Multifamily Housing | Apr 27, 2019

5 noteworthy multifamily developments

Special-needs housing in West Hollywood, Calif., and a warehouse-turned-apartments in the Twin Cities are among the notable multifamily projects to open recently. 

| Apr 26, 2019

Organized Living Offers ‘Century Gray’ Product Finish for Multifamily Storage Systems

Organized Living releases new color option for apartment and condominium storage systems.

Multifamily Housing | Apr 23, 2019

Recharging Edison’s batteries

America’s greatest inventor would have appreciated this project team’s ingenuity and persistence.

Multifamily Housing | Apr 17, 2019

Multifamily real estate trends for 2019 and beyond

Boomers are on the move and Millennials are seeing upward mobility, but issues with affordability and housing product mix persist.

Multifamily Housing | Apr 16, 2019

Multifamily rentals are still alive and kickin’

Apartments are being built, and in goodly number. But not enough of it is affordable.

Multifamily Housing | Apr 12, 2019

NYC officials partner with nonprofit to build modular affordable housing

Thorobird and BACDYS partner with Brooklyn’s FullStack Modular on project.

Multifamily Housing | Apr 11, 2019

St. Augustine Terrace brings affordable housing to the Bronx

Magnusson Architecture + Planning designed the building.

Multifamily Housing | Apr 8, 2019

Priced to sell: DUMBO condo development offers starter units in luxury setting

Designed by ODA New York, 98 Front Street will be loaded with amenities like a salt water pool, co-working spaces, and indoor and outdoor fitness centers.

boombox1
boombox2
native1

More In Category


Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021