Each year, when the calendar strikes August 25, the operations of Perrault Farms kick into high gear.
For the next 35 days, the Toppenish, Wash., facilities operate around the clock to harvest, dry, bale and chill the hops that will be sold to commercial and craft brewers worldwide.
“It’s a very perishable crop,” says Steve Perrault, president of the fourth-generation family business. “Hops are kind of like a wine grape—when they’re ready, they’re ready, and we need to be very efficient at processing them.”
Perrault commissioned new metal buildings to replace the business’ previous cramped and outdated facilities. The buildings are designed to support maximum productivity during the crop’s brief harvesting season.
A 19,530 square-foot hop kiln building is the first stop for the green hop cones after they are stripped from the vines. In this building, propane furnaces blow hot air on the cones to remove excess moisture. The entire process takes about nine hours, 25 percent faster than at the previous facility.
“We’ve cut down our drying time, which has also reduced our propane use and electricity substantially, so it’s a much more sustainable facility,” Perrault says.
After drying, the cones are transported via conveyor to the adjacent 26,000 square-foot hop baling building, where they begin to cool. Ambient air blows through vented air trenches within the concrete floor slab, reducing cone temperature while eliminating the risk of spontaneous combustion.
A four-foot cupola extending the full length of the building allows the moist, hot air to escape out of the roof.
Next, the hop cones are compressed into 200-pound bales, stacked and transported by conveyor to the building’s refrigerated cold room where the temperature is reduced to 28 degrees Fahrenheit.
A second-story office area and conference room at the center of the building overlooks the baling operations, providing a powerful sales tool. The facility also includes a laboratory used in the business’ hop-breeding program as well as an onsite pilot brewery where new varieties of hops can be tested.
The exteriors of both buildings feature metal panels, reinforced concrete tilt-up panels with exposed aggregate finish, and a standing seam metal roof.
“The panels around the buildings contribute to the architectural design and also protect the structures from damage from forklifts and tractors as they maneuver around the site,” says Steve Young, general manager of Concord Construction, the Star builder in Wapato, Wash., that oversaw construction. “The concrete also adds structural strength to the hop baling building when the hops are cooling.”
Extensive use of metal liner wall panels contributes to the structure’s interior aesthetics, and the interior space also features hot dipped galvanized structural steel on all frames, columns and rafters so they won’t be susceptible to rusting from the excess moisture in the air.
The project also includes a 7,500 square-foot equipment cover building.
Because the new facilities process significantly more hops than the previous ones, Perrault Farms has been able to increase the acreage of crops it plants by more than 30 percent.
The new buildings also accommodate the stricter food safety guidelines required by craft brewers, which typically use fresh hops in their brewing process.
“With the craft brewing industry growing so rapidly, food safety is very important to all of us,” Perrault says.
The new complex has definitely impressed other hop farmers in the Yakima Valley, the largest hops-producing region in the U.S.
“Everybody who has gone through the buildings is amazed; it’s one of the top facilities in the industry right now,” Perrault says. “This is something I had to do for the next generations coming up.”
Project construction was completed in 10 months.
“By going with metal buildings from Star Buildings, it really decreases the construction time, which also makes it more cost-effective,” Young says.
Related Stories
Adaptive Reuse | Jul 9, 2018
Work, park, live: Inside Cincinnati’s parking garage turned lifestyle hotel
The Summit hotel and conference center is a converted parking garage that was once a factory.
Architects | Jun 28, 2018
Designing successful maker spaces
The challenge is to design makerspaces that work, spaces that function as a tool for educators to produce better students.
Architects | Jun 27, 2018
Steven A. Lichtenberger joins Leo A Daly as President
He will lead the firm’s global planning, architecture, engineering, and interiors practice worldwide.
Accelerate Live! | Jun 24, 2018
Watch all 19 Accelerate Live! talks on demand
BD+C’s second annual Accelerate Live! AEC innovation conference (May 10, 2018, Chicago) featured talks on AI for construction scheduling, regenerative design, the micro-buildings movement, post-occupancy evaluation, predictive visual data analytics, digital fabrication, and more. Take in all 19 talks on demand.
Building Team | Jun 22, 2018
What owners should know before choosing the design-build project delivery method
Outside of drawing up a well-written contract, owners often overlook a key attribute that can significantly impact the success of a design-build project, writes Skanska’s Julie Hyson.
Architects | Jun 14, 2018
Chicago Architecture Center sets Aug. 31 as opening date
The Center is located at 111 E. Wacker Drive.
Multifamily Housing | Jun 13, 2018
Multifamily visionaries: KTGY’s extraordinary expectations
KTGY Architecture + Planning keeps pushing the boundaries of multifamily housing design in the U.S., Asia, and the Middle East.
| Jun 11, 2018
Accelerate Live! talk: Regenerative design — When sustainability is not enough
In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), HMC’s Eric Carbonnier poses the question: What if buildings could actually rejuvenate ecosystems?
| Jun 11, 2018
Accelerate Live! talk: The smart jobsite — Predictive visual data analytics for proactive project controls
In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), a trio of experts in predictive visual data analytics presents how design-build giant Clayco has leveraged this technology to achieve production efficiency on several construction sites.
| Jun 11, 2018
Accelerate Live! talk: Design innovation at Adrian Smith + Gordon Gill Architecture
In this 15-minute talk at BD+C’s Accelerate Live! conference (May 10, 2018, Chicago), AS+GG’s Anthony Viola takes us behind the magic curtain to illuminate the firm’s methods for nurturing design innovation.