Long Beach, Calif., office tower converted to market rate multifamily housing

Multifamily Housing

Long Beach, Calif., office tower converted to market rate multifamily housing

The $44 million 200 West Ocean project repurposed materials to dramatically lower carbon footprint.


By Peter Fabris, Contributing Editor | January 23, 2023
Long Beach, Calif., office tower converted to market rate multifamily housing
More than 75% of the units have substantial natural ventilation and direct outdoor patios, allowing residents to benefit from cool ocean breezes. Photo: Paul Turang, courtesy Studio One Eleven

A project to convert an underperforming mid-century office tower in Long Beach, Calif., created badly needed market rate housing with a significantly lowered carbon footprint. The adaptive reuse project, composed of 203,177 sf including parking, created 106 apartment units out of a Class B office building that had been vacant for about 10 years.

The $44 million 200 West Ocean project repurposed existing steel and concrete instead of trashing them, resulting in a 69% reduction in embodied carbon, an estimated 3.19 million Kg of CO2, and prevented some 26 million pounds of material from entering the waste stream. 

The design included cutting slots into existing concrete to double the size of all windows, increasing natural daylight, and maximizing views for residents. This transformed an otherwise dark, insular, and flat concrete facade into an inviting, articulated building, producing a more appealing connection between the city fabric and residents.

The massing and floor plans of the building were altered to carve out balconies and outdoor terraces from the façade. More than 75% of the units have substantial natural ventilation and direct outdoor patios, allowing residents to benefit from cool ocean breezes. Recessed patios on the south side of the building reduce heat gain and maximize ocean views.

200 West Ocean long beach housing tower 1839-2229_mod.jpg
Photo: Paul Turang, courtesy Studio One Eleven

Strengthening part of the parking structure roof enabled design firm Studio One Eleven to add a community room, pool, spa, and barbecue area. Outdated mechanical equipment was removed from the roof of the main building, allowing transformation of the rooftop space into eight two-story penthouse townhomes.

The rooftop stretches beyond the glass facade of the top two stories and is lit from below at night. Interior atriums were included in the four inbound penthouse units. By creating an opening in the rooftop, bedrooms without direct windows could have natural light and ventilation as well as dramatic views through the double-height living room beyond.

Residents have just a five-minute walk to public transit that connects to downtown Los Angeles. The front sidewalk connects directly to the Pike, a promenade of dining, retail, and the Long Beach Convention Center.

On the project team:
Developer: Greystar
Design architect: Studio One Eleven
Architect of record: Studio One Eleven
MEP engineer: Donald Dickerson Assoc.
Structural engineer: Labib Funk and Assoc.
Civil engineer: KPFF
Landscape Architect: Mark Tessier Landscape
Construction Manager: JR van Dijs

Photo: Paul Turang, courtesy Studio One Eleven 200 West Ocean
Photo: Paul Turang, courtesy Studio One Eleven

Design essay from architect Studio One Eleven

Here are more details on the project from architect Studio One Eleven:

Originally designed by AC Martin and Associates in 1967, this Class B building was commissioned by the General Telephone Company of California, the largest independent telephone company in the United States during the days of the Bell System, to serve as the headquarters for the southern region. Studio One Eleven was commissioned to repurpose this oceanview building as market rate housing.

Studio One Eleven’s design pays homage to the building’s mid century architectural history and introduces renewed vibrancy with contemporary touches. The original building felt insular with an impenetrable facade and dark windows, so the renovation sought to reverse this relationship with the urban fabric and to invite views and connectivity. The addition of a gray vertical frame over the entry accentuates the building’s presence on Ocean Boulevard. To capitalize on the views and to allow more natural lighting, Studio One Eleven doubled all existing windows in size and cut slots in the concrete bulkhead to make them larger. The outdated rooftop mechanical equipment was removed and two new stories were added to give the building an iconic appearance, furthering the identity of 200 Ocean within a burgeoning downtown.

By drastically changing the floor plans and changing the massing of the building, carving outdoor balconies and terraces from the facade of the building, Studio One Eleven was able to create voluminous, varied, and light-filled units that each have access to the outdoors. The new residential units will have exposed concrete walls in the corridors, tall ceilings and many with balconies with either ocean or city views. Overall, lower units feel connected to the street while upper units are connected to views.

200 West Ocean long beach housing tower Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven

Utilizing the tall ground floor that was originally designed for retail, Studio One Eleven created double height lofts with mezzanines and floor to ceiling windows. On the top floors, inbound townhome units feature interior atriums, created by carving openings in the roof and allowing for interior bedrooms to have direct access to natural light and ventilation. Above the fourth floor, residents have unobstructed views southward over the waterfront, Queen Mary, and Catalina Island beyond, and northward towards downtown Los Angeles and San Gabriel Mountain range beyond. By strengthening part of the parking structure roof, Studio One Eleven was able to add an expansive ground floor amenity deck that features a pool deck and spa, community rooms, and a barbecue area for residents.

Minimizing the overall quantity of material used in a building, especially high-embodied-carbon materials such as concrete, steel, and petrochemical-based insulation products, can significantly reduce the overall embodied carbon of a project. By re-using the existing building for a new purpose, the project results in 69% lowered embodied carbon and 3.19M Kg CO2e emissions avoided, as well as over 26M lbs diverted from the waste stream.

200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Paul Turang, courtesy Studio One Eleven
200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Courtesy Studio One Eleven
200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Courtesy Studio One Eleven
200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Courtesy Studio One Eleven
200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven
200 West Ocean tower Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven
Photo: Paul Turang, courtesy Studio One Eleven

 

Related Stories

Projects | Mar 22, 2022

Austin multifamily project to feature 60 micro-housing apartments

A new 34,364 sf multifamily project, Sixth and Chicon, in Austin, Texas, will feature 60 micro-housing apartments designed for “the urban minimalist.”

Projects | Mar 18, 2022

Former department store transformed into 1 million sf mixed-use complex

Sibley Square, a giant mixed-use complex project that transformed a nearly derelict former department store was recently completed in Rochester, N.Y.

Multifamily Housing | Mar 15, 2022

Multifamily rents climbed 15.4 percent in one year

Multifamily asking rents picked up another $10 in February to reach a national average $1,628, and year-over-year growth recorded a 15.4 percent bump, according to the new Yardi Matrix Multifamily National Report.

Multifamily Housing | Mar 15, 2022

A 42-story tower envelops residents in Vancouver’s natural beauty

The city of Vancouver is world-renowned for the stunning nature that surrounds it: water, beaches, mountains. A 42-story tower, Fifteen Fifteen, will envelop residents in that natural beauty.

Multifamily Housing | Mar 15, 2022

Hermosa Village earns 2021 NAHB Best in American Living Award

Cadence McShane Construction Company received first place in this year's NAHB Best in American Living Award for its Hermosa Village project.

Projects | Mar 11, 2022

Suffolk completes construction of luxury condominium 2000 Ocean

The 38-story glass-encased tower along the beach on 1.3 acres is owned by KAR Properties and designed by TEN Arquitectos. 

Projects | Mar 9, 2022

New 243-unit luxury apartment community opens in St. Paul, Minn.

Waterford Bay, a four-story, 243-unit luxury multifamily development recently opened in St. Paul, Minn.

Mass Timber | Mar 8, 2022

Heavy timber office and boutique residential building breaks ground in Austin

T3 Eastside, a heavy timber office and boutique residential building, recently broke ground in Austin, Texas.

Multifamily Housing | Mar 4, 2022

221,000 renters identify what they want in multifamily housing, post-Covid-19

Fresh data from the 2022 NMHC/Grace Hill Renter Preferences Survey shows how remote work is impacting renters' wants and needs in apartment developments.

Projects | Mar 2, 2022

Manufacturing plant gets second life as a mixed-use development

Wire Park, a mixed-use development being built near Athens, Ga., will feature 130 residential units plus 225,000 square feet of commercial, office, and retail space. About an hour east of downtown Atlanta, the 66-acre development also will boast expansive public greenspace. 

boombox1
boombox2
native1

More In Category

Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Â