Length of North American construction disputes continues to increase

Codes and Standards

Length of North American construction disputes continues to increase

They already far exceed global average.


By Peter fabris, Contributing Editor | July 16, 2018

The average time taken to resolve construction disputes in North America increased to an average of 17.7 months in 2017, an increase of two months from 2016, according to a report released by Arcadis.

Length of disputes in the region far exceeded the global average, the report says. Globally, the length of time to resolve disputes stood at 14.8 months, a one month increase over 2016.

The average value of North American disputes decreased to US $19M in 2017 from $21M in 2016. Globally, the figure stood at US $43.4M, up from $32.5M in 2016.

“Failure to properly administer the contract” remained the most common cause of construction disputes globally, and “errors and/or omissions in the contract documentation” remained the most common cause in North America. With positive economic drivers and larger and more complex projects anticipated this year, there is a critical need to embrace more sophisticated risk management and claims avoidance techniques, including leveraging digitalization, Arcadis says.

Related Stories

AEC Tech | Jun 17, 2016

Driverless cars could soon start impacting commercial, retail project design

Offsite parking and more space for valet parking lines are among the foreseeable changes.

Codes and Standards | Jun 17, 2016

Bay State moves toward single BIM protocol on state projects

Massport’s guidelines a step forward for integrated BIM initiative.  

Multifamily Housing | Jun 14, 2016

San Francisco voters approve tougher affordability requirement on new housing development

Critics charge that the measure may backfire and actually reduce new affordable units.  

Concrete | Jun 13, 2016

American Concrete Institute releases new Guide to Shotcrete

Includes information on application procedures, testing.  

Healthcare Facilities | Jun 10, 2016

Top 10 health technology hazards include some influenced by space design

ECRI Institute’s annual list includes operational and workflow issues.  

Codes and Standards | Jun 9, 2016

Supreme Court ruling could aid developers on properties containing wetlands

Unanimous decision allows landowners to take regulatory decisions straight to court.

Green | Jun 8, 2016

TD Bank Group's renovated Toronto office is first WELL-Certified project under WELL v1

The newly renovated 25,000-sf space achieved gold-level status.

Concrete | Jun 7, 2016

Concrete Institute publishes document providing concrete curing guidance

New curing monitoring techniques included.  

Energy | Jun 7, 2016

Energy modeling payback typically as short as one to two months

Energy modeling is a ‘no-brainer—like checking MPG on a car’

Green | Jun 2, 2016

USGBC offers new LEED pilot credit: Building Material Human Hazard and Exposure Assessment

For assessing human health-related exposure scenarios for construction products.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021