The average time taken to resolve construction disputes in North America increased to an average of 17.7 months in 2017, an increase of two months from 2016, according to a report released by Arcadis.
Length of disputes in the region far exceeded the global average, the report says. Globally, the length of time to resolve disputes stood at 14.8 months, a one month increase over 2016.
The average value of North American disputes decreased to US $19M in 2017 from $21M in 2016. Globally, the figure stood at US $43.4M, up from $32.5M in 2016.
“Failure to properly administer the contract” remained the most common cause of construction disputes globally, and “errors and/or omissions in the contract documentation” remained the most common cause in North America. With positive economic drivers and larger and more complex projects anticipated this year, there is a critical need to embrace more sophisticated risk management and claims avoidance techniques, including leveraging digitalization, Arcadis says.
Related Stories
Codes and Standards | Jan 5, 2017
2018 building energy code upholds efficiency gains
Efforts to scale back efficiency requirements largely defeated.
Codes and Standards | Jan 4, 2017
Low-income housing doesn’t lower neighborhood housing values
A Trulia study contradicts longstanding fears.
Codes and Standards | Jan 3, 2017
Intelligent transportation systems have implications for designers, construction firms
Sensors and Internet of Things devices will have to be embedded in infrastructure.
Codes and Standards | Dec 15, 2016
OSHA releases safety recommendation guide for construction industry
It is said to be most helpful to small and mid-sized contractors.
Codes and Standards | Dec 14, 2016
Cities must invest $375 billion to avoid catastrophic global climate change
C40 Cities Climate Leadership Group advocates low carbon infrastructure.
Codes and Standards | Dec 14, 2016
Resilient construction techniques pay for themselves over lifetime of buildings
Spending $340,000 for resiliency would pay for itself over the lifetime of a $10 million structure.
Codes and Standards | Dec 12, 2016
Dept. of Energy launches program to advance zero energy school design
Six school districts and two states are among the first to mainstream zero energy schools.
Codes and Standards | Dec 9, 2016
California city’s plan for net zero building includes net zero water usage
Santa Monica city services building aims for highest level of sustainability.
Codes and Standards | Dec 8, 2016
WELL and BREEAM to align standards
The goal is to make it easier for projects pursuing both standards.
Codes and Standards | Dec 7, 2016
U.S. lumber industry pushes for import duties on Canadian softwood
The industry claims the product is being sold below fair market value.