L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

Codes and Standards | Aug 6, 2019

New technology, aligning training with local trends among keys to workforce development

Construction industry must also invest in training, recruiting high school students.

Codes and Standards | Aug 1, 2019

Planners, city official rethink parking requirements on new projects

Reducing number of parking spots frees up land for ‘more purposeful’ uses.

Codes and Standards | Jul 31, 2019

USGBC-LA chooses first ‘Net Zero Accelerator’ technologies

Wide range of solutions address numerous environmental challenges.

Codes and Standards | Jul 30, 2019

Solar brokerage will provide financing for small/medium businesses

First to fund solar for smaller-scale commercial operations.

Codes and Standards | Jul 29, 2019

ASCE group unveils structural safety database

Confidential reporting on structural failures, near misses, and other incidents.

Codes and Standards | Jul 26, 2019

Floating landscape infrastructure wins top ASCE innovation prize

Climate resiliency a key theme of entrants.

Codes and Standards | Jul 24, 2019

New York making slow progress on resiliency seven years after Hurricane Sandy

Property owners face many challenges; coastal defense project plans are complex and need more time to plan.

Codes and Standards | Jul 23, 2019

Berkeley, Calif. passes nation’s first ordinance to make new buildings all-electric

No gas hook-ups will be allowed in new houses, apartments, and commercial buildings.

Codes and Standards | Jul 22, 2019

San Francisco office building is city’s first structure certified by BREEAM USA for existing buildings

The Landmark @ One Market is one of San Francisco’s most architecturally distinctive buildings.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021