L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Codes and Standards

L.A.’s expedited permitting process credited with faster approvals on $1 billion project

Parallel Design-Permitting Process includes flagging elements for correction during conceptual design.


By Peter Fabris, Contributing Editor | January 14, 2020

Courtesy Pixabay

The completion of the $1 billion Metropolis development in downtown Los Angeles was aided by the city’s streamlined permitting process, according to the developer.

With the recent completion of the 56-story, 650-unit condominium tower Thea, the development provides 1,500 residences, 350 hotel rooms, and 70,000 sf of retail space. The 6.3-acre Metropolis project broke ground in 2014. Two residential towers, one in 2017 and one in 2018, as well as the Hotel Indigo, are already open.

The developer, Greenland USA, says Los Angeles Department of Buildings and Safety’s Parallel Design-Permitting Process helped it complete the project efficiently and on time. The program allows plan inspectors to check and identify elements that need correction during the conceptual design phase.

Among the benefits to the program:

· Reduces design revisions

· Earlier approvals from other agencies

· Reduced permit processing time

· Earlier starts for contractors   

· Cost savings from a shorter construction timeline

Related Stories

| Sep 1, 2011

Project Aims to Automate Code Compliance Assessment

FIATECH, a consortium of owners from the industrial, power, and retail markets that build large structures, launched a project this year to validate the use of automation technology for code compliance assessment, and to accelerate the regulatory approval process using building models. Long-term objectives include the development of an extensive, open-source rule set library that is approved by industry and regulatory bodies for use by technology developers and code officials.

| Sep 1, 2011

EPA Says Additional Lead Paint Cleaning Rules Not Necessary

The EPA has concluded that current Lead: Renovation, Repair, and Painting Program (LRRP) cleaning requirements and lead-safe work regulations are sufficient to protect the public from lead dust hazards. “Our members have been instrumental in contacting legislators to detail the detrimental impact of the current LRRP," says Richard Walker, American Architectural Manufacturers Association’s president and CEO. “This collective industry voice has prompted the EPA to make the responsible decision to refrain from adding further, unnecessary costs to homeowners under the current economic climate."http://www.aamanet.org/news/1/10/0/all/603/aama-commends-its-members-congress-for-vacating-lrrp-clearance-rule

| Aug 11, 2010

Best AEC Firms of 2011/12

Later this year, we will launch Best AEC Firms 2012. We’re looking for firms that create truly positive workplaces for their AEC professionals and support staff. Keep an eye on this page for entry information. +

boombox1
boombox2
native1

More In Category



Legislation

Efforts to encourage more housing projects on California coast stall

A movement to encourage more housing projects along the California coast has stalled out in the California legislature. Earlier this year, lawmakers, with the backing of some housing activists, introduced a series of bills aimed at making it easier to build apartments and accessory dwelling units along California’s highly regulated coast. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021