Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

New high school built in just seven months thanks to modular construction


By M SPACE | June 10, 2013
When the Lake Washington School District outside Seattle needed a new high school built on an ambitious permitting and construction schedule of seven months, modular construction proved to be an ideal solution.
 
“Conventional construction just wasn’t an option,” said Allan Long, Sr. Project Manager for M SPACE, the modular contractor for the project.
 
The LWSD ran into various permitting issues restricting site work on a new Science, Technology, Engineering and Math (STEM) school that was set to open in the fall of 2012. Since the modular process allows the bulk of construction to be done offsite in a factory, with minimal site disruption, the LWSD chose modular as the solution to its challenges.
 
The school is now serving 300 students, and by 2014, will be at near capacity with 600 9th-12th graders.
 
Integrus Architects, the designer on the project, began working the modular aspect of the project into it from the beginning, according to Yong Sun Lee, project manager with Integrus.
 
 
 
 
“In schematic design, we met with and toured various modular manufacturers’ facilities to understand the fabrication process,” Lee said. 
 
“It was in the early stages that we were sensitive to issues of modular dimensions (transportation widths and heights), structure and material types.  In design development, we maintained communication with the participating modular manufacturers and dealers with constructability/design insight,” she said. 
 
Blazer Industries in Oregon began building the “mods” in April 2012, and M SPACE started craning them into place in July 2012.  The school was constructed in two phases, with the first phase ending in August 2012. M SPACE contracted with Absher Construction as the onsite GC for the civil work, modular construction, roofing, sprinkler system and mechanical, electrical and plumbing.
 
 
 
 
M SPACE began setting the second phase in September 2012 and finished the following month, with the remaining site work completed by March 2013. With the two phases combined, the permanent 65,000 square-foot two-story school has 24 classrooms, a presentation hall, common areas, administrative offices and a nurse’s office. Additional features include photovoltaic panels in part of the roof, storefront windows, power cord reels in the science studios, two-hour rated walls, and light dimming ballasts in fixtures.
 
Four spaces in the school were site built, allowing modular and traditional construction to be combined to best suit the client’s need. The site-built commons has 22-foot ceilings, offering an open and inviting space for students. The top of the commons – the roof mods – were built in the factory, reducing the amount of time that workers had to spend at significant heights, according to Alan Duer, M SPACE Pacific Northwest Territory Manager.
 
“Mixing modular construction with conventional construction proved to be a valid alternative to the old ways of building,” Duer said. 
 
To learn more about the school, please visit the M SPACE website.
 
 
 

Related Stories

Mechanical Systems | Jun 16, 2023

Cogeneration: An efficient, reliable, sustainable alternative to traditional power generation

Cogeneration is more efficient than traditional power generation, reduces carbon emissions, has high returns on the initial investment, improves reliability, and offers a platform for additional renewable resources and energy storage for a facility. But what is cogeneration? And is it suitable for all facilities?

Office Buildings | Jun 15, 2023

An office building near DFW Airport is now home to two Alphabet companies

A five-minute drive from the Dallas-Fort Worth International Airport, the recently built 2999 Olympus is now home to two Alphabet companies: Verily, a life sciences business, and Wing, a drone delivery company. Verily and Wing occupy the top floor (32,000 sf and 4,000 sf, respectively) of the 10-story building, located in the lakeside, work-life-play development of Cypress Waters.

Transit Facilities | Jun 15, 2023

Arlington, Va., transit station will support zero emissions bus fleet

Arlington (Va.) Transit’s new operations and maintenance facility will support a transition of their current bus fleet to Zero Emissions Buses (ZEBs). The facility will reflect a modern industrial design with operational layouts to embrace a functional aesthetic. Intuitive entry points and wayfinding will include biophilic accents.

Urban Planning | Jun 15, 2023

Arizona limits housing projects in Phoenix area over groundwater supply concerns

Arizona will no longer grant certifications for new residential developments in Phoenix, it’s largest city, due to concerns over groundwater supply. The announcement indicates that the Phoenix area, currently the nation’s fastest-growing region in terms of population growth, will not be able to sustain its rapid growth because of limited freshwater resources. 

Multifamily Housing | Jun 15, 2023

Alliance of Pittsburgh building owners slashes carbon emissions by 45%

The Pittsburgh 2030 District, an alliance of property owners in the Pittsburgh area, says that it has reduced carbon emissions by 44.8% below baseline. Begun in 2012 under the guidance of the Green Building Alliance (GBA), the Pittsburgh 2030 District encompasses more than 86 million sf of space within 556 buildings. 

Industry Research | Jun 15, 2023

Exurbs and emerging suburbs having fastest population growth, says Cushman & Wakefield

Recently released county and metro-level population growth data by the U.S. Census Bureau shows that the fastest growing areas are found in exurbs and emerging suburbs. 

Healthcare Facilities | Jun 14, 2023

Design considerations for behavioral health patients

The surrounding environment plays a huge role in the mental state of the occupants of a space, especially behavioral health patients whose perception of safety can be heightened. When patients do not feel comfortable in a space, the relationships between patients and therapists are negatively affected.

Engineers | Jun 14, 2023

The high cost of low maintenance

Walter P Moore’s Javier Balma, PhD, PE, SE, and Webb Wright, PE, identify the primary causes of engineering failures, define proactive versus reactive maintenance, recognize the reasons for deferred maintenance, and identify the financial and safety risks related to deferred maintenance.

University Buildings | Jun 14, 2023

Calif. State University’s new ‘library-plus’ building bridges upper and lower campuses

A three-story “library-plus” building at California State University, East Bay (CSUEB) that ties together the upper and lower campuses was recently completed. The 100,977-sf facility, known as the Collaborative Opportunities for Research & Engagement (“CORE”) Building, is one of the busiest libraries in the CSU system. The previous library served 1.2 million visitors annually.

Higher Education | Jun 14, 2023

Designing higher education facilities without knowing the end users

A team of architects with Page offers five important factors to consider when designing spaces for multiple—and potentially changing—stakeholders.

boombox1
boombox2
native1

More In Category




Museums

UT Dallas opens Morphosis-designed Crow Museum of Asian Art

In Richardson, Tex., the University of Texas at Dallas has opened a second location for the Crow Museum of Asian Art—the first of multiple buildings that will be part of a 12-acre cultural district. When completed, the arts and performance complex, called the Edith and Peter O’Donnell Jr. Athenaeum, will include two museums, a performance hall and music building, a grand plaza, and a dedicated parking structure on the Richardson campus.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021