Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

New high school built in just seven months thanks to modular construction


By M SPACE | June 10, 2013
When the Lake Washington School District outside Seattle needed a new high school built on an ambitious permitting and construction schedule of seven months, modular construction proved to be an ideal solution.
 
“Conventional construction just wasn’t an option,” said Allan Long, Sr. Project Manager for M SPACE, the modular contractor for the project.
 
The LWSD ran into various permitting issues restricting site work on a new Science, Technology, Engineering and Math (STEM) school that was set to open in the fall of 2012. Since the modular process allows the bulk of construction to be done offsite in a factory, with minimal site disruption, the LWSD chose modular as the solution to its challenges.
 
The school is now serving 300 students, and by 2014, will be at near capacity with 600 9th-12th graders.
 
Integrus Architects, the designer on the project, began working the modular aspect of the project into it from the beginning, according to Yong Sun Lee, project manager with Integrus.
 
 
 
 
“In schematic design, we met with and toured various modular manufacturers’ facilities to understand the fabrication process,” Lee said. 
 
“It was in the early stages that we were sensitive to issues of modular dimensions (transportation widths and heights), structure and material types.  In design development, we maintained communication with the participating modular manufacturers and dealers with constructability/design insight,” she said. 
 
Blazer Industries in Oregon began building the “mods” in April 2012, and M SPACE started craning them into place in July 2012.  The school was constructed in two phases, with the first phase ending in August 2012. M SPACE contracted with Absher Construction as the onsite GC for the civil work, modular construction, roofing, sprinkler system and mechanical, electrical and plumbing.
 
 
 
 
M SPACE began setting the second phase in September 2012 and finished the following month, with the remaining site work completed by March 2013. With the two phases combined, the permanent 65,000 square-foot two-story school has 24 classrooms, a presentation hall, common areas, administrative offices and a nurse’s office. Additional features include photovoltaic panels in part of the roof, storefront windows, power cord reels in the science studios, two-hour rated walls, and light dimming ballasts in fixtures.
 
Four spaces in the school were site built, allowing modular and traditional construction to be combined to best suit the client’s need. The site-built commons has 22-foot ceilings, offering an open and inviting space for students. The top of the commons – the roof mods – were built in the factory, reducing the amount of time that workers had to spend at significant heights, according to Alan Duer, M SPACE Pacific Northwest Territory Manager.
 
“Mixing modular construction with conventional construction proved to be a valid alternative to the old ways of building,” Duer said. 
 
To learn more about the school, please visit the M SPACE website.
 
 
 

Related Stories

Building Team Awards | Apr 10, 2015

Anaheim’s soaring intermodal hub

Anaheim's Regional Transportations Intermodal Center is the largest ETFE project in North America.

Building Team Awards | Apr 10, 2015

Virtual collaboration helps complete a hospital in 24 months

PinnacleHealth needed a new hospital STAT! This team delivered it in two years, start to finish.

Building Team Awards | Apr 10, 2015

New arts venue reinvigorates Virginia Tech's campus

The STV-led Building Team creates a world-class performance and arts venue with learning and entrepreneurial dimensions.

BIM and Information Technology | Apr 9, 2015

A carboard box by Google can bring virtual reality to architecture

The global search engine giant has launched a new product, Google Cardboard, that easily allows users to experience virtual reality.

Building Team Awards | Apr 9, 2015

Multifaced fitness center becomes campus landmark

A sloped running track and open-concept design put this Building Team to the test. 

Building Team Awards | Apr 9, 2015

Nation's first LEED-certified bus depot

A bus garage in Harlem shows that even the most mundane of facilities can strut its environmentally sensitive stuff.

Building Team Awards | Apr 9, 2015

Setting the bar for port-of-entry design

Whenever you eat a tomato from Mexico, there’s a one-in-three chance it came through this LEED Gold gateway.

Building Team Awards | Apr 9, 2015

Big D’s billion-dollar baby: New Parkland Hospital Tops the Chart | BD+C

Dallas’s new $1.27 billion public hospital preserves an important civic anchor, Texas-style.

Building Team Awards | Apr 9, 2015

IPD-driven fusion facility serves science and student life in Chicago

In dire need of modern science labs and a student union, North Park University built both—in the same building.

Building Team Awards | Apr 9, 2015

‘Prudent, not opulent’ sets the tone for this Catholic hospital

This Building Team stuck with a project for seven years to get a new hospital built for a faithful client.

boombox1
boombox2
native1

More In Category




Brick and Masonry

A journey through masonry reclad litigation

This blog post by Walter P Moore's Mallory Buckley, RRO, PE, BECxP + CxA+BE, and Bob Hancock, MBA, JD, of Munsch Hardt Kopf & Harr PC, explains the importance of documentation, correspondence between parties, and supporting the claims for a Plaintiff-party, while facilitating continuous use of the facility, on construction litigation projects.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021