The Allen Independent School District in Allen, Texas, will not open its high school's $60 million Eagle Stadium this fall.
The stadium opened in 2012, but cracks recently began appearing throughout the structure, Business Insider reports. Nelson Forensics inspected the stadium and judged that the support structures were not designed to hold the stadium's weight.
Some of the problems include failure to completely fill the concourse deck pan during concrete pours and too much space between stirrups. Overall, the investigators found that the load demand exceeded the building's standards by 10-20% in multiple areas; in a few isolated areas, this number rose to 70%.
Prior to this prelimary report, the stadium's designer, PBK Architects, had said that the cracking was likely a result of concrete shrinkage. Now, WFAA reports, PBK and Pogue Construction, who built the stadium, will pay for the repairs through their insurance. The repairs are estimated at less than $1 million.
During this year's football season, Allen will pay $5,300 per game so that its students can play at a nearby high school.
Below are some photos of the damage and a graphic released by Nelson Forensics (all images courtesy of Business Insider and the Dallas Morning News).
Related Stories
| May 14, 2012
Adrian Smith + Gordon Gill Architecture design Seoul’s Dancing Dragons
Supertall two-tower complex located in Seoul’s Yongsan International Business District.
| May 14, 2012
SMPS and Deltek announce alliance
A/E/C industry leaders partner to advance technology’s role in design firm marketing and business development.
| May 14, 2012
ArchiCAD e-Specs integration unveiled
Architects, engineers and construction professionals use InterSpec’s e-SPECS products on thousands of projects annually to maintain synchronization between construction models, drawings, and project specifications.
| May 11, 2012
2012 White Paper: High-Performance Reconstructed Buildings: The 99% Solution
Download the complete White Paper, Chapters 1-10
| May 11, 2012
Chapter 10 Action Plan: 18 Recommendations for Advancing Sustainability in Reconstructed Buildings
We offer the following recommendations in the hope that they will help step up the pace of high-performance building reconstruction in the U.S. and Canada. We consulted many experts for advice, but these recommendations are solely the responsibility of the editors of Building Design+Construction. We welcome your comments. Please send them to Robert Cassidy, Editorial Director: rcassidy@sgcmail.com.
| May 11, 2012
Chapter 9 The Key to Commissioning That Works? It Never Stops
Why commissioning for existing and renovated buildings needs to be continuous to be effective.
| May 11, 2012
Chapter 8 High-Performance Reconstruction and Historic Preservation: Conflict and Opportunity
What historic preservationists and energy-performance advocates can learn from each other.
| May 11, 2012
VFA to acquire Altus Group's Capital Planning division
Strategic move strengthens VFA's facilities capital planning market osition in North America.
| May 11, 2012
Betz promoted to senior vice president for McCarthy’s San Diego Office
He will oversee client relations, estimating, office operations and personnel as well as integration of the company’s scheduling, safety and contracts departments.
| May 11, 2012
CRSI appoints Brace chairman
Stevens also elected to board of directors and vice-chair.