The U.S. Green Building Council awarded the Joliet Junior College (JJC) Facility Services Building a LEED New Construction 2009 Gold certification – making the Facility Services Building the first of its kind on a higher education campus to receive this level of certification.
Designed by Legat Architects and built by Gilbane, the Facility Services Building’s new mechanical and electrical systems resulted in a 42% reduction in energy use and an annual savings of approximately 37% in operating costs.
Gilbane oversaw the procurement, installation and commissioning of all the LEED systems, working with contractors to ensure that they used LEED-compliant materials and submitting the documentation for all of the LEED construction-related points. The team also worked with JJC to lead a significant construction waste recycling effort.
Sustainable elements of the building include:
- Geothermal HVAC system to reduce heating and cooling loads
- Reflective roof surface to reduce heat gain
- Solar heat collectors tied to outside air intake to minimize the amount of energy used to heat the inside of the building
- Use of LED lighting in all areas of the building
- Motion sensors for lighting in occupied spaces
- Operable, high-efficiency windows to improve ventilation and bring in fresh air
- More than 75% of construction waste diverted from landfills
- Use of recycled and locally sourced materials during construction
- Low-VOC paints, adhesives, and sealants used in all spaces of the building
JJC’s Facility Services Building is part of a $220 million master plan aimed at transforming the college’s approach to sustainability and efficiency. The 42,500-square-foot facility replaces several scattered temporary buildings that previously housed the custodial, maintenance, planning/construction and roads/grounds staff at JJC. BD+C
Related Stories
| Mar 19, 2012
Skanska promotes Saunders to VP/GM of Bayshore Concrete Products
During his more than 13 years with Bayshore, Saunders has provided products for Victory Bridge in New Jersey, Route 52 Causeway in Ocean City, N.J., and for numerous piers at Naval Station Norfolk and the Norfolk Naval Shipyard.
| Mar 19, 2012
Smith Carter joins forces with Genivar
Smith Carter has a workforce of some 190 employees and designs complex buildings in challenging environments.
| Mar 19, 2012
HKS Selected for Baylor Medical Center at Waxahachie
Baylor Medical Center at Waxahachiewill incorporate advanced technology including telemedicine, digital imaging, remote patient monitoring, electronic medical records and computer patient records.
| Mar 19, 2012
Mixed-use project redefines Midtown District in Plantation, Fla.
Stiles Construction is building the residential complex, which is one of Broward County’s first multifamily rental communities designed to achieve LEED certification from the USGBC.
| Mar 16, 2012
Temporary fix to CityCenter's Harmon would cost $2 million, contractor says
By contrast, CityCenter half-owner and developer MGM Resorts International determined last year that the Harmon would collapse in a strong quake and can't be fixed in an economical way. It favors implosion at a cost of $30 million.
| Mar 16, 2012
Work on Oxnard, Calif. shopping center resumes after a three-year hiatus
Stalled since 2009, developers of the Collection at RiverPark decided to restart construction on the outdoor mall.
| Mar 16, 2012
Stego embarks on HPD Pilot Program
Vapor barrier manufacturer strives to provide better green choices to designers and builders.
| Mar 16, 2012
Marvin Windows and Doors accepting entries for fourth-annual myMarvin Architect’s Challenge
Architects in U.S. and abroad offered the chance to showcase their very best work.
| Mar 14, 2012
Hearing to decide fate of unfinished Harmon in Las Vegas under way
The testimony began with CityCenter consulting engineer Chukwuma Ekwueme methodically showing photo after photo of parts of the Harmon, where he and his team had chipped away the concrete pillars and beams to examine the steel reinforcing bars inside.