A jobsite dashboard is helping Clark Construction take the drudgery out of managing punch lists

Building Technology

A jobsite dashboard is helping Clark Construction take the drudgery out of managing punch lists

Turnover Vision is the latest example of Clark digitizing its construction management process.


By John Caulfield, Senior Editor | April 10, 2018

Clark Construction now uses Turnover Vision on all of its projects. The algorithm driving this mobile app also helps the contractor anticipate problems. Image: Clark Construction

Last year, Clark Construction started deploying Turnover Vision, an interactive punch list management application developed by the firm’s Research & Development Group, which combines punch list and scheduling data to optimize a project’s work plan.

Turnover Vision analyzes big data from a project’s punch list and organizes them into interactive heat maps and graphs. Using simplified architectural floor plans as the common communications platform, the dashboard provides a breakdown of real-time punch list status and turnover productivity rates.

The algorithm driving Turnover Vision’s dashboard “also allows us to anticipate productivity in the punch list phase,” says David Barritt-Flatt, director of research and development for Clark Construction in Bethesda, Md. The goal of this tool, he explains, is to reduce project closeout timelines and to improve the client experience through increased trust and transparency.

Prior to the implementation of Turnover Vision, which Clark piloted in 2016, the firm’s project teams were spending more than 15 hours each week documenting punch list items, manually updating PDF versions of turnover maps, and meeting with clients to discuss turnover rates.

Barritt-Flatt elaborates that deploying this dashboard not only eliminates a lot of administrative labor, but also “gives our subcontractors better direction” to identify and solve problems quicker. Equally important, the dashboard frees Clark’s engineers to focus on their primary responsibilities because they are spending a lot less time doing paperwork.

“One of our vice presidents, a construction leader, said that Turnover Vision was like adding a half- to a full-time employee to the project,” says Barritt-Flatt. He adds that clients now want Clark to adapt the app to go beyond producing punch list reports, so the contractor is now investigating Turnover Vision’s possible application for jobsite safety.

“We view this as part of our evolution to digitize our construction management approach,” he says.

Turnover Vision uses simplified architectural floor plans as its common communications platform. Image: Clark Construction

 

In the November 2017 edition of its company magazine Superstructure, Clark Construction singled out R&D Group team member Ryan Nam as the driving force behind Turnover Vision. While working on a multifamily residential project, Nam came up with the idea of an interactive dashboard to leverage Clark’s practices by merging big data with visual analytics.

Turnover Vision debuted last year at the recently completed Central Place residential tower in Arlington, Va., and was expanded to Clark’s residential and mixed-use projects across the country.

Clark started with residential and hospitality projects because they typically have a lot of room design iteration. But with tweaks, the firm is now using Turnover Vision on nearly all of its projects, including museums—one of Clark Construction’s specialties.

Related Stories

| Feb 27, 2012

Consigli complete first building for Bigelow Ocean Sciences Campus

Designed by WBRC Architects Engineers in association with Perkins + Will.

| Feb 26, 2012

Milwaukee U-Haul facility receives LEED-CI Silver

The new elements of the facility now include: efficient lighting with day-lighting controls and occupancy sensors, a high-efficiency HVAC system used in conjunction with a newly constructed thermal envelope to help reduce energy consumption, and the installation of low-flow fixtures to reduce water consumption.

| Feb 22, 2012

Suffolk awarded Boston post office renovation project

Renovation of art deco landmark will add 21,000 square feet of retail and 110 new parking spaces.

| Feb 21, 2012

PV America West conference showcases solar growth market

Solar industry gathers March 19-21, 2012 in San Jose to discuss technology, market development and policy.

| Feb 20, 2012

All Steel names Breagy director of metro New York

Breagy is responsible for overseeing this region’s sales team while strategically coordinating the sales efforts of Allsteel dealers and representatives in the tri-state area.

| Feb 16, 2012

Summit Design + Build begins build-out for Emmi Solutions in Chicago

The new headquarters will total 20,455 sq. ft. and feature a loft-style space with exposed masonry and mechanical systems, 15 foot clear ceilings, two large rooftop skylights and private offices with full glass partition walls.

| Feb 13, 2012

Center for Sustainable Building Research launches CommercialWindows.org

Resource aims at reducing commercial operating costs and energy consumption.

| Feb 8, 2012

World’s tallest solar PV-installation

The solar array is at the elevation of 737 feet, making the building the tallest in the world with a solar PV-installation on its roof.

| Feb 2, 2012

Call for Entries: 2012 Building Team Awards. Deadline March 2, 2012

Winning projects will be featured in the May issue of BD+C. 

| Jan 31, 2012

28th Annual Reconstruction Awards: Modern day reconstruction plays out

A savvy Building Team reconstructs a Boston landmark into a multiuse masterpiece for Suffolk University. 

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021