It's official: Norman Foster-designed Harmon hotel and casino to be razed due to structural issues

It's official: Norman Foster-designed Harmon hotel and casino to be razed due to structural issues

Construction of the Las Vegas tower was halted in 2008 after experts discovered faulty steel beams in the structure. Now its owner, MGM, has received permission to demolish the building. 


By BD+C Staff | May 9, 2014
Photo: Vrysxy via Wikimedia Common
Photo: Vrysxy via Wikimedia Common

The long and controversial tale of the Harmon hotel and casino is over: MGM Resorts International has received permission to demolish the tower, Dezeen reports.

The court ruling comes in the midst of the debate between owner MGM and developer Tutor Perini, which has been waged over who is at fault for the building's failure.

Construction of the resort was halted after experts discovered faulty steel beams in the structure. They determined that the beams would not stand up to an earthquake.

Elizabeth Gonzalez, a Clark County District judge, has ordered lawyers on either side to collect outstanding evidence, in effect paving the way for demolition. The demolition will involve the complex being taken apart floor by floor, at a cost of $11.5 million.

Foster + Partners designed the Harmon, which broke ground in 2006. The structural issues were discovered two years into construction.

Some history on the project via Wikipedia:

In late 2008, work on the Harmon Hotel/Condo Tower was stopped after inspectors discovered construction defects: county inspectors discovered improper installation by Pacific Coast Steel, of critical steel reinforcements (rebar) after 15 stories of the building had already been erected.

The error caused a major change in the building's design; instead of being 49 stories, it was reduced to 28 stories with the condominium element, The Harmon Residences removed entirely. At the time, 88 of the 207 condominiums were reserved by buyers who had put 20 percent down. Those buyers were offered refunds or the option to buy in other buildings. 

Related Stories

| May 11, 2012

Chapter 9 The Key to Commissioning That Works? It Never Stops

Why commissioning for existing and renovated buildings needs to be continuous to be effective.

| May 11, 2012

Chapter 8 High-Performance Reconstruction and Historic Preservation: Conflict and Opportunity

What historic preservationists and energy-performance advocates can learn from each other.

| May 11, 2012

VFA to acquire Altus Group's Capital Planning division

Strategic move strengthens VFA's facilities capital planning market osition in North America.

| May 11, 2012

Betz promoted to senior vice president for McCarthy’s San Diego Office

He will oversee client relations, estimating, office operations and personnel as well as integration of the company’s scheduling, safety and contracts departments.

| May 11, 2012

CRSI appoints Brace chairman

Stevens also elected to board of directors and vice-chair.

| May 11, 2012

Dempster named to AIA College of Fellows

Altoon Partners’ technical and construction services leader honored for his contributions.

| May 11, 2012

AIA launches education and training portal

New portal to host Contract Documents training, education resources in one convenient place.

| May 10, 2012

Chapter 7 When Modern Becomes Historic: Preserving the Modernist Building Envelope

This AIA CES Discovery course explores the special reconstruction questions posed by Modern-era buildings.

| May 10, 2012

Chapter 6 Energy Codes + Reconstructed Buildings: 2012 and Beyond

Our experts analyze the next generation of energy and green building codes and how they impact reconstruction.

| May 10, 2012

Chapter 5 LEED-EB and Green Globes CIEB: Rating Sustainable Reconstruction

Certification for existing buildings under these two rating programs has overtaken that for new construction.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021