It's official: Norman Foster-designed Harmon hotel and casino to be razed due to structural issues

It's official: Norman Foster-designed Harmon hotel and casino to be razed due to structural issues

Construction of the Las Vegas tower was halted in 2008 after experts discovered faulty steel beams in the structure. Now its owner, MGM, has received permission to demolish the building. 


By BD+C Staff | May 9, 2014
Photo: Vrysxy via Wikimedia Common
Photo: Vrysxy via Wikimedia Common

The long and controversial tale of the Harmon hotel and casino is over: MGM Resorts International has received permission to demolish the tower, Dezeen reports.

The court ruling comes in the midst of the debate between owner MGM and developer Tutor Perini, which has been waged over who is at fault for the building's failure.

Construction of the resort was halted after experts discovered faulty steel beams in the structure. They determined that the beams would not stand up to an earthquake.

Elizabeth Gonzalez, a Clark County District judge, has ordered lawyers on either side to collect outstanding evidence, in effect paving the way for demolition. The demolition will involve the complex being taken apart floor by floor, at a cost of $11.5 million.

Foster + Partners designed the Harmon, which broke ground in 2006. The structural issues were discovered two years into construction.

Some history on the project via Wikipedia:

In late 2008, work on the Harmon Hotel/Condo Tower was stopped after inspectors discovered construction defects: county inspectors discovered improper installation by Pacific Coast Steel, of critical steel reinforcements (rebar) after 15 stories of the building had already been erected.

The error caused a major change in the building's design; instead of being 49 stories, it was reduced to 28 stories with the condominium element, The Harmon Residences removed entirely. At the time, 88 of the 207 condominiums were reserved by buyers who had put 20 percent down. Those buyers were offered refunds or the option to buy in other buildings. 

Related Stories

Sports and Recreational Facilities | Jul 23, 2015

Japan announces new plan for Olympic Stadium

The country moves on from Zaha Hadid Architects, creators of the original stadium design scrapped last week.

Green | Jul 23, 2015

NASA: U.S. headed for worst droughts in a millennium

Data from NASA shows carbon emissions could be the driving force behind devastating water shortages and record droughts in the western U.S.

Airports | Jul 22, 2015

MUST SEE: JFK airport taps Gensler to design terminal for animals

Pets can enjoy luxurious spa and grooming services before being transported directly to their flight from the terminal.

Office Buildings | Jul 21, 2015

Finally! There's a workplace trend that’s worth embracing

There’s a realization by corporate real estate executives that in order to create a successful workplace, there must be alignment between their people, their place, and the tools they have to do their jobs.

University Buildings | Jul 21, 2015

Maker spaces: Designing places to test, break, and rebuild

Gensler's Kenneth Fisher and Keller Roughton highlight recent maker space projects at MIT and the University of Nebraska that provide just the right mix of equipment, tools, spaces, and disciplines to spark innovation. 

Architects | Jul 21, 2015

Architecture Billings Index at highest mark since 2007

This is the first month in 2015 that all regions are reporting positive business conditions, said AIA Chief Economist Kermit Baker.

BIM and Information Technology | Jul 20, 2015

New stylus brings digital sketching to the next level

Without buttons, users can change the weight of the stylus’ stroke.

Architects | Jul 20, 2015

New York design competition looks to shed the sidewalk shed

New York, which has nearly 200 total miles of sidewalk sheds, is seeking a concept that is practical but that also looks good.

Cultural Facilities | Jul 19, 2015

SET Architects wins design competition for Holocaust Memorial

The design for the memorial in Bologna, Italy, is dominated by two large metal monolithic structures that represent the oppressive wooden bunks in concentration camps in Germany during World War II.

Sports and Recreational Facilities | Jul 17, 2015

Japan scraps Zaha Hadid's Tokyo Olympic Stadium project

The rising price tag was one of the downfalls of the 70-meter-tall, 290,000-sm stadium. In 2014, the cost of the project was 163 billion yen, but that rose to 252 billion yen this year.

boombox1
boombox2
native1

More In Category


Museums

The Tampa Museum of Art will soon undergo a $110 million expansion

In Tampa, Fla., the Tampa Museum of Art will soon undergo a 77,904-sf Centennial Expansion project. The museum plans to reach its $110 million fundraising goal by late 2024 or early 2025 and then break ground. Designed by Weiss/Manfredi, and with construction manager The Beck Group, the expansion will redefine the museum’s surrounding site.



Reconstruction & Renovation

Movement to protect historic buildings raises sharp criticism

While the movement to preserve historic buildings has widespread support, it also has some sharp critics with well-funded opposition groups springing up in recent years. Some opponents are linked to the Stand Together Foundation, founded and bankrolled by the Koch family’s conservative philanthropic organization, according to a column in Governing magazine.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021