It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

Hotel Facilities

It only took 26 days to complete construction on the Crowne Plaza Changi Airport hotel extension

PPVC techniques allowed the project to save time and manpower.


By David Malone, Associate Editor | July 5, 2017

Photo: Patrick Bingham-Hall

The Singapore Changi Airport is, according to the most recent numbers from the Airports Council International, the 17th busiest airport in the world by passenger traffic. With so many people passing through on a daily basis, it was important for the new addition to the Crowne Plaza Changi Airport hotel to be built in as little time as possible.

The new building was Singapore’s first private sector commercial project to use pre-fabricated, pre-finished volumetric construction (PPVC), which led to the addition being built in just 26 days. WOHA designed the original 320-room hotel as well as the 243-room, 103,495-sf addition.

 

Photo: Patrick Bingham-Hall.

 

The use of the PPVC method slashed manpower requirements on site by as much as 45%, reduced overall construction time by 17%, and accomplished both of these with about 40% in manpower savings.

 

Photo: Patrick Bingham-Hall.

 

“The Crowne Plaza Changi Airport hotel extension (CPEX) demonstrates that it is possible to significantly reduce the number of workers required, shorten construction time, improve building quality and even overcome site constraints by changing the way we build,” says Singapore’s Building and Construction Authority CEO John Keung in a release.

 

Photo: Patrick Bingham-Hall.

Related Stories

Products and Materials | Jan 31, 2024

Top building products for January 2024

BD+C Editors break down January's top 15 building products, from SloanStone Quartz Molded Sinks to InvisiWrap SA housewrap.

Airports | Jan 30, 2024

Rafael Viñoly Architects’ design for the new Florence, Italy, airport terminal will feature a rooftop vineyard

At Florence, Italy’s Aeroporto Amerigo Vespucci, the new international airport terminal will feature a fully operating vineyard on the facility’s rooftop. Designed by Rafael Viñoly Architects, the terminal is expected to see over 5.9 million passengers annually. Renderings for the project have recently been released.

Airports | Jan 15, 2024

How to keep airports functional during construction

Gensler's aviation experts share new ideas about how to make the airport construction process better moving forward.

Airports | Dec 4, 2023

4 key innovations and construction trends across airport design

Here are some of the key trends Skanska is seeing in the aviation sector, from congestion solutions to sustainability.

Giants 400 | Nov 13, 2023

Top 60 Airport Facility Construction Firms for 2023

Hensel Phelps, Turner Construction, AECOM, and Walsh Group top BD+C's ranking of the nation's largest airport terminal and airport facilities general contractors and construction management (CM) firms for 2023, as reported in the 2023 Giants 400 Report. 

Giants 400 | Nov 13, 2023

Top 65 Airport Facility Engineering Firms for 2023

AECOM, Jacobs, Arup, Burns & McDonnell, and WSP head BD+C's ranking of the nation's largest airport terminal and airport facilities engineering and engineering architecture (EA) firms for 2023, as reported in the 2023 Giants 400 Report.

Giants 400 | Nov 13, 2023

Top 65 Airport Facility Architecture Firms for 2023

Gensler, Corgan, PGAL, and HOK top BD+C's ranking of the nation's largest airport terminal and airport facilities architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report. 

Building Materials | Oct 2, 2023

Purdue engineers develop intelligent architected materials

Purdue University civil engineers have developed innovative materials that can dissipate energy caused by various physical stresses without sustaining permanent damage.

Products and Materials | Sep 29, 2023

Top building products for September 2023

BD+C Editors break down 15 of the top building products this month, from smart light switches to glass wall systems.

Giants 400 | Aug 22, 2023

Top 115 Architecture Engineering Firms for 2023

Stantec, HDR, Page, HOK, and Arcadis North America top the rankings of the nation's largest architecture engineering (AE) firms for nonresidential building and multifamily housing work, as reported in Building Design+Construction's 2023 Giants 400 Report.

boombox1
boombox2
native1

More In Category



Great Solutions

41 Great Solutions for architects, engineers, and contractors

AI ChatBots, ambient computing, floating MRIs, low-carbon cement, sunshine on demand, next-generation top-down construction. These and 35 other innovations make up our 2024 Great Solutions Report, which highlights fresh ideas and innovations from leading architecture, engineering, and construction firms.


Airports

SOM unveils ‘branching’ structural design for new Satellite Concourse 1 at O’Hare Airport

The Chicago Department of Aviation has revealed the design for Satellite Concourse 1 at O’Hare International Airport, one of the nation’s business airports. Designed by Skidmore, Owings & Merrill (SOM), with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA), and Arup, the concourse will be the first new building in the Terminal Area Program, the largest concourse area expansion and revitalization in the airport’s almost seven-decade history. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021