flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

IPD contract saves time and money for cancer center [2014 Building Team Awards]

IPD contract saves time and money for cancer center [2014 Building Team Awards]

Partners share the risk and reward of extreme collaboration on this LEED Silver project, which relies heavily on Lean principles.


By Julie S. Higginbotham, Senior Editor | July 20, 2014
The new Lawrence + Memorial Hospital Cancer Center will allow patients to receiv
The new Lawrence + Memorial Hospital Cancer Center will allow patients to receive comprehensive oncology services in a single lo

For its Waterford, Conn., Cancer Center, a comprehensive treatment facility affiliated with Dana-Farber Community Cancer Care, Lawrence + Memorial Hospital decided to try something new: true three-party Integrated Project Delivery.

The contractual agreement covered L+M, architecture/engineering firm TRO JB, and construction manager Suffolk Construction, with programming, design, and construction all informed by Lean principles.

To further extend the collaborative theme, this three-party project management team invited three trade partners to participate in an incentive compensation layer, involving a pool consisting of at-risk potential profits.

TRO JB, Suffolk, and three handpicked HVAC/plumbing, electrical, and site work subs would participate in the ICL. If the project came in over budget or exceeded the schedule, the ICL profit pool would be tapped to pay the penalties. If the facility came in under budget or ahead of schedule, the ICL group would get the profit pool plus 50% of the savings, with the hospital pocketing the remaining savings.

Bronze Award
Project Summary

Lawrence + Memorial Hospital Cancer Center
Waterford, Conn.

BUILDING TEAM
Submitting firm: Suffolk Construction (GC/CM)
Owner/developer: Lawrence + Memorial Hospital 
Architect, MEP/FP: TRO JB
Structural: Simpson Gumpertz & Heger
Civil: DiCesare-Bentley Engineers

GENERAL INFORMATION
Project size: 47,000 sf
Construction cost: $24 million (IPD contract value $34.5 million)
Construction period: May 2012 to September 2013
Delivery method: Tri-party integrated project delivery

Early collaboration on the design, schedule, budget, and quality goals was a must for making the plan work. Using 3P (Production Preparation Process) Lean design and pull planning tools, the Building Team was able to make key decisions efficiently. Input from about 70 Cancer Center stakeholders—including administration, medical staff, support staff, patient advocates, and partners from Dana-Farber—was solicited in an intense three-day 3P charrette, which resulted in schematic draft floor plans. 

Only minor changes were needed after this point, testifying to the effectiveness of the event. (The most significant contract alteration, requested by L+M as a value-added item, was a geothermal well field system that will pay for itself in just a few years.)

A co-location center set up in two of L+M’s hospital conference rooms was made available to the Building Team for the duration of the project. This home base proved crucial to ensuring efficient communication and also provided a convenient setting for stakeholder evaluation of mockups. 

As a result of the collaborative efforts, the overall project schedule was reduced by six months, and the facility came in $1.2 million under budget. Actual construction was completed in only 10 months, meeting a “stretch goal” previously set by the client. Streamlined front-end decisions played an important role, including an RFI process that was 80% shorter than the client had previously experienced.

Building Team Awards judges were impressed with the participants’ ability to weigh wants and needs and craft a facility that achieved ambitious goals. The client has engaged Suffolk and TRO JB for a second IPD contract, this time to renovate a three-story medical office building. As with healthcare itself, new ideas about delivery are proving indispensable to positive outcomes.   

Related Stories

| Jan 11, 2013

HMC Architects: In their own voices

See what HMC professionals say about their “Best AEC Firm to Work For”

| Jan 10, 2013

Guide predicts strongest, weakest AEC markets for 2013

2013 Guide to U.S. AEC markets touts apartments, natural gas, senior housing and transmission and distribution.

| Jan 9, 2013

Panasonic and Bluebeam preview new architect app at CES 2013

Panasonic and Bluebeam Software collaborate to develop and introduce the 4K tablet and software to the design and construction industry.

| Jan 3, 2013

Answered prayers

A bold renovation enables a small church to expand its mission on a grand scale.

| Jan 3, 2013

Top BIM/VDC articles of 2011-2012

A compendium of BD+Cs top building information modeling and virtual design + construction articles from 2011-12.

| Jan 3, 2013

8 trends shaping today’s senior housing

The ranks of those age 65 and older are swelling by the thousands every day. Is there an opportunity for your firm in the seniors housing market?

| Jan 2, 2013

Trends Report: New facilities enhance the quality of campus life

Colleges and universities are building state-of-the-art student unions, dining halls, and other non-academic buildings to enrich the campus experience, boost enrollment, and stay competitive.

| Jan 2, 2013

M&A activity at U.S. AEC firms up slightly

Total mergers and acquisitions in the AEC industry hit 171 in 2012, up slight from the 169 deals in 2011.

| Jan 2, 2013

Global data center market to ‘slow’ to 14.3% this year

Total global investment in data centers is expected to slow down somewhat this year but still increase at a respectable 14.3%, according to DCD Intelligence.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021