flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

IPD contract saves time and money for cancer center [2014 Building Team Awards]

IPD contract saves time and money for cancer center [2014 Building Team Awards]

Partners share the risk and reward of extreme collaboration on this LEED Silver project, which relies heavily on Lean principles.


By Julie S. Higginbotham, Senior Editor | July 20, 2014
The new Lawrence + Memorial Hospital Cancer Center will allow patients to receiv
The new Lawrence + Memorial Hospital Cancer Center will allow patients to receive comprehensive oncology services in a single lo

For its Waterford, Conn., Cancer Center, a comprehensive treatment facility affiliated with Dana-Farber Community Cancer Care, Lawrence + Memorial Hospital decided to try something new: true three-party Integrated Project Delivery.

The contractual agreement covered L+M, architecture/engineering firm TRO JB, and construction manager Suffolk Construction, with programming, design, and construction all informed by Lean principles.

To further extend the collaborative theme, this three-party project management team invited three trade partners to participate in an incentive compensation layer, involving a pool consisting of at-risk potential profits.

TRO JB, Suffolk, and three handpicked HVAC/plumbing, electrical, and site work subs would participate in the ICL. If the project came in over budget or exceeded the schedule, the ICL profit pool would be tapped to pay the penalties. If the facility came in under budget or ahead of schedule, the ICL group would get the profit pool plus 50% of the savings, with the hospital pocketing the remaining savings.

Bronze Award
Project Summary

Lawrence + Memorial Hospital Cancer Center
Waterford, Conn.

BUILDING TEAM
Submitting firm: Suffolk Construction (GC/CM)
Owner/developer: Lawrence + Memorial HospitalĀ 
Architect, MEP/FP: TRO JB
Structural: Simpson Gumpertz & Heger
Civil: DiCesare-Bentley Engineers

GENERAL INFORMATION
Project size: 47,000 sf
Construction cost: $24 million (IPD contract value $34.5 million)
Construction period: May 2012 to September 2013
Delivery method: Tri-party integrated project delivery

Early collaboration on the design, schedule, budget, and quality goals was a must for making the plan work. Using 3P (Production Preparation Process) Lean design and pull planning tools, the Building Team was able to make key decisions efficiently. Input from about 70 Cancer Center stakeholdersā€”including administration, medical staff, support staff, patient advocates, and partners from Dana-Farberā€”was solicited in an intense three-day 3P charrette, which resulted in schematic draft floor plans.Ā 

Only minor changes were needed after this point, testifying to the effectiveness of the event. (The most significant contract alteration, requested by L+M as a value-added item, was a geothermal well field system that will pay for itself in just a few years.)

A co-location center set up in two of L+Mā€™s hospital conference rooms was made available to the Building Team for the duration of the project. This home base proved crucial to ensuring efficient communication and also provided a convenient setting for stakeholder evaluation of mockups.Ā 

As a result of the collaborative efforts, the overall project schedule was reduced by six months, and the facility came in $1.2 million under budget. Actual construction was completed in only 10 months, meeting a ā€œstretch goalā€ previously set by the client. Streamlined front-end decisions played an important role, including an RFI process that was 80% shorter than the client had previously experienced.

Building Team Awards judges were impressed with the participantsā€™ ability to weigh wants and needs and craft a facility that achieved ambitious goals. The client has engaged Suffolk and TRO JB for a second IPD contract, this time to renovate a three-story medical office building. As with healthcare itself, new ideas about delivery are proving indispensable to positive outcomes. Ā Ā 

Related Stories

| Nov 5, 2014

AEC firms leverage custom scripts to bridge the ā€˜BIM language gap'

Without a common language linking BIM/VDC software platforms, firms seek out interoperability solutions to assist with the data transfer between design tools.

| Nov 5, 2014

Survey: More than 75% of workload takes place without face-to-face interactions

With the rise of technology, much of the workdayā€”even the most productive morning hoursā€”is spent corresponding via email or conference call, according to a recent survey of corporate workers by Manciniā€¢Duffy.

| Nov 5, 2014

The architects behind George Lucas' planned Chicago museum unveil 'futuristic pyramid'

Preliminary designs for the $300 millionĀ George Lucas Museum of Narrative Art have been unveiled, and it looks like a futuristic, curvy pyramid.

Sponsored | | Nov 5, 2014

How to maximize affordability and sustainability through all-wood podiums

Wood podium construction takes an age-old material and moves it into the 21st century.Ā 

| Nov 4, 2014

Zaha Hadid's first building in Shanghai debuts

Sky SOHO is the third in a trilogy of SOHO China developments designed by Zaha Hadid Architects.

| Nov 4, 2014

HOK breaks ground on colossal research complex for LG in Seoul

Located in Seoulā€™s Magok District, the LG Science Park provides facilities to support innovative research and industrial prototyping.Ā HOK designed phase one of the master plan and six of the laboratory and office buildings.

| Nov 3, 2014

IIT names winners of inaugural Mies Crown Hall Americas Prize

Herzog & de Meuron's iconic 1111 Lincoln Road parking garage in Miami Beach, Fla., is one of two winners of the $50,000 architectural prize.

| Nov 3, 2014

Cairo's ultra-green mixed-use development will be topped with flowing solar canopy

The solar canopy will shade green rooftop terraces and sky villas atop the nine-story structure.

| Nov 2, 2014

Top 10 LEED lessons learned from a green building veteran

M+W Group's David Gibney offers his top lessons learned from coordinating dozens of large LEED projects during the past 13 years.

| Oct 31, 2014

Dubai plans worldā€™s next tallest towers

Emaar Properties has unveiled plans for a new project containing two towers that will top the charts in height, making them the worldā€™s tallest towers once completed.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Ā